1 SUMMARY JOB DESC RENOVASI QC 12 days Mon 12/24/18 Sat 1/5/19
2 Persiapan 5 days Mon 12/24/18 Fri 12/28/18
3 Pemindahan Rak, Meja,dll 0.5 days Mon 12/24/18 Mon 12/24/18
4 Melepas kabel, instalasi, angin 0.5 days Mon 12/24/18 Mon 12/24/18
5 Pembongkaran Instalasi listrik dan angin tahap 2 0.5 days Tue 12/25/18 Tue 12/25/18
6 Perbaikan Meja, Rak, dll 1 day Tue 12/25/18 Tue 12/25/18
7 Pengecatan sebagian meja 0.5 days Tue 12/25/18 Tue 12/25/18
8 Mengeluarkan semua alat-alat di QC 1 day Fri 12/28/18 Fri 12/28/18
9 Pekerjaan Akhir 2 days Fri 1/4/19 Sat 1/5/19
10 Memasangkan Peralatan 2 days Fri 1/4/19 Sat 1/5/19