MASTER PROJECT SCHEDULE Date : 23-10-2015

Rev : 01

ID Task Name Duration Start Finish


B B B B B
05 Jul '15 02 Aug '15 30 Aug '15 27 Sep '15 25 Oct '15 22 Nov '15 20 Dec '15 17 Jan '16 14 Feb '16 13 Mar '16
14 25 05 16 27 07 18 29 10 21 01 12 23 04 15 26 06 17 28 08 19 01 12 23
1 Matrix Extension Project 181 days Wed 05/08/15 Tue 01/03/16
2 Milestones 139 days Mon 24/08/15 Sat 30/01/16
24
25 Construction 181 days Wed 05/08/15 Tue 01/03/16
26 Kick Off Meeting 1 day Wed 05/08/15 Wed 05/08/15
27 Mobilization + Site access6 days Mon 17/08/15 Sat 22/08/15
28 Surveying 3 days Wed 05/08/15 Fri 07/08/15
29 Main building 165 days Mon 24/08/15 Tue 01/03/16
30 Pile Cap 23 days Mon 24/08/15 Fri 18/09/15
91
92 Ground Floor 36 days Thu 03/09/15 Tue 13/10/15
141
142 Mezanine Floor 34 days Wed 30/09/15 Fri 06/11/15
175
176 First Floor 28 days Fri 23/10/15 Tue 24/11/15
209
210 Mezazine 1A Floor 24 days Tue 17/11/15 Mon 14/12/15
243
244 Second Floor 28 days Sat 05/12/15 Wed 06/01/16
277
278 Mezazine 2A Floor 34 days Wed 23/12/15 Sat 30/01/16
311
312 Roof Beam Level 38 days Sat 09/01/16 Mon 22/02/16
340
341 Roof Top Level 31 days Tue 26/01/16 Tue 01/03/16

Task Project Summary Inactive Milestone Manual Summary Rollup Deadline


Split External Tasks Inactive Summary Manual Summary Progress
Project: Matrix Project Schedule R
Milestone External Milestone Manual Task Start-only Progress Summary
Summary Inactive Task Duration-only Finish-only Manual Progress

Page 1 REV 0