You are on page 1of 2

SITE TEST REPORT

SITE INSPECTION AND TEST RECORD FOR VOLTAGE TRANSFORMER SECONDARY INJECTION
SEC - EOA 4400003554/00
Contract #
Name of substation:
Construction of New 115/13.8kV Khudariyah Substation Job #

Equipment

VT. DETAILS
RATIO CLASS VA CORE FUNCTION

MEASURED VOLTAGE
PHASE

R-N
Y-N

B-N

Remarks

Test Inst. Used Voltage Transformer Secondary Injection


Tested By Witnessed By
SITE TEST REPORT

SITE INSPECTION AND TEST RECORD FOR VOLTAGE TRANSFORMER SECONDARY INJECTION
SEC - EOA 4400003554/00
Contract #
Name of substation:
Construction of New 115/13.8kV Khudariyah Substation Job #

Equipment

MEASURED VOLTAGE
PHASE

R-N
Y-N

B-N

Remarks

Test Inst. Used Voltage Transformer Secondary Injection


Tested By Witnessed By