SSG-NG01012401-869393-F07-00047 - R01-MDS For Ogbotobo CFA Pile Installation & Testing - RV - 02 - 19.03.16 PDF
SSG-NG01012401-869393-F07-00047 - R01-MDS For Ogbotobo CFA Pile Installation & Testing - RV - 02 - 19.03.16 PDF
Nigeria
Classification Status:
Restricted
SSG-NG01012401_869393-F07-00047
C- REJECTED
Proprietary Information: This document contains proprietary information and may not be partly or wholly reproduced without prior
written permission from Shell Petroleum Development Company
Lawal L.O
02 19-March-2016 Issue for Approval Funke Ige Okosun Allison
Contractor:
Revision Philosophy
Supplier Document shall be revised in accordance with the Document Numbering Procedure SSG-
NG01012401-GEN-JA-6017-00001.
Revision History
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
CONTENTS
ITEM D E S C R I PT I O N
1.0 R ef er e nces an d C o de
2.0 Sc op e
3.0 I nt r oduc ti o n
4.0 C ons t r uc ti on s e qu enc e
5.0 Qual i ty
6.0 Saf et y
A ppe ndic es
Appe ndi x A - WORK SCHEDULE
A p p e n d i x B - M A I N E Q U I P M E N T D AT A S H H E T
A p p e n d i x C- Q A / Q C DO C U M E N T A T I ON
A ppe ndi x D - SKET C HE S OF SLT KE NT E L E DG E SY SY TE M
A p p e n d i x E - C A L I B E R AT I O N C E R T I F I C T E S O F T E S T E Q U I P M E N T
A ppe ndi x F - JH A
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
1.0 R E F E R E N C E S A N D R E L EV A N T D O C U M E N T S
2.0 ICE Specification for Piling and Embedded Retaining Walls. Thomas Telford, London,
2007 (Section B13 Static Load Testing of piles
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
[Type here]
2.0 SC OPE
T h i s d o c u m e n t d e s c r i b e s t h e p r o c e d u r e s a n d m e t h o d o f w o r k f o r t h e i n s t a l l a-
t i o n o f a s e ri e s o f CF A p i l e s ( W o r k i ng a n d T e s t ) t o s u p po r t s t r u c t u re s o f f ac i l it i e s
b e i n g i n s t a ll e d b y S C N L a t t h e O g b o t o b o F l o w s t a t i o n .
P r i o r t o i n s t a l l a t i o n o f t h e w o r k i n g p i l e s, t r i a l p i l e s s h a l l b e i n s t a l l e d a n d t e s t e d t o
2 .5 * D esign capac ity to pro v ide in fo rm atio n pile capac ity .
Inst al lat io n o f t he t ri al pile s also e v alu at e co nst ruc t io n su i t ab il it y o f co nst ruc t io n
m e t ho do l o gy . Aft e r ins t allat io n o f t he w o rk ing pi le s, se le c t e d pile s sh all be t e st e d
to 1 .5 *design ca pacity to co nfirm practica bil it y o f use o f the piles to wo rking lo ad
alre a dy k no w n.
T his do cum e nt de scr ib es t he he alt h, safe t y , e nv iro n m e nt al an d q uali ty co nside r
atio ns asso ciat ed with the wo rks.
T he im m e diat e surro undin gs co nsist o f t he w a te rco urse k no w n as O gbo to bo Co ncre te
Barge ( O CG) slo t a nd OC B i t se lf w it h ac co m m odat io n ho use bo at s a s sho w n i n t he
pict ure be lo w .
T he pur po se o f t he t e st pile s is t o ach iev e t he fo llo w ing:
T o pro v e t hat t he se le ct e d pili ng m e t ho d is pract ical i n t he giv e n gro und
co nditio ns.
T o use t he info rm at io n gaine d fro m inst al lat io n and t e st ing o f t he se pile s i n
t he de s ign o f a ny pe rm ane nt p ile s.
T o m it i g at e d e s i g n ri s k a n d de s i g n p e r io d .
The results ca n be v iewed as add itio nal info rm atio n to that already gained fro m the
sit e inv e st igat io n ( SI) car rie d o ut duri ng 20 10 at t his sit e .
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
T h e a r e a o f t h e s i t e w h e r e t h e C F A p i l e s a r e t o b e i n s t a l l e d i s s h o w n i n r e f e r e n c e 1 . 1.
P art o f t he pile s are t o suppo rt pipe rack s and part is t o su ppo rt t he je t t y .
T h e ge o t e c h n i c a l i n v e s t i g a t i o n t h a t w a s c a r r i e d o u t h a s g i v e n s u f f i c i e nt b o r e ho l e
info rm at io n w hich ne cess it at e d t he o rigina l pre cast co nc ret e pile de s ign o f
4 4 0m m x 440m m x 40 m d i m e n s io n . Ho w e v e r , th e ri s k o f d a m a ge to e x is t i n g i n s t al l at io n
s w it h t he use o f im pact hamm e r t o inst all t he pile s aro und t he OCB, CFA pi le s o f diam
e t e r and de pt h 60 0m m and 26 m re spe ct iv e ly hav e be e n ado pte d fo r pile s ne ar t he OCB.
T h e t r i a l p i l e s s h a l l b e o f t h e s a m e s i z e, e x p e c t e d d e p t h a n d s p e c i f i c a t i o n a s t h e w o r k i n g p i l e s a s
d e s i g n e d (See Reference 1.2)
T h e C F A p i l e s h a v e b e e n d e s i g n e d t o b e o f 6 0 0 mm d i a m e t e r t o a d e p t h o f 2 6 m o f m a x i m u m 5 m
f r e e s ta n d i n g a b o v e r i v e r b e d. T h e p i l e s w i l l b e r e i n f o r c e d w i t h r i b b e d b a r s t o a d e p t h o f a b o u t
1 1m with 1m of the rebar dowelling into the pile cap for anchorage. For the pile to be constructed above water
head, a conductor steel pipe of 700 mm diameter and thickness of 10mm minimum shall first be installed by
predrilling or pre augering or vibro method to a reasonable depth below the river bed adequate for stability.
S ee f u l l d e t a i l s p a s t e d a b o v e a n d a s d e p i c t e d i n R e f e r e n c e 1 . 1
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
A l l t h e p i l e s s h a l l b e t e s t e d f o r i n t e g r i t y u s i n g l o w s t r a i n i m p a c t t e s t i n g. 2 Trial piles shall be installed
and tested with Static Load to v a l i d a t e t h e d e s i g n o f t h e p e r m a n e n t p i l e s, as well as its constructability
with the method chosen. In the same way, after installing every other piles, few selected working piles will be
t e s t e d f o r c a p a c i t y.
The system for to be used for Static Load test system in this regard shall be the K e n t l e d g e L o a d i n g s y s t e m.
This system j u s t a s t h e r e a c t i o n p i l e s y s t e m e x e r t t h e n e c e s s a r y t e s t load o n t h e t e s t p i l e i n
s a m e o n t r o l l e d m a n n e r a n d i n a c c o r d a n c e w i t h t h e A S T M o r a n y o t h e r approved s p e c i f i c a t i o n o n
P ile Lo ad Testin g.
T h e e x a c t positions and details of the piles to be used as trial piles shall be communicated to the company for
approval before it is undertaken. While the working pile position is already issued as contained in reference 1.1.
Please note that selected working piles to be tested shall be of same dimensions and properties as the designed
pile, but the choice of being selected for test in this case shall be based on constraints or challenges that may
be encountered during installations. Piles may also be selected for test for reason as evaluation against a
particular capacity or events or conditions.
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
3.0 C ON ST R UC TI ON SE Q U EN C E
3.1. I n t r o d u c t i o n
3.2. S i t e Se t - Up
D e t aile d risk asse ssm e nt s w ill be at t ache d to t his do cum e nt fo r co nst ruct io n
iss ue an d sho uld be m onit o re d and u pdat e d dur in g t he se w o rk s.
A d a i l y v a l i d s i g n e d P e r m i t t o W o r k (P T W) f r o m t h e c l i e n t i s r e q u i r e d b e f o r e a n y w o r k c a n
commence.
A ll p e r s o n n e l w i l l h a v e a t t e n d e d t h e m a n d a t o r y C o n s t r u c t i o n s i t e i n d u c t i o n
and w il l hav e be e n brie fe d o n t he co nte nt s o f t he risk asse s sm e nt s and J HA
re lev ant t o t he ir o pe ra tio ns.
a. 1 0 0 0 M T R a m p e d b a r g e ( f o r t r a n s p o r t a t i o n o f e q u i p m e n t a n d m a t e r i a l s ) a n d
5 0 0 M T Spud barge ( fo r pili ng) w il l be de liv e red t o sit e by riv e r, t o w ed o r pushe d
with 250hp tug
b. 4 5 T o n C r a w l e r c r a n e d e l i v e r e d t o s i t e u s i n g t h e b a r g e
c. D e l i v e r S o i l m e c C M 7 0 / C M 4 8 C F A , V i b r o h a m m e r , p o w e r p a c k , a n d 3 6 0
Ex cav ato r using t he barge .
d. D e l i v e r a l l c o n c r e t e m a t e r i a l s a n d c o n c r e t e p u m p t o s i t e .
e. D e l i v e r p a y l o a d e r, t r a n s i t m i x e r s u s i n g t h e b a r g e .
f. Deliver Concrete Batch Plant using the barge
g. L i f t a n d l o a d C o n d u c t o r c a s i n g , V i b r o h a m m e r a n d P o w e r p a c k i n t o t h e s p u d b a r
ge usin g t he craw le r crane .
h. L o a d r e b a r , 2 s t e e l p i l i n g g a t e s , v a r i o u s o t h e r e q u i p m e n t a n d s t e e l s e c t i o n a n d
ne at ly st acke d u nt o t he barge .
i. L i f t a n d l o a d c o u n t e r c o n c r e t e w e i g h t s s t a c k e d e v e n l y f o r b a r g e b a l a n c i n g i n t o t h e
spu d ba rge us i ng t he c raw le r c rane ,
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
j. L o ad t he CFA Ri g unt o t he spud bar ge .
k. P u s h t h e s p u d b a r g e w i t h t h e t u g / w o r k b o a t t o f i r s t p i l e p o s i t i o n .
l. A c t i v a t e a n d l a u n c h t h e 1 0 m l o n g s p u d - p o l e s i n t o t h e r i v e r b e d f o r a n c h o r a g e a n d
sta bility
a. P o s i t i o n o f p i l i n g l o c a t i o n i s w o r k e d o u t u s i n g m a r i n e s u r v e y s y s t e m ( S a y
D GP S sy st em ) using at le ast 2 k no w n po int s o n sho re . Aft e r t r ac in g po sit io n o f
p i l i n g lo c a t io n p i l i n g wo rk i n g p l at fo rm ( s p u d b a r g e ) i s s h i f te d a n d s e t a t
that lo catio n.
b. P o s i t i o n a n d a n c h o r t h e s p u d b a r g e w i t h t h e a n c h o r p i l l a r s . c.
Fix au ge r unto t he C FA Rig.
d. C o n n e c t v i b r o h a m m e r t o t h e p o w e r p a c k
e. Position steel gate beams on the side of the barge to coincide into set pile position.
f. P i t c h f i r s t s t e e l p i l e ( c o n d u c t o r P i l e ) i n t o g a t e , p o s i t i o n a n d m a i n t a i n u p r i g h t
po sit io n
g. L i f t v i b r o - h a m m e r o n t o t o p o f s t e e l p i l e a n d d r i v e p i l e d o w n t o 5 m e t er s i n t o r i v e r
be d o r e m be d int o riv e r be d suff icie nt ly t o e nsure no dri ft ing o f bo tt o m w hile
dr illi ng a nd co ncr eting.
h. S t r i p g a t e d o w n a n d m o v e i n t h e C F A R i g t o p o s i t i o n f o r d r i l l i n g
i. As rig is po s it io n ing, t he co nc re te w e ight blo c ks is arra nge d w it h t he crane to
alw ay s bala nce t he ba r ge .
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
j. St art D rill ing to 26 .0m de pt h
k. C o n n e c t t h e c o n c r e t e p i p e l i n e t o r i g a n d p u m p ( C o n c r e t e p u m p s h a l l b e o n l a n d
no t barge ) .
l. A t p i l e d e p t h , t h e a u g e r i s l i f t e d 3 0 - 5 0 c m a n d c o n c r e t i n g b e g i n s t i l l a u g e r i s
co m ple t e ly o ut o f pile
m. R e b a r i s p i t c h e d w i t h r i g s e r v i c e w i r e
n. R e b a r i s p o s i t i o n e d c e n t r a l l y i n t o t h e p i p e o.
Rebar is i ns tal led to 12m .
p. T h e s t e e l c o l u m n i s p i t c h e d .
q. T h e c o l u m n i s i n s t a l l e d i n s i d e t h e r e b a r t o 5 m d e p t h r.
Repeat a-q fo r every pile
s. T h e p h o t o b e l o w s h o w s e x a m p l e s o f p i l i n g f r o m a s p u d b a r g e , s i m i l a r t o b e i n g
pro po se d fo r t he wo rks. Furt he r pho t o gra p hs and a specif icat io n can be fo und in
A ppe n dix 2 .
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
3.5 C onc r et e Wor k
Co nnect pipe line bet w e e n rig a nd co ncre t e p u m p
CONCRET E P UMP AND D EL IVERY T RUCK S SHAL L AL L BE ON T HE L AND NEAR P IL E P OSIT ION
A ND P UMP ED INT O P IL E.
Ow ing to t he pre se nce o f t he w at e rco urse , special pre ca ut io ns m ust be t ak e n t o
pre v e nt po llut io n o f t hat w ate rco urse in acco rdance w it h t he E nv iro nm e nt al
P o lic y o f SP D C and E nv iro nm e nt al P ro t e c t io n Ac t o f Nige ria .
These will inc lu de:
• A de sig nat e d, bonde d p lant re f ue lin g are a s it u at e d w e ll aw ay fro m t he st re am .
• Use o f bio de gra dable hy draul ic fluid i n t he piling ri g, t e st ri g a n d any o t he r
m ac h i n e ry ( e . g . e x c a v at o r , p um p a n d t ra n s i t m ix e r ) .
• All p lant m ust be inspe ct e d daily fo r f lui d le ak s and m ust no t be use d unt il any
leak is rectif ied.
• N o p l a n t , m a t e r i a l s , l a b o r o r d e b r i s m a y b e a l l o w e d t o e n t e r t h e w a t er .
• E m e r ge n c y s p i ll k i t s m us t be m a de a v a i la b l e a n d m ai n t ai n e d a t a l l t im e s .
• A le ak -pro o f sk ip fo r w ast e co ncre te and co nc re t e w ash -o ut is t o be pro v ide d.
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
All sit e pe r so nne l w ill be brie fe d o n t he e nv iro nm e nt al em e rgency re spo nse
pro ce dure . A flo w chart de p ict in g t he E VOM EC Env iro nm e nt al Incide nt
Re spo nse P ro ce dure is sho w n o n t he fo llo w ing page .
Whe re t he co ncre t e place m e nt m ay displace gro undw ate r to t he sur f ace , co ncre t ing s hall
t e m p o r a r i l y s t o p a t 1 m a b o v e r i v e r b e d , t h i s w a t e r w i l l t h e n b e c o n t a i n e d w i t h i n c o n d u c-
t o r casi n g to prev e nt dire ct r un - o ff int o t he st re am and allo w e d t o se t tle . T he re aft e r,
co nc re te is co m ple te d in a co nt ro lle d m anne r w it ho ut t he auge r in t he ho le . Ho w e v e r, t he
qua nt it y o f w at e r di splace d is no t lik e ly to be large a nd sho uld dispe rse quick ly .
QA/QC Officers (3 no.) Ensures quality controls in piling, concrete batching and
concreting
Surveyor (1 no.) Set out piling points and marks out and monitor pile testing
activities
Piling Rig Operator (1 no.) Operates piling rigs and head of piling crew
Crane Operator (1 nos) operates the crane and co-ordinates all lifting activities
Pay loader Operator (1 nos) operates the pay loader, assist in concrete materials
loading/offloading
Truck drivers (2 nos.) Drives concrete trucks from batch plant to delivery points
Pump operator (1 nos) operates the concrete pumps and controls concrete placement
Marine Captain (1 No.) co-ordinates and controls all marine activities; material and
equipment transportations, shifting and anchoring of spud barge
Marine deckhand/ crew (5 nos.) assists the captain. Maintains the marine equipment
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
3.7 P i li ng Moni t or i ng
As t he t e st pil ing m e t ho ds w ill be ide nt ical t o t ho se curre nt ly pla nne d fo r t he
pe rm ane nt pi le s ( su bject to v alidat io n o f t e st re sult s) , t he fo l lo w ing
e nv iro nm e nt al m o nito ring w i ll be car rie d o ut dur ing inst a llat io n of t e st pile s.
• No is e m o nit o ring – w it h re s pe c t to t he m o st s e ns it iv e re ce pt o rs i.e . t he O C B.
• Vibrat io n – As e x pla ine d in prev io us pa ge s, v ibrat io n l ev e ls are
g e ne r a l ly lo w , b u t a re d e pe n d e n t u po n t h e t y p e o f so il o r ro c k .
St udie s o f v i brat io n c ase histo ry dat a s ugge st t hat in ge ne r al t he v ibrat io n
le v e ls fro m bo re d pili ng are lo w and e v e n t ho ugh t hey are a bo v e t he
t h r e s h o l d o f h u m a n p e r c e p t i o n ( P e a k P a r t i c l e V e l o c i t y ( P P V ) o f 0 .1 4 m m / s ) ,
t h e y a r e n o t e xp e c t e d t o c a u s e a p r o b l e m . T h e v i b r a t i o n s f r o m r o t a r y p i l i n g a r e
n o t p re d ic t e d t o h av e an y ad v e rs e ( i . e . , po t e n t i a l l y d am a g i n g ) e f f e c t o n b u r ie d s e r
v i c e s o r o t h e r s t r u c t u r e s n e a r b y . In any case vibration monitoring shall be carried out as
the operation is being carried out.
• Gro und gas – T he m o nit o ring o f co nce nt rat io n and o r flo w s o f gro und gas
w ill be car r ie d o ut .
Co ncret e and re i nfo rce m e nt w ill be su ppl ie d t o t he pro je ct spe cifica t io n and appro v e d
m i x e d d e s i g n verified with trial mixes with accepted results. Reinforcement shall have spacers for
eccentricity control.
Depths
T he de sig ne d de pt h is 26 m . Auge r le ngt h is v e rifia ble . Je an L u it z T ara lo g in t he r ig
also m o nito rs pile de pt h bo rin g t o re qui re d de pt h.
Boring Tools
Bo ring t o o ls ( au ge r) ar e av ailable to co pe w it h dif fe re nt st rat a . T he r ig is a lso
e quip pe d w it h se nso rs t hat m e asure s t he to rque and dril lin g rate w it h re spe ct t o e v
e ry st rat a e nco unt e re d.
Co ncret e
T h e r e q u i r e d c o n c r e t e g r a d e i s C 3 5 / 4 5 w i t h s l u m p r a n g i n g f r o m 1 2 5 m m to 2 0 0 m m
Slum p shall be t ake n a nd re c o rde d t o co nfo rm t o range and co nc ret e cube sam ple
also co lle cte d fo r c rus hing a nd co m pariso n o f 2 8 day s re sult s w it h designe d co ncret e
grade.
Before the concrete is accepted to use, Trial mix(es) shall be carried out and results adjudged
satisfactory.
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
3.8 E nvi r onm ent al Im pac t s and Pr op os ed Mi t i g at i on
Vibrat io n le v e ls de pe nd v e ry m uch upo n t he nat ure o f t he su bso ils, t he dist a nce
fro m st ruc t ure s e t c . and t he re fo re t he re are no ge ne ric f igu re s fo r indiv id ual rigs .
Ho w e v e r, v ibrat io n dat a co lle ct e d from t he m any and v ar io us lo cat io ns and
s i t u a t i o n s f o r t h e p r o p o s e d r i g t y p e g i v e s c o n f i d e n c e t h a t v i b r a t i o n l e v e l s w i l l b e l ow.
Notwithstanding, vibration monitoring equipment shall be installed on the site during piling to
ensue that thresholds are not exceeded by any means.
No ise o ut put fro m t he pili ng o pe rat io ns can be div ide d i nt o t hre e m ain act iv it ie s:
• Handlin g crane unde r lo ad
• Bo ring
• Shak in g spo il o f f t he auge r
P o llut io n fro m Co ncre te spo ils sha ll be m in im ize d as high lig ht e d i n Se ct io n 3 .5
above.
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
4.0 T E STI N G
Be fo re any t e st ing ca n co m me nce all arisi ng f ro m auge ring a nd a ny o the r m ate rials
such a s t h e e a r t h b u n d a n d s p i l l e d c o n c r e t e m u s t b e c l e a r e d a w a y , t h e p i l i n g h e a d
trimm ed to a flat, lev el surface.
4.1 St at i c L oad T es t
T he pili ng i s int e nde d fo r de sig n dev e lo pm e nt / v alidat io n a nd t he
m agnit u de o f t he t est lo ads w ill be se t at t he D e sign Ve rif icat io n Lo ad (D VL )
w hic h is t he 2 .5 t i m e s de signe d lo ad fo r t r ial pile an d 1 .5 t im e s de si gne d lo a d fo r
wo rking pi les.
L o ad t e st ing shall be carrie d o ut i n acco rda nce w it h t he ASTM St a ndard and
Inst it ut io n o f Civ il E ngine e rs ( ICE) S pe cific at ion fo r P ilin g an d Em be d de d Ret ain ing
Walls.
T he t e st asse m blage as sho w n in t he sc he m at ic o f Appe n dix D w ill be ere ct e d usin g a
m o bile o r crawler crane
P ho t o graph be lo w sho w s a ty pical pile t e st in g assem blage .
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
St at ic lo ad t e st s w il l be carrie d o ut fo r co m pre ssio n, an d t he lo ad a pp lie d us ing
K e nt le dge de a d w e ight fo r appl ic at io n o f t he re ac t io n lo ads. T he a rrange m e nt
o f t he K e n t le dge a nd the t e st lo ad re qui rem e nt s m e an t hat lo ads a re appl ie d w it h
a jack sequent ially .
T h e d e f l e c t i o n s a n d l o a d s w i l l b e m o n i t o r e d u s i n g l o a d c e l l s a n d t h e s e r e s u l t s will
b e a n al y ze d a n d i n t e rp r e t e d fo r t he p u r po se o f v a l i da t i n g/ m o d i fy in g t h e
pile des ign .
4.1.1 S e q u e n c e o f a c t i v i t i e s f o r S t a t i c L o a d T e s t i n g ( S L T ) .
The test shall begin with the arrangement of the set up as shown in Appendix D.
Set- Up Arrangements
A bearing 800mm x 800mm x 200mm cap (ICE Document Section B.15.9 Reaction system) shall be
constructed on the selected pile to be tested for the jack to be placed on level plane and also to
house the dowel bars which shall be cranked to remain within it. (The bar shall later be straightened
after the test and the support broken. Please note that it is only when the support has cured or cube
strength ascertained to be equal or greater than 25N/mm2 strength that the test can be carried out).
Blocks/wood support crib for the test beam shall be placed a distance of between 2.5m to 3.0m
center to center from test pile.
The 4 Nos load block frame is them placed 2m apart on which the load blocks are arranged in
layers adequate as 110% Test Load as shown in Attachment 1.
Next is the jack with its accessories including the load cell are placed centered on the test pile and test
beam. There shall be minimum 10mm thick bearing plate between the jack and the test pile support
and also between the load cell top and bottom of test beam
According to Section 7.2.2 of ASTM a minimum of two displacement indicators shall be placed on the
reference beams to bear on the pile top at axisymmetric points equidistant from the center of the test
pile, or pile cap, with stems parallel to the longitudinal axis of the pile.
The two parallel reference beams shall be oriented, one on each side of the pile to be tested, in a
direction that permits placing their supports as far as feasible from the other supports.
Also survey level instrument shall be used to check if Kentledge system displaces vertically.
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
Loading Procedure
Maximum Allowable Test load for working piles test load shall be 150% Allowable pile load.
Loading
Working pile, According to ASTM D 1143 load procedure C section 8.1.3), unless failure occurs
first, shall be loaded to a maximum of 150 % of the anticipated design load, applying the load in
increments of 25 % of the design load. Each load increment shall be maintained until the rate of axial
movement does not exceed 0.25 mm (0.01 in) per hour, with a minimum time adequate to verify this
movement rate based on the accuracy of the movement indicator readings, and with a maximum of 2
hr. After applying the maximum load and reaching an overall test duration of at least 12 hr. Unloading
shall begin when the axial movement measured over a period of 1 hr does not exceed 0.25 mm (0.01
in); otherwise the maximum load shall be allowed to remain on the pile or pile group for 24 hrs.
For trial/test pile, up to 200% of allowable loads shall be applied in incremental of 25% and the pile
movement observed with the installed gauges until the rate of axial movement does not exceed
0.25 mm or per hour. However, if pile movement exceed this limit, the observation of its movement
shall be undertaken for every loading for a maximum of 2 hours.
Unloading
After applying the maximum load and reaching an overall test duration of at least 12 hr or when the
axial movement measured over a period of 1 hr does not exceed 0.25 mm (0.01 in) unloading shall begin
; otherwise the maximum test load shall be allowed to remain for a minimum period of
24 hours. The unloading shall also be done in decrements of 25 % of the maximum test load with 1 hr
between decrements.
After the load has been applied and removed in accordance with ASTM 8.1.3 and as described above,
the trial pile shall be reloaded to 200% maintained load in increments of 50 % of the pile or pile group
design load, allowing 20 minutes between load increments. Then the additional load that will take
the loading to 250% allowable load shall be applied in increments of 10 % of the design load for the
pile or pile group until reaching the maximum required load (250%) or failure, allowing 20 min
between load increments.
If failure occurs continue jacking the pile until the settlement equals 10 % of the pile diameter or
width. If failure does not occur, hold the full load for 2 hr and then remove the load in four equal
decrements, allowing 20 min between decrements.
See below, the loading cycle table for the trial and working piles foe each of the pile types
Failure
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
Failure load/ maximum load possible during loading/reloading is defined as the load that makes total
axial movement of pile equals 10 % the pile diameter or width. This load then becomes the Ultimate
Capacity of the Pile.
See below, the loading cycle table each for the working piles and trial/test pile.
WORKING PILES
ALLOWABLE PILE
CAPACITY= 600 KN
MAXIMUM STATIC TEST
LOAD= 900 KN
LOAD % LOAD PRESSURE
DURATION MEASUREMENT INTERVALS
STEPS LOAD (KN) (bar)
1 0.0% 0 - 2 hours* 5, 10, 20, 40, 60, 80, 100, 120
2 25.0% 150 33.16 2 hours* 5, 10, 20, 40, 60, 80, 100, 120
3 50.0% 300 66.31 2 hours* 5, 10, 20, 40, 60, 80, 100, 120
4 75.0% 450 99.47 2 hours* 5, 10, 20, 40, 60, 80, 100, 120
5 100.0% 600 132.63 2 hours* 5, 10, 20, 40, 60, 80, 100, 120
6 125.0% 750 165.78 2 hours* 5, 10, 20, 40, 60, 80, 100, 120
5, 10, 20, 40, 60, 80, 100, 120, 180, 240,
300, 360, 420, 480, 540, 600, 660, 720, 780,
24 840, 900, 960, 1020, 1080, 1140, 1200,
7 150.0% 900 198.94
hours** 1260, 1320, 1380, 1440, 1500, 1560, 1620,
1680, 1740, 1800, 1860, 1920, 1980, 2040,
2100, 2160, 2220.
8 125.0% 675 149.20 1 hour 5, 10, 20, 40, 60
9 100.0% 450 99.47 1 hour 5, 10, 20, 40, 60
10 75.0% 300 66.31 1 hour 5, 10, 20, 40, 60
11 50.0% 225 49.73 1 hour 5, 10, 20, 40, 60
12 25.0 150 33.16 1 hour 5, 10, 20, 40, 60
5, 10, 20, 40, 60, 80, 100, 120, 180, 240,
12 300, 360, 420, 480, 540, 600, 660, 720, 780,
12 0.0% 0 -
hours*** 840, 900, 960, 1020, 1080, 1140, 1200,
1260, 1320, 1380, 1440
* Load shall be maintained for maximum 2 hour except if pile settlement is less than 0.25mm/hour
** Load Shall be maintained for maximum 24 hours is pile settlement is greater than
0.25mm/hour
*** Load Shall be maintained for maximum 12 hours is pile settlement is greater than
0.25mm/hour
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
TRIAL/TEST PILES
ALLOWABLE PILE
CAPACITY= 600 KN
MAXIMUM STATIC TEST
LOAD= 1500 KN
LOAD LOAD PRESSURE
% LOAD DURATION MEASUREMENT INTERVALS (min)
STEPS (KN) (bar)
1 0.0% 0 - 2 hours* 5, 10, 20, 40, 60, 80, 100, 120
2 hours*
2 25.0% 150 5, 10, 20, 40, 60, 80, 100, 120
33.16
2 hours*
3 50.0% 300 5, 10, 20, 40, 60, 80, 100, 120
66.31
2 hours*
4 75.0% 450 5, 10, 20, 40, 60, 80, 100, 120
99.47
2 hours*
5 100.0% 600 5, 10, 20, 40, 60, 80, 100, 120
132.63
2 hours*
6 125.0% 750 5, 10, 20, 40, 60, 80, 100, 120
165.78
2 hours*
7 150.0% 900 5, 10, 20, 40, 60, 80, 100, 120
198.94
2 hours*
8 175.0% 1050 5, 10, 20, 40, 60, 80, 100, 120
232.10
2 hours*
9 200.0% 1200 5, 10, 20, 40, 60, 80, 100, 120
265.25
10 175.0% 1050 1 hour 5, 10, 20, 40, 60
232.10
1 hour
11 100.0% 600 5, 10, 20, 40, 60
132.63
1 hour
12 50.0% 300 5, 10, 20, 40, 60
66.31
20
13 0.0% 0 - 5, 10, 15 20
minutes
20
14 50.0% 300 5, 10, 15 20
66.31 minutes
20
15 100.0% 600 5, 10, 15 20
132.63 minutes
20
16 150.0% 900 5, 10, 15 20
198.94 minutes
20
17 200.0% 1200 5, 10, 15 20
265.25 minutes
18 210.0% 1260 2 hours* 5, 10, 20, 40, 60, 80, 100, 120
278.51
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
2 hours*
19 220.0% 1320 5, 10, 20, 40, 60, 80, 100, 120
291.78
2 hours*
20 230.0% 1380 5, 10, 20, 40, 60, 80, 100, 120
305.04
2 hours*
21 240.0% 1440 5, 10, 20, 40, 60, 80, 100, 120
318.30
2 hours*
22 250.0% 1500 5, 10, 20, 40, 60, 80, 100, 120
331.56
20
23 187.5% 1125 5, 10, 15 20
248.67 minutes
20
24 125.0% 750 5, 10, 15 20
165.78 minutes
20
25 62.5% 375 5, 10, 15 20
82.89 minutes
* Load shall be maintained for maximum 2 hour except if pile settlement is less than 0.25mm/hour
** Load shall be maintained for maximum 12 hours is pile settlement is greater than
0.25mm/hour
Test Officers (2 Nos/shift) Assist the Engineer in test setting up and data acquisition
Safety Officer (1 No. /shift): Ensuring Compliance to Safety Procedures, Risk assessment and
JHA
QA/QC Officer (1 No. /shift): Documents Test records and Ensuring Compliance to Test
Standard and procedure, valid calibration of equipment.
First Aider (1 No. /shift): Carry out first aid activity in case of injury and coordination of
emergency operation during testing
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
Crane Operator (1 no.): Lift, Place and operate the drop weight system
Excavator Operator (1 No.) To excavate test pile area to give room for attachment of gauges
Fitter/Technician (1 no.): To prepare attachment surface, drill holes and fix gauges
There are the minimum equipment shall be needed to complete the Static Loading Test
Kentledge System
Concrete block of weight (1.5 to 3 tons), used as test load, with at least 10 % greater than the
maximum anticipated test load.
Hydraulic Jacks
Single acting Hydraulic Jacks with Hydraulic Pump and Pressure measurement tools all calibrated.
Bearing Plates/Stiffeners
Steel bearing plates are needed to spread the load from the outer perimeter of the jack(s), or the
bearing surface of beams or boxes, to bear on the surface of the test pile or pile cap, also to
spread the load between the jack(s), load cells, and hemispherical bearings, and to spread the load to
the test beam(s), test pile, or pile cap. Bearing plates shall extend the full flange width of steel beams
and the complete top area of piles, or as specified by the Engineer, so as to provide full bearing and
distribution of the load.
Dial gauges
Minimum two dial gauges shall be provided to monitor the pile’s head movements by mounting
between the pile head and reference beams. The micrometer has a range of 0‐35 or 0-50 mm and an
accuracy of 0.01 mm.
Reference Beam
Two reference beams (Steel channel or angle) will be cross‐connected and laid on support, firmly
embedded in ground.
The beams shall act as load bearing and also the support the load blocks.
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
Survey Level Instrument
Other Equipment
Medium Duty Crane, Tow Trailers, Grinding Machine with Steel and Concrete grinders, Drilling
Machine and Tools, Welding Machine, chisel, hammer, hydraulic oil etc.
Result Presentation
This involves testing all CFA, with the Pulse Echo Method described above to evaluate pile for
defects such as
Inclusions in pile concrete (soil or any other material) especially for CFA piles
Change in pile profile
Discontinuity and non-uniformity in pile concrete already placed
CATEGORY B: No indication of a possible defect but no toe reflection for long piles, low strain
waves often do not have sufficient energy to return to the shaft top after reflection
from toe. This condition typically occurs when the pile length is more than 30 to 50
times the nominal shaft diameter, but it is dependent on the amount of shaft
friction present, when shaft fall into this category, pile integrity assessment is only
possible along the shaft.
CATEGORY C: Clear indication of serious defect .Here major positive reflection occurs before the toe
and no reflection is evident at the nominal depth.
CATEGORY D: Indication of Possible defect, often toe reflection present. This category includes
piles that show positive velocity reflection but still clear toe reflection
CATEGORY E: Records do not support any conclusion. This includes piles with inconclusive
records due to bad
4.2.1 Procedure
For all piles in this project which are cast-in-place concrete piles or concrete filled pipe piles, the
integrity testing is performed no sooner than 7 days after casting or after concrete strength achieves
at least 75 % of its design strength, whichever occurs earlier. It is ensured that the pile head surface is
accessible, above water, and clean of loose concrete, soil or other foreign materials resulting from
construction. If the pile head is contaminated, sufficient pile section shall be removed to reach sound
concrete: because proper pile top preparation is critical to the successful application of this method, if
a necessary, small area is prepared by a hand grinder to provide a smooth surface for motion sensor
attachment and impact.
The accelerometer must be firmly affixed to the pile top in order to measure the high-frequency
motion of that surface during impact and reflection. For best results, the accelerometer should be
bonded to the pile top. Petroleum jelly works nicely in cold weather. Other adhesive materials such as
plastic clay or bowl sealer wax can also be used.
The motion sensor (Transducer) is placed at or near the pile head using a suitable, or temporary,
thin layer of bonding material (that is, wax, Vaseline, putty etc.) so that it is assured that it
correctly measures the axial pile motion (transducer axis of sensitivity aligned with the pile axis).
The motion sensor is placed generally near the center of the pile. Additional locations should be
considered for piles with diameters greater than 500 mm.
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
The low strain impact is applied to the pile head within a distance of 300 mm from the motion
sensor. If the pile head is not accessible, as when already integral with the structure, the sensor(s)
may be attached to the side of the pile.
The signals from the motion sensor are conveyed to the Pile Integrity Tester (PIT) for
recording, reducing, and displaying data as a function of time. The PIT includes a graphic
display of velocity, and a data storage capability for retrieving records for further analysis.
Measurement from several impacts is recorded. Suitable records of at least three impacts are
averaged and necessary amplification to the averaged record is applied. The records from the
individual impacts or the averaged record, or both taken as the averaged, amplified record are
then evaluated for integrity.
Test Engineer (1 No.) Operates the equipment, acquire the data and interprets the results.
Test officer (1 no.) Assist in placing transducer, preparation of pile heads
QA/QC (1 no.) Assist in identifying the piles provision of pile installation details.
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
5.0 QUALI TY
Prior to construction the inspector shall have and review the following:
Details of concrete mix design and sampling and testing requirements; and
Reinforcing details and methods for pile top finishing and cutoff levels.
Upon arrival at the jobsite, the inspector shall take the time to thoroughly review the
contractor’s equipment for compliance with the plans and specifications and approved
installation plan.
• Check-in to understand day’s planned work and confirm that party responsible for concrete
sampling is at site.
• Document auger diameter and length, auger pitch, concrete (each truck
immediately when delivered), reinforcing type, and configuration.
• Check calibration concrete volume monitoring equipment, and other
Measurement equipment for which calibration is required. Confirm that monitoring
equipment is set to record at proper depth intervals as required.
• Check equipment condition and tolerances
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
5.3 During Drilling
• Confirm that pile location is within horizontal tolerances and pile plumbness is within the
range specified.
• Confirm plug placed at auger bit tip.
• Confirm the location of the pile to be constructed, so that relevant sub surface
conditions, pile construction requirements (i.e., pile number, embedment depth, cut- off,
and batter, if required) can be quickly and accurately referenced.
• Document auger verticality or specified batter, as applicable. Document cuttings and auger
advance rate.
• Confirm for consistency with conditions disclosed in geotechnical report, pile test report, and
load test report.
• Confirm removal of excessive cuttings/spoil build-up around auger.
• Monitor behavior of the pile and surrounding ground during construction of test pile
foundations. Check for indications of ground subsidence or loss of fluid concrete.
o Document concrete properties (batch time, temperature, additives, and flow) and those
samples that have been obtained for strength testing at the intervals, per project
specifications.
o Document the pile grouting/concreting operation, including immediate start of Placement and
pumping of initial concrete volume and pressure head, and auger withdrawal rates, per approved
installation plan. Confirm (from automated monitoring data and observations) that target
minimum concrete factor is attained along the length of the pile. Confirm for consistency with
reported conditions disclosed in geotechnical report, test pile report, and
load test report.
o Document depth at which concrete return is first observed. Confirm consistency with
conditions disclosed in geotechnical report, test pile report, and load test report.
o Should a discontinuity in grout/concrete return or other questionable conditions be
observed, inform the contractor of the condition and note the conditions observed on pile logs
or data sheets. In some cases, the contractor may re-drill the pile to the full length. Re- drilling
the pile to less than the full length to restart the concreting operation is generally considered
unacceptable.
o Confirm continuous and steady auger pull, with slow positive auger rotation if approved in
the installation plan, and concrete pumping until auger tip comes out of the ground.
Document total volume of grout/concrete pumped, and overall grout/concrete factor.
Obtain pile records from automated monitoring equipment.
o Confirm that the pile top is cleared of any debris or contaminated grout or concrete.
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
5.5 During Reinforcement Placement and Pile Top Finishing
5.6 Post-Installation
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
6.0 HEALTH SAFETY AND ENVIRONMENT MANAGEMENT
6.1 Objectives
The carrying out the Health, Safety and Environment Management is to:
a) Provide a process that achieves no harm.
b) Outline the actions in carrying out the assessment to ensure acceptable HSE
standards and practice.
e) To maintain productivity
6.2.1 On-shore
(b) Gloves shall be worn when handling cables, rods, or any sharp or splintery materials. (c)
A safety hat, coverall and hat shall be worn at all time within site during the test and
survey operations.
(d) There shall be no smoking in the vicinity of on the site especially near the plant area. (e)
The work area shall be kept free of excess tools and equipment which may cause any
obstruction or interruption to the movement of vehicles, plants and personnel on site.
(f) Cables shall be checked at the end of every work day for excessive wear and tear and
should be replaced when necessary.
(g) First aid kit shall be maintained on site to treat breaks in the skin or any other minor
Injuries.
(h) Use of mobile phones, camera and other signal/flash emitting devices shall not be
permitted within plant area
(j) SPDC CSSS Policy shall be maintained all through site operation
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
6.2.2 Off-shore
a) Gloves should be worn when handling cables, rods or any sharp splintery materials. b)
e) The work area should be kept free of excess tools and equipment.
f) First aid kit is to be maintained on site to treat breaks in the skin or any other minor
injuries.
g) When working on water either in a boat or on a barge, float or platform, a life jacket must
always be worn.
h) Adequate anchor and securing lines must always be used and these lines should be
checked from time to time to assure proper tension.
i) Crew members should ensure that their bodies are clear of all lines before dropping
anchor and anchor lines should never be straddled.
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
A l l p e r s o n n e l w i l l b e f u ll y b r ie f e d o n t he s a fe m e t ho d o f w o rk , v i a t he u s e o f a s i t e s
pe cific in duct io n and ope rat io n Spe ci fic M e t ho d and Risk T raini ng
(SM ART) brief ings, pr ior to the wo rks be ing carried o ut.
All li ft in g o pe rat io ns ( e .g. L ift ing o f pipe s usi ng an e x cav ato r e qui ppe d w it h an
SL I) w ill be co nt r o lle d by t he lift su pe rv iso r and Suit ably Qu alif ie d and
Ex pe rie nce d P e rso n ne l ( SQEP ) bank s -m e n.
St at ic lo ad t e st i ng i nv o lv e s t he applicat io n o f v e ry high lo a ds o v e r an ex t e n
de d pe rio d o f t im e . T he re fo re , w he n under lo ad t he ri g is v e ry
hazar do us an d o nly ex pe rie nce d, s pe c ia li ze d pe rso nne l s ho uld c a rry o ut and m ana
ge the pro cess. St rict restrictio ns o n acc ess to the testing area w ill be
applied.
T he sit e safe ty and e nv iro nm e nt w ill be co nt i nually m o nito re d v ia w ee k ly site inspe
ct io ns as w e l l t he co nt inua l m o nito ring a s de scribe d in t he abo v e
parag rap hs. T he se i nspe ct io ns are carrie d o ut inde pe nde nt ly o f t he pro je ct
m anage m e nt and a re r ec o rde d. In spe ct io n re sult s w ill be m ade av ail able u po n re qu
e st . T he He alt h a nd Safe t y P lan w ill a lso be co nt inual ly rev ie w e d, the
re sult s re co rde d and c hange s im plem e nt e d .
In the event of any accident or mishap occurring on site, whether or not they are caused by
the inadequacy of safety provision or non-compliance with safety regulations, this
will immediately be notified to the relevant authorities. The following emergency
information will be observed by all personnel prior to the start of field activities.
(1) Three major categories of emergencies could occur during site operations. (a)
Illnesses and physical injuries.
(b) Catastrophic events (fire, explosion, earthquake) (d)
Man Overboard
(c) Safety equipment problems
It is critical to have clear procedures in place in case someone falls overboard. Man- overboard
procedures shall incorporate the use of stand-by boats, life rings with appropriate length of
rope (90 feet minimum), and ladders that extend three feet below and above the water
surface.
In a case where an employee falls overboard, they will need assistance to get back on board.
This must be accomplished quickly, particularly if the water is frigid, the person is not wearing
a life jacket, is tangled in a line or caught in a current.
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
Additionally, where employees are at a greater risk of hypothermia, additional precautions (e.g.,
use of immersion suits) should be considered when there is a chance of falling overboard.
Emergency Procedure
Throw a life ring to person overboard (bitter end of line attached on board)
If permanently mounted life ring not available, throw any floatable object
DO NOT JUMP IN AFTER THE PERSON
Immediately alert the derrick operator or superintendent and initiate emergency contact
procedures
Launch the safety skiff and recover the individual
Be prepared for treatment of Hypothermia in cold water conditions
SSG-NG01012401_869393-F07-00047 METHOD STATEMENT FOR OGBOTOBO CFA PILE INSTALLATION & TESTING
APPENDIX A: WORK SCHEDULE FOR OGBOTOBO CFA PILE INSTALLTION
Authorised
Revision Date Description Prepared By Reviewed By:
By:
R01 18-03-16 ISSUED FOR REVIEW EVELYN OBENE FRIDAY R LAWAL L.O.
CONTRACTOR
Project: SOUTHERN SWAMP ASSOCIATED GAS SOLUTIONS (SSAGS)
Title: JHA FOR CFA PILE INSTALLTION ON LAND AND ON SPUD BARGE AT OGBOTOBO
Page 2 of 9
3.10. Third party C3.11. Provide drinking water for the crew
3.11 Misunderstanding
interest of tasks C3.12. Ensure adequate communication from
3.11. Poor start to finish of the task
communication C3.13. Adequate supervision is required.
Authorised
Revision Date Description Prepared By Reviewed By:
By:
R03 18-03-16 ISSUED FOR REVIEW EVELYN OBENE FRIDAY R LAWAL L.O.
CONTRACTOR
Project: SOUTHERN SWAMP ASSOCIATED GAS SOLUTIONS (SSAGS)
Title: JHA FOR PILE LOAD TEST MONITORING AT DAY AND NIGHT
Page 2 of 5
2 Gathering of 2.1 Manual Handling 2.1 Poor handling 2.1 Trip and fall 2.1 Personnel injury 2.1 Personnel (M) C2.1 Do not work under the influence R1. First Aider / Nurse with R1. Doctor Chibuzor
equipment and 2.2 Weather Conditions technique 2.2 back injury 2.2 Equip/material damage. 2.2 Asset. (M) of drug and alcohol complete first aid kit (08150651103)
2.3 Slippery surfaces, 2.2Heavy rains & storms 2.3 Hand injury C2.2 only trained and competent R2. MEDEVAC R2. Site Nurse
materials for test Mohammed N.
2.4 tripping hazards 2.3 Hand injuries, personnel to carryout task. R3. Station ambulance on
monitoring at Night. (08052832312)
2.5 falling tools and 2.4 slips, trips and falls. C2.3 Handle material properly, use site.
appropriate lifting techniques. No R.3 HSE officer.
objects. 2.5 Incompetent personnel R4 JTF/Community site
mechanical lifting shall be done at Wisdom Ejiogu
2.6. pinch points. 2.6 Inadequate or no safety representative
night. (07051175761)
2.7.Defective tools and warning signs R.4 First Aider
unpremobbed 2.7 Sharp edges C2.3.1 Use a flashlight to clear the area
(Gordon Omonose)
equipment before walking into an unknown
2.8 Wrong tool selection R.5 Project Manager
2.8 Poor housekeeping situation.
(Kimiebi Ojujoh )
C2.3.2 Use sky scan for possible
2.9 Insufficient R.6 HSE Supervisor
thunder & lightning
Lighting (Gift Lelegbene)
C2.3.3 Do not lift object above 25kg
R.7 Engineer(Lawal
manually.
Lateef)
C2.3.4 Maintains close supervision on
R.8 Smith Keyomah
all task to be performed at night.
(Security Manager
C2.3.5 Ensure availability of adequate
08150498248)
firefighting equipment.
C2.3.6 Ensure adequate illumination of
work area.
C2.3.7 Use designated PPE (Visibility
Vest, Hardhat, Safety Shoes, Work
Gloves
2.4 Ensure a good visibility vest so that
other personnel can see where you are
2.5 Maintain good housekeeping.
Arrange materials and tools properly.
2.6 Establish a buddy system at the
beginning of every night shift
Project: SOUTHERN SWAMP ASSOCIATED GAS SOLUTIONS (SSAGS)
Title: JHA FOR PILE LOAD TEST MONITORING AT DAY AND NIGHT
Page 4 of 5
3 Connecting 3.1 Manual handling 3.1 Personnel working 3.1 struck by lose 3.1.Various injuries to 3.1Testing Personnel (H) C3.1 Do not work under the influence R1. First Aider / Nurse with R1. Doctor Chibuzor
Monitoring devices 3.2 Uneven ground near load under tension object Personnel 3.2 Equipment of drug and alcohol complete first aid kit (08150651103)
3.3 Pressurised 3.2 Equipment failure 3.2 Equipment toppling 3.1.2 Fatality C3.2 only trained and competent R2. MEDEVAC R2. Site Nurse
to test Kent ledge Mohammed N.
equipment 3.3 Not following over 3.1.3 Damage to equipment personnel to carryout task. R3. Station ambulance on
setup (08052832312)
3.4 incompetent approved work procedure 3.3 Hit by falling object C3.3 Handle material properly, use site.
appropriate lifting techniques. No R.3 HSE officer.
personnel 3.4 Poor knowledge of 34 Equipment damage R4 JTF/Community site
mechanical lifting shall be done at Wisdom Ejiogu
3.5 unauthorized associated hazard 3.6 representative
night. (07051175761)
personnel 3.6 wrong body posture.
R.4 First Aider
3.6 Uncertified 3.7 poor supervision C3.3.1 Use a flashlight to clear the area
(Gordon Omonose)
equipment 3.8 Crush point before walking into an unknown
R.5 Project Manager
situation.
3.9 Pinch points (Kimiebi Ojujoh )
C3.3.2 Do not lift object above 25kg
R.6 HSE Supervisor
manually.
(Gift Lelegbene)
C3.3.4 Maintains close supervision on
R.7 Engineer(Lawal
all task to be performed at night.
Lateef)
C3.3.5 Ensure availability of adequate R.8 Smith Keyomah
firefighting equipment. (Security Manager
C3.3.6 Ensure adequate illumination of 08150498248)
work area.
C3.4. Ensure hydraulic connections and
hoses are free of leakages
C3.5 Ensure all loose items are secured
properly
C3.6 Ensure work area is properly
barricaded with adequate warning
against unauthorised entry.
C3.6.1 Ensure only certified and tested
equipment are used.
C3.6.2 Ensure all gauges and pressure
monitoring equipment are calibrated.
Project: SOUTHERN SWAMP ASSOCIATED GAS SOLUTIONS (SSAGS)
Title: JHA FOR PILE LOAD TEST MONITORING AT DAY AND NIGHT
Page 5 of 5
4 Load test monitoring 4.1 Poor illumination 4.1 Poor visibility of work 5.1.1 Tripping Q5.1.1 Various Injuries 5.1.1 Testing M C4.1 Ensure proper lighting system at R1. First Aider / Nurse with R1. Doctor Chibuzor
at night 4.2 Reptiles, insects area Q5.1.2. Damage to /Monitoring Personnel work site; ensure light at the muster complete first aid kit (08150651103)
4.3 Stress/fatigue 4.2 Exposure to insects 5.1.2 Insect/reptiles equipment. point location R2. MEDEVAC R2. Site Nurse
bites Mohammed N.
4.4 Inadequate and contact with reptiles Q5.1.3 Fatality C4.2.1 Discuss JHA in TBM and R3. Station ambulance on
4.3 poor work rotation ensure all personnel understands site. (08052832312)
Security
Q5.1.4 Hill health R.3 HSE officer.
4.5 Adverse weather plan C4.2.2 Ensure proper work rotational R4 JTF/Community site
system; a dedicate night team to Wisdom Ejiogu
condition 4.4 Personnel exposure to 5.1.3 Hill health representative
perform task. (07051175761)
4.6 Lone walker at attack at night
R.4 First Aider
night 4.5 Exposure to due, rain, C4.2.3 Ensure adequate security is in
(Gordon Omonose)
4.7 Trip hazards and cold at night place
R.5 Project Manager
4.6 Equipment failure 5.1.4 Kidnapping, C4.2.4 Ensure use of appropriate PPE(
4.8 Agronomy of work (Kimiebi Ojujoh )
4.7 Personnel tripping on Molestation Coveralls with high visible reflective
station R.6 HSE Supervisor
object bands, clear eye goggles, hand gloves
4.9 Equipment under 5.1.5 Excessive cold and steel toe safety boots)
(Gift Lelegbene)
pressure 4.8 Poor task supervision R.7 Engineer(Lawal
4.9 working under 5.1.6 Trapped in- C4.3 Ensure efficient buddy system Lateef)
influence of drug and between C4.3.1 Stay close and communicate. Do R.8 Smith Keyomah
alcohol equipment not assume that your partner knows (Security Manager
4.10 blind spot. what you are about to do. 08150498248)
4.11 poor communication 5.1.7 Fall C4.3.2 Ensure dedicated PTW system
for night task is in place
4.12 Stress and fatigue
worker at night. C4.3.3 Ensure Safety signs are
displayed
Insufficient Lighting
C4.4 Ensure proper work supervision
C4.4.1 mosquito repellent to be
available at the work location
C4.4.2 Proper communication system
to be in place; Radio
C4.4.3 Clinic service to be available
during night activity
C4.5 Ensure all available lighting is
turned on
C4.6 Use a flashlight to clear the area
before walking into an unknown
situation
C4.6.1 Ensure safe distance from all
equipment under pressure.
C4.7 Use all equipment according to
manufacturer's directions
C4.7.1 Ensure night team Get enough
sleep at day, eat well so that workers
can remain alert and in good health.