Labour ( Mazdoor ) Required For Different Works

Sr. No. Item Beldars Mazdoors Bhisti Mason

Excavation in Foundations,trenches
1 etc. in ordinary soil including disposal 1/5.66 1/7.075 - -
up to 30 m and lift of 1.5 m

Refilling Excavated earth in


2 foundation, plinth,etc. including 1/9.43 1/14.15 1/56.6 -
consolidation in 15 cm layers

Disposal of surplus earth within a lead


3 - 1/2.83 - -
of 30 m

4 Laying P.C.C. 1/1.415 1/0.943 1/3.77 1/11.32

5 Laying R.C.C. 1/0.94 1/0.94 1/2.12 1/5.66

Centering and shuttering for flat Carpenter


6 1/2.4 - -
surfaces 1/2.4

Blacksmith
7 Reinforcement work R.C.C. 1/100 - -
1/100

Random Rubble masonry with blue


8 1/0.94 1/1.415 1/11.32 1/0.94
stone in foundation

1 st class brickwork in 1 : 4 cement


mortar in superstructure,partition wall,
9 - 1/0.629 1/5.66 1/1.258
junction of roof,parapet walls, string
course

Carpenter
10 Doors and Windows Frames 1/0.18 - -
1/0.09

Carpenter
11 Pannelled,glazed,etc. shutters 1/0.019 - -
1/0.005

Fixing 40 mm x 3 mm x 38 cm flat iron Blacksmith


12 1/36 - 1/36
holdfasts 1/36
Blacksmith Carpenter
13 Fixing 16 mm dia M.S.Rods 1/5.5 -
1/16.5 1/8.25

4 cm thick cement concrete flooring


14 1/10 1/13.33 1/40 1/8
laying ,mixing and finishing

12 mm thick plastering with any


15 - 1/13.33 1/40 1/13.33
mortat

white
White washing or colour washing ( 3
16 - 1/60 washer -
Coat)
1/60

Painter
17 Painting two coats on wood or steel - 1/5 -
1/3.33
Per Day

m3

m3

m3

m3

m3

m2

Kg.

m3

m3

m3 ( 4 door
frames 7.5 cm x
10 cm ) of 1.2 m
x 2.1 m size

m3 ( 4 shutters
40 mm thick 2.0
m x 1.15 m )

Per holdfasts
Per running m

m2

m2

m2

m2