TIMELINE

Duration CHART OF DAY
Activities
Number Of Day Starting Date Ending Date 30‐Oct month 29‐Nov 30‐Nov 1‐Dec 2‐Dec 3‐Dec 4‐Dec 5‐Dec 6‐Dec 7‐Dec 8‐Dec 9‐Dec 10‐Dec 11‐Dec 12‐Dec 13‐Dec 14‐Dec 15‐Dec 16‐Dec 17‐Dec 18‐Dec
Procurement 30 30‐Oct‐17 29‐Nov‐17 <‐‐‐‐‐‐‐‐‐‐‐‐>

Access Road Repairing + Mob Demob 17 30‐Nov‐17 16‐Dec‐17


Mob Excavator, Buldozer and Compactor 1 30‐Nov‐17 30‐Nov‐17
Operation Excavator, Buldozer, Compactor 15 01‐Dec‐17 16‐Dec‐17
Demob Excavator and Buldozer 1 16‐Dec‐17 16‐Dec‐17
Compactor Rental + Mob Demob 12 30‐Nov‐17 11‐Dec‐17
Mob Compactor 1 30‐Nov‐17 30‐Nov‐17
Operation Compactor 10 01‐Dec‐17 11‐Dec‐17
Demob Compactor 1 11‐Dec‐17 11‐Dec‐17

Operation + Mob Demob 16 02‐Dec‐17 17‐Dec‐17


Mob Crane 1 02‐Dec‐17 02‐Dec‐17
Operation Crane 14 03‐Dec‐17 17‐Dec‐17
Demob Crane 1 17‐Dec‐17 17‐Dec‐17

Flushing and Clean Up + Mob Demob 6 02‐Dec‐17 07‐Dec‐17


Mob Mud Pump 1 02‐Dec‐17 02‐Dec‐17
Operation Mud Pump 4 03‐Dec‐17 07‐Dec‐17
Demob Mud Pump 1 07‐Dec‐17 07‐Dec‐17

Radial Jetting + Mob Demob 13 07‐Dec‐17 19‐Dec‐17


Mob Mud Pump 1 07‐Dec‐17 07‐Dec‐17
Operation Mud Pump 10 08‐Dec‐17 18‐Dec‐17
Demob Mud Pump 1 18‐Dec‐17 19‐Dec‐17