You are on page 1of 2

LST- ECT- LFT-

EST-Earliest Latest Earliest Latest TOTAL


Job Duration
start time start start finish FLOAT
time time time
Receive notice to proceed and sign contract. 3 0 0 3 3 0
Prepare and submit project schedule 2 3 3 5 5 0
Obtain building permits 14 5 5 19 19 0
Item Procurement(Steel,Cement,etc) 20 19 55 39 75 36
Mobilization on Site, Power Supply and electricity supply 7 19 26 26 33 7
Setting up site office temporary accommodation, lay down yard, fencing, etc 5 26 31 31 36 5
Excavate foundations 20 31 51 51 71 20
Form column piers and spread foundations 4 51 55 55 59 4
Pour column piers and foundations 3 55 58 58 61 3
Curing piers and foundations 3 58 61 61 64 3
Supporting Framework 4 61 65 65 69 4
Erect steel columns, beams and joint - 1st and 2nd floors 14 65 79 79 93 14
Erect steel columns, beams and joist - 3rd floor and 4th floor 10 79 89 89 99 10
Erect steel columns, beams and joist - 5rd floor 6th floor 10 89 99 99 109 10
Install miscellaneous iron and bracing 10 99 109 109 119 10
Form and Pour Concrete - Floors and Roof 1st floor 10 109 119 119 129 10
Install rebar and in-floor utilities 1st floor(including mechanical, electrical, plumbing) 0
Pour and cure 1st floor slab 10 119 129 129 139 10
Form and Pour Concrete - Floors and Roof 2nd floor 10 129 139 139 149 10
Install rebar and in-floor utilities 2nd floor(including mechanical, electrical, plumbing) 5 0
Pour and cure 2nd floor slab 10 139 149 149 159 10
Form and Pour Concrete - Floors and Roof 3rd floor 10 149 159 159 169 10
Install rebar and in-floor utilities 3rd floor(including mechanical, electrical, plumbing) 5 0
Pour and cure 3rd floor slab 10 159 169 169 179 10
Form and Pour Concrete - Floors and Roof 4th floor 10 169 179 179 189 10
Install rebar and in-floor utilities (including mechanical, electrical, plumbing) 5 0
Pour and cure 4th floor slab including roof 10 179 189 189 199 10
Form and Pour Concrete - Floors and Roof 5th floor 10 189 199 199 209 10
Install rebar and in-floor utilities (including mechanical, electrical, plumbing) 0
Pour and cure 5th floor slab including roof 10 199 209 209 219 10
Form and Pour Concrete - Floors and Roof 6th floor 10 209 219 219 229 10
Install rebar and in-floor utilities (including mechanical, electrical, plumbing) 0
Pour and cure 6th floor slab including roof 10 219 229 229 239 10
Masaonary and Brickwork 42 229 271 271 313 42
Install rebar and in-floor utilities (including mechanical, electrical, plumbing) 25 229 271 254 296 42
Install exterior sheathing and metal studs 21 229 271 250 292 42
Rough-in plumbing at toilets and masonry walls 21 271 292 292 313 21
Installing Windows and doors 20 292 322 312 342 30
Paint walls and woodwork 30 292 322 322 352 30
Install light fixtures - test and clean 14 322 367 336 381 45
Install hard tile flooring in common areas 30 322 352 352 382 30
Clean hard tile floors 15 352 367 367 382 15
Remove debris from building and do final clean-up 5 352 367 357 372 15
Obtain certificate of occupancy 3 367 370 370 373 3
Issue final completion documents including warranties 3 370 373 373 376 3
Issue final request for payment 2 373 373 375 375 0
FINISH 0 375 375 375 375 0

CRITICAL PATH = 2-3-4-6-5-9-10-11-12-13-14-15-16-17-18-19-20-22-23-25-26-28-29-31-32-34-35-37-39-41-43-45-46-48-49-50

You might also like