ID Task Name Duration Start Finish Feb '18 Mar '18 Apr '18 May '18 Jun '18

28/01 04/02 11/02 18/02 25/02 04/03 11/03 18/03 25/03 01/04 08/04 15/04 22/04 29/04 06/05 13/05 20/05 27/05 03/06 10/06
1 1 Project Dunex 98 days Tue Wed
13/02/18 06/06/18
2 1.1 Pekerjaan Panel 98 days Tue 13/02/18 Wed 06/06/18
3 1.1.1 Pengiriman 76 days Tue 13/02/18 Fri 11/05/18
Panel Insulation
4 1.1.2 Pemasangan 35 days Wed 14/02/18 Mon 26/03/18
Panel Dinding
5 1.1.3 Finishing 30 days Tue 13/03/18 Mon 16/04/18
6 1.1.4 Pemasangan 36 days Tue 17/04/18 Mon 28/05/18
Panel Atap
7 1.1.5 Finishing 20 days Tue 15/05/18 Wed 06/06/18
8 1.1.6 Pemasangan 10 days Sat 26/05/18 Wed 06/06/18
Lantai
9
10 1.2 Pekerjaan Pintu 32 days Tue 01/05/18 Wed 06/06/18
11 1.2.1 Pengiriman 4 days Tue 01/05/18 Fri 04/05/18
Pintu dan Assesories
12 1.2.2 Manual Sliding 6 days Sat 05/05/18 Fri 11/05/18
Door uk.
2500x4000mm
13 1.2.3 Sectional Door 5 days Sat 12/05/18 Thu 17/05/18
uk. 2800x3000mm
14 1.2.4 Sectional Door 6 days Fri 18/05/18 Thu 24/05/18
uk. 2000x2000mm
15 1.2.5 Swing Door uk. 2 days Wed 23/05/18 Thu 24/05/18
900x1900mm
16 1.2.6 Emergency Exit 1 day Fri 25/05/18 Fri 25/05/18
Door uk.
900x1900mm
17 1.2.7 High Speed 6 days Sat 26/05/18 Fri 01/06/18
Doors uk.
18 1.2.8 Hydraulic Dock 11 days Fri 18/05/18 Wed 30/05/18
Leveler uk.
1830x2119mm
19 1.2.9 Dock Shelter 3 days Thu 31/05/18 Sat 02/06/18
uk. 3500x3500mm
20 1.2.10 Dock Shelter 3 days Mon 04/06/18 Wed 06/06/18
uk. 2700x2600mm

Task Project Summary Manual Task Start-only Deadline

Project: Time Line Dunex Split Inactive Task Duration-only Finish-only Progress
Date: Tue 13/02/18 Milestone Inactive Milestone Manual Summary Rollup External Tasks Manual Progress

Summary Inactive Summary Manual Summary External Milestone