DAILY FIELD REPORT FORM

Contractor PROJECT NAME: ____________________________________ Report No. : ___________________________


___________________________________________________ Area : ___________________________
PT. XYZ ___________________________________________________ Day/ Date : ___________________________
Contract No:________________________________________ Work Hour : ___________________________
Page : ___________________________

MANPOWER Qty TOTAL CONSTRUCTION EQUIPMENT Qty TOTAL


WORK HOUR EQUIPMENT HOUR

Indirect :
1 Planner & Project Controller Site 1 9 1 Survey Tools and Equipment 1 9
2 Surveyor 1 9 2 Chipping Tools 1 9
3 Field Enginer 1 9 3 Welding Machine 1 9
4 Safety Inspector 1 9 4 Boom Truck cap. 1 Ton 1 9
5 Mechanic/ HE Coordinator 1 9
6 Security 1 9

Direct :
1 Chainman 1 9
2 Foco Truck Operator 1 9
3 Helper 1 9
4 Rigger 1 9
5 Foreman Fitter 1 9
6 Crane Operator 1 9
7 Millw right 2 18

TOTAL 14 126 TOTAL 4 36


SOCIAL
WEATHER Bright Rain Bad Normal Time Loss
OBSTACLES
07.00-09.00 x 07.00-09.00 x
09.00-11.00 x 09.00-11.00 x
11.00-13.00 x 11.00-13.00 x
13.00-15.00 x 13.00-15.00 x
15.00-17.00 x 15.00-17.00 x
Total Time Loss 0 Total Time Loss 0
TODAY ACTVITIES

1 CONTINUE CHECKING DISTANCE EACH OF ANCHOR BOLT & ELEVATION FDN


2 CHIPPING FDN BOOSTER COMPRESSOR SCRUBBER V-18-102 A/ B
3 AS BUILT FDN BOOSTER COMPRESSOR K-18-131 C
4 PADDING INSTALLATION FDN PRESSURE VESSEL DRUM V-18- 102 A/B
BOOSTER COMPRESSOR SCRUBBER V-18-102 A/ B
5 PREPARATION FOR CRANE 45 T INSPECTION
6 SAFETY INDUCTION FOR ADDITIONAL EMPLOYEES
7 AS BUILT FDN DIESEL STORAGE TANK T-18-715

OBSTACLES/ PROBLEM

TITLE GENERAL SITE MANAGER DAY/ DATE :


CONTRACTOR PIC

TITLE DAY/ DATE