Achmad Nizar Fauzi (201510340311061)

MENGGUNAKAN METODE LOG PEARSON III

 Diketahui data Debit Banjir di Sungai sebagai berikut:

Tahun Debit Banjir (m3/dt)


2007 802,6
2008 500
2009 1060,9
2010 1103,9
2011 380
2012 1041,2
2013 350
2014 406,8
2015 439,9
2016 502,3
 Cara pengerjaan:

No Xi Log Xi (Log Xi – Log Xirt) (Log Xi – Log Xirt)2 (Log Xi – Log Xirt)3
1 802,6 2.904 0.127 0.016 0.00207
2 500 2.699 -0.078 0.006 -0.00048
3 1060,9 3.026 0.249 0.062 0.01538
4 1103,9 3.043 0.266 0.071 0.01880
5 380 2.580 -0.197 0.039 -0.00767
6 1041,2 3.018 0.241 0.058 0.01392
7 350 2.544 -0.233 0.054 -0.01264
8 406,8 2.609 -0.168 0.028 -0.00471
9 439,9 2.643 -0.134 0.018 -0.00239
10 502,3 2.701 -0.076 0.006 -0.00044
Jumlah 27,767 -0,003 0,358 0,02184
Log Xirt 2,777

TUGAS BESAR BANGUNAN AIR


Achmad Nizar Fauzi (201510340311061)

 Perhitungan:
∑𝐥𝐨𝐠 𝑿𝒊
 Log Xirt =
𝟏𝟎

𝟐𝟕,𝟕𝟔𝟕
=
𝟏𝟎

= 2,777

 (Log Xi – Log Xirt) = (2,904 - 2,777)

= 0,127

 ∑(Log Xi – Log Xirt) = 0,127 + (-0,078) + 0,249 + 0,267 + (-0,197) + 0,241 + (-0,233)
+ (-0,168) + (-0,134) + (-0,076)

= 0,000

 (Log Xi – Log Xirt)2 = (0,127)2

= 0,016

 ∑(Log Xi – Log Xirt)2 = 0,016 + 0,006 + 0,062 + 0,071 + 0,039 + 0,058 + 0,054 + 0,028

+ 0,018 + 0,006

= 0,336

 (Log Xi – Log Xirt)3 = (0,127)3

= 0,00207

 ∑(Log Xi – Log Xirt)3 = 0,00207 + (-0,00048) + 0,01538 + 0,01880 + (-0,00767)


+ 0,01392 + (-0,01264) + (-0,00471) + (-0,00239) + (-0,00044)

= 0,02184

TUGAS BESAR BANGUNAN AIR


Achmad Nizar Fauzi (201510340311061)

 Dihitung harga simpangan baku/ Standar Deviasi

∑(𝐋𝐨𝐠 𝐗𝐢 – 𝐋𝐨𝐠 𝐗𝐢𝐫𝐭)𝟐


Sd =√
𝐧−𝟏

0,358
=√
10−1

= 0,199

 Dihitung Koefisien Kemencengan


𝒏 ∑(𝒍𝒐𝒈 𝒙𝒊−𝒍𝒐𝒈 𝒙𝒊𝒓𝒕 )^𝟑
Cs = (𝒏−𝟏)(𝒏−𝟐)𝐬𝐝^𝟑

𝟏𝟎 (𝟎,𝟎𝟐𝟏𝟖𝟒)
=
(𝟏𝟎−𝟏)(𝟏𝟎−𝟐)𝟎,𝟏𝟗𝟗^𝟑

= 0,3849

 Menghitung Q 100 tahun

Tr Pt Log XT XT
G Sd G.Sd
(tahun) (%) (m3/det) (m3/det)
1 2 3 4 5 6 7
100 1 2,604 0,199 0,518 3.295 1972,4
Keterangan:

 Kolom (1) = Periode ulang


 Kolom (2) = Probabilitas Tr/100 (%)
 Kolom (3) = Lihat tabel G Distribusi Log Pearson III
 Kolom (4) = Nilai simpangan baku
 Kolom (5) = (3) * (4)
 Kolom (6) = Rerata Log Xi + (5)
 Kolom (7) = 10(6)

TUGAS BESAR BANGUNAN AIR


Achmad Nizar Fauzi (201510340311061)

 Perhitungan

 Dengan cara Interpolasi untuk mendapatkan nilai G :


Diket :
x1 =0.3 y1 = 2,544
x2 = 0.3849 y2 = (ditanya)
x3=0.4 y3 = 2,615
𝐱𝟐−𝐱𝟏
y2 = y1 + 𝐱𝟑−𝐱𝟐 x (y3 – y1)
0,3849−0,3
= 2,544 + x (2,615 – 2,544)
0,4−0,3

= 2,604
Maka nilai G = 2,604
 Log XT = (log Xirt) + G (Sd log X)
= 2,777 + 2,604 (0,199)
= 3,295 m3/det
 XT = 103.295
= 1972,4 m3/det

TUGAS BESAR BANGUNAN AIR


Achmad Nizar Fauzi (201510340311061)
DESAIN HIDROLIK PINTU PENGAMBILAN (INTAKE)

 Hasil hitung Q100 = 1972,4 m3/det


 Elevasi muka air di hilir intake = + 67,80
 Elevasi di dasar intake = +66,50
 Elevasi dasar sungai = +65,00

1. Bangunan Pengambilan (intake)

Qn , (debit di saluran primer) = 5.0 m3/dt


Debit rencana pengambilan 1.2 x Qn = 6.0 m3/dt
Kecepatan pengambilan rencana, v = 1.95 m/dt
Dimenasi bangunan pengambilan dapat dihitung dengan rumus sebagai berikut :

dimana : Qn = debit rencana

 = 0.80 (koefisien debit)

a = tinggi bukaan pintu, m

b = lebar bersih bukaan pintu, m

g = percepatan gravitasi 9.81 m/dt2

z = kehilangan tinggi energi pada bukaan, m

Mencari kehilangan energi pada bukaan (z)

v = 1.0-2.0 m/dt (KP 02 hal 113),di ambil v =1.95 m/dt

v =  (2 x g x z)0.5

1.95 = 0.8 (2 x 9.81 x z)0.5

1.95 = 3.54 z0.5

z0.5 = 0.55

z = 0.30 m

TUGAS BESAR BANGUNAN AIR


Achmad Nizar Fauzi (201510340311061)

2. Elevasi bangunan pengambilan


Elevasi dasar hilir bangunan pengambilan + 65.00 m
Elevasi ambang bangunan pengambilan + 66.50 m
Elevasi mercu bendung + 68.30 m
El muka air di hulu bagian pengambilan + 68.10 m
n = 0.10
Elevasi mercu bendung = Elevasi muka air di hilir intake + z + h
= +67.80 + 0.30 + 0.20
= +68.30 m
Elevasi muka air di bendung = Elevasi muka air di hilir intake + z
= +67.80 + 0.30
= +68.10
a (tinggi bukaan,m) = EL MA Hulu – z – n – El ambang
= 68.10 - 0.30 - 0.1- 66.50
= 1.20 m
b (lebar bersih pintu,m) = Q / (v x a)
= 6 / ( 2 x 1.20 )
= 2.50 m
Kontrol :
Q =  x b x a ( 2 x g x z )0.5
= 0.8 x 2.50 x1.2 ( 2 x 9.81 x 0.30)0.5
=
5.82 m3/dt 6 m3/dt
Perhitungan mendekati debit saluran primer,maka tinggi bukaan (a) dan lebar bukaan (b)
sudah sesuai
Untuk mempermudah eksploitasi,nilai perbandingan tinggi dan lebar pintu = 0.8 – 1.0
Tinggi pintu = a + 0.30
= 1.2 + 0.3
= 1.5 m
Di tentukan tinggi pintu .= 2.0 m

TUGAS BESAR BANGUNAN AIR


Achmad Nizar Fauzi (201510340311061)
Lebar pintu = 2.50 m
Di pakai = 2 pintu x lebar = 1.25 m

 Jadi P, tinggi bendung


P = + Elv mercu bendung – Elv. Dasar Sungai
P = +68.30 – 65.00 = + 3.30 m

TUGAS BESAR BANGUNAN AIR


Achmad Nizar Fauzi (201510340311061)
3. Perhitungan Lebar Efektif Bendung,Pintu Pembilas, dan Pilar Pengarah
 Lebar sungai = 150 m
 Lebar bendung max = 1,2 x Lebar sungai » KP 02 Hal 48
= 1,2 x 150
= 180 m
 Lebar bendung di pakai (Lb) = lebar sungai
= 150 m
 Lebar bersih bangunan pembilas = 60% lebar total pengambilan
= 0,6 x ( 2 x 1,25 m + 1 x 1m )
= 2,1 m
Lebar pembilas di pakai = 2,5 m

Direncanakan :

Pintu pembilas = 2 pintu dengan lebar 1,25 m = 2,5 m


Pilar pembagi = 1 pilar dengan lebar 1,00 m = 1,0 m +
= 3,5 m
 Lebar pilar pengarah di rencanakan = 1,0 m

Lebar mercu bendung (B)

B = Lb – pilar pengarah – ( lebar pembilas + pilar )

= 150 – 1 – 3,5

= 145,5 m

Lebar efektif mercu (Be)

Be = B – 2 (n x Kp + Ka) x He

= 145,5 – 2 ( 2 x 0,01 + 0,1 ) x He

= 145,5 – 0,24 He

TUGAS BESAR BANGUNAN AIR


Achmad Nizar Fauzi (201510340311061)
Debit air diatas ambang  tinggi muka air (H)  He

𝟐 𝟐
Q = 𝟑 x Cd x√𝟑 𝐱 𝐠 x Be x He3/2

Q = Q100th = 1972,4 m3/det

Cd = asumsi = 1,3

2 2
1972,4 = 3 x 1,3 x√3 x 9,81 x ( 145,5 – 0,24 He ) x He3/2

1972,4 = 2,22 x ( 145,5 – 0,24 He ) x He3/2

Dengan cara trial and error He  1,0 m = 317,90 m3/det

1,5 m = 581,99 m3/det

1,75 m = 732,13 m3/det

2,0 m = 892,93 m3/det

2,25 m = 1063,63 m3/det

2,5 m = 1243,57 m3/det

2,75 m = 1432,18 m3/det

3,00 m = 1628,99 m3/det

3,25 m = 1833,58 m3/det

3,415 m = 1972,68 m3/det

Kontrol :

2 2
1972,4 = 3 x 1,3 x√3 x 9,81 x (145,5 – 0,24 x 3,415) x 3,4153/2

1972,4  1972,68 (m3/det)

Maka He yang di gunakan = 3,415 m

TUGAS BESAR BANGUNAN AIR


Achmad Nizar Fauzi (201510340311061)
 Lebar efektif mercu ( Be )

Be = 145,5 – 0,24 He

= 145,5 – ( 0,24 x 3,415 ) = 144,68 m

Perhitungan Hd

V2
He = Hd +
2g

Q 1972,4 1972,4
V= = =
A 𝐵𝑒(𝑃+𝐻𝑑) 144,68 (3,30+𝐻𝑑)

1972,4
( )2
144,68(3,30+𝐻𝑑)
3,415 = Hd +
2 x 9,81

Dengan cara coba-coba,

Hd = 3 » He = 3,239
Hd = 3,5 » He = 3,705

Interpolasi !
𝑥 3,5−3
=
3,415−3,239 3,705−3,239
x = 0,189 m
Hd = 3 + x
Hd = 3 + 0,189
Hd = 3,189 m

maka Hd yang digunakan = 3,189 m

- Kontrol
Cd = C0 x C2 x C2
- Misal di coba dengan data Ogee IV
R = 0,45 Hd
R = 0,45 x 3,189
R = 1,44 m

TUGAS BESAR BANGUNAN AIR


Achmad Nizar Fauzi (201510340311061)

- C0 = 𝐻𝑒⁄𝑟 = 3,415⁄1,44 = 2,37 , dari grafik didapat 1,380

- Gambar 3.1 Harga-harga koefisien C0 (Kp 02 Hal 53)

- C1 = 𝑃⁄𝐻𝑒 = 3,30⁄3,415 = 0,97 , dari grafik didapat 0,96

- Gambar 3.2 Harga-harga koefisien C1 (Kp 02 Hal 54)

TUGAS BESAR BANGUNAN AIR


Achmad Nizar Fauzi (201510340311061)

- C2 = 𝑃⁄𝐻𝑒 = 3,30⁄3,415 = 0,96 , dari grafik didapat 0,998

- Gambar 3.3 Harga-harga koefisien C2 (Kp 02 Hal 54)


-
- Kontrol
Cd = C0 x C2 x C2

1,30 = 1,380 x 0,960 x 0,998

1,30  1,32 (Mendekati Cd asumsi) » OK

- Karena nilai Cd kontrol dengan nilai Cd hitung hampir sama, maka perhitugan dapat
digunakan.

TUGAS BESAR BANGUNAN AIR


Achmad Nizar Fauzi (201510340311061)
 Mercu Bendung Tetap dan Profil Aliran

Mengacu Pada KP 02 Hal 57 tentang Tipe-Tipe Ogee maka dilakukan penghitungan sebagai berikut

(Dipilih Ogee IV)

 Merencanakan Dimensi Lengkung Mercu Bendung Bagian Hulu


Diketahui Hd = 3,189 m

R = 0.45 * Hd x = 0.119 * Hd
= 0.45 * 3.189 = 0.119 * 3.189
= 1.44 = 0,379

TUGAS BESAR BANGUNAN AIR


Achmad Nizar Fauzi (201510340311061)
 Merencanakan Dimensi Lengkung Mercu Bendung Bagian Hilir

X1,776 = 1,873 Hd0,776 Y

= 1,873 . 3,1890,776 . Y

1
Y = . X1,776
4,61

Y = 0,22 X1,776

Titik Gradien (Y’= 1)

Y’ = 1,776 . 0,22 . X0,776 - Koordinat

1 = 0,39 X0,776 X Y
0,336 0,032
1 1/0,776
0,672 0,109
X =( )
0,39 1,008 0,223
1,344 0,372
X = 3,36 m
1,680 0,553
Y = 0,22 X1,776 2,016 0,764
2,352 1,005
Y = 0,22 . 3,361,776
2,688 1,274
Y = 1,89 m 3,024 1,570
3,360 1,893
Maka (X,Y) = (3,36 ; 1,89)

Didapat :

X = 3.360

Y =1.893

Cek :

 X = 0.336

Y = 0.22 . 0. 3361.776 = 0.032

 X = 0.672
Y = 0.22 . 0.6721.776 = 0.109

TUGAS BESAR BANGUNAN AIR


Achmad Nizar Fauzi (201510340311061)

Gambar Lengkung Hilir


 Merencanakan Profil Muka Air

𝐐
𝑩𝒆 . 𝒀𝒛
-√𝟐. 𝐠 . (𝐙 + 𝐇𝐞 + 𝐘𝐳) = 0

Diketahui :

Q = 1972,4 m3/dt ; Be = 144,68 m

Yz = … ; Z = 3.30 m ; He = 3.415 m

Dengan Menggunakan fungsi “Goal Seek” pada Ms. Excel didapat Yz sbb;

Q Be Z Yz He 𝑄
𝐵𝑒−𝑌𝑧
-√2 𝑔 ( 𝑧 + 𝐻𝑒 + 𝑌𝑧 ) = 0

1972,4 144,68 0,330 1,362 3,415 0


1972,4 144,68 0,660 1,325 3,415 0
1972,4 144,68 0,990 1,290 3,415 0
1972,4 144,68 1,320 1,257 3,415 0
1972,4 144,68 1,650 1,227 3,415 0
1972,4 144,68 1,980 1,199 3,415 0
1972,4 144,68 2,310 1,172 3,415 0
1972,4 144,68 2,640 1,147 3,415 0
1972,4 144,68 2,970 1,123 3,415 0
1972,4 144,68 3,300 1,101 3,415 0

TUGAS BESAR BANGUNAN AIR


Achmad Nizar Fauzi (201510340311061)
Dimana Z dimensi dari mercu dan Yz merupakan profil muka air pada mercu bendung.

Cek :

 Z = 0.330
Yz = 1.362
𝟏𝟗𝟕𝟐,𝟒
𝟏𝟒𝟒,𝟔𝟖. 𝟏.𝟑𝟔𝟐
-√𝟐 . 𝟗. 𝟖𝟏 . (𝟎. 𝟑𝟑𝟎 + 𝟑. 𝟒𝟏𝟓 + 𝟏. 𝟑𝟔𝟐) = 0

 Z = 0.660
Yz = 1.325
𝟏𝟗𝟕𝟐,𝟒
𝟏𝟒𝟒,𝟔𝟖 . 𝟏.𝟑𝟐𝟓
-√𝟐 . 𝟗. 𝟖𝟏 . (𝟎. 𝟔𝟔𝟎 + 𝟑. 𝟒𝟏𝟓 + 𝟏. 𝟑𝟐𝟓) = 0

Gambar Profil Muka Air

TUGAS BESAR BANGUNAN AIR


Achmad Nizar Fauzi (201510340311061)
 Merencanakan Peredam Energi Kolam Olak Vlugter

Gambar Kolam Olak Vlugter (KP 02 Hal 76)

 Mencari Tinggi Air di hilir bendung

Direncanakan : Kolam Olag Vlugter


k = koefisien kekasaran stickler = 45
I = kemiringan saluran = 0,002
Diketahui : b = lebar sungai = 150 m
Q = 1972,4 m3/dt

Q = A.v

V = k.R2/3.I1/2

A = ( b + mh )h = (150 + h)h = 150h + h2

P = b + 2h√𝑚2 + 1 = 150 + 2h√12 + 1

𝐴 150h + ℎ2
R = =
𝑃 150 + 2h√12 +1

TUGAS BESAR BANGUNAN AIR


Achmad Nizar Fauzi (201510340311061)
150h + ℎ2
v = 45.( )2/3. (0,002)1/2
150 + 2,83h

150h + ℎ2 2/3
= 2,0. ( )
150 + 2,83h

150h + ℎ2 2/3
Q = (150h + h2). 2,0. ( )
150 + 2,83h

(150h + ℎ2 )5/3
1972,4 = 2,0.
(150 + 2,83h)2/3

Dengan cara coba-coba,

h=4 » Q = 3010,23

h=3 » Q = 1864,94

Interpolasi !
𝑥 4−3
=
1972,40−1864,94 3010,23−1864,94

x = 0,094 m

h=3+x

h = 3 + 0,094

h = 3,094 m

V = k . R2/3 . I1/2
2/3
(bh+mℎ2 )
V =k.[ ] . I1/2
b + 2h√𝑚2 +1

2/3
(150x3,094+3,0942 )
V = 45 . [ ] . (0,002)1/2
150 + 2x3,094√12 +1

V = 4,024 m/dt

TUGAS BESAR BANGUNAN AIR


Achmad Nizar Fauzi (201510340311061)
- Tinggi energi di sebelah hilir bendung
𝑣2 𝑣2 4,0242
He2 = = = = 0,83 m
2𝑔 2𝑔 2𝑥9,81

Elevasi Muka Air di hilir bendung = Elv. dasar sungai + h

= +65.00 + 3,094

= +68,094

Elevasi tinggi energi disebelah hilir bendung = Elv. dasar sungai + h + He2

= +65.00 + 3,094 + 0,83

= + 68,924

Elevasi tinggi energi disebelah hulu bendung = Elv. Mercu Bendung + He


= +68,30 + 3,415
= +71,715

- Mencari beda tinggi energi antara hulu dan hilir bendung (Z)
Z = Elv. tinggi energi hulu – Elv. tinggi energi hilir

Z = +71,715 – 68,924

Z = 2,791 m

3 𝑞2
hc =√
𝑔

Dimana :
Q 1972,4
q = debit per satuan lebar = 𝐵𝑒 = 144,68 = 13,63 m3/dt/m

g = percepatan gravitasi = 9,81 m/dt2

hc = kedalaman air kritis, m

3 13,632
hc =√ = 2,67 m
9,81

𝑍 2,791
= = 1,05
ℎ𝑐 2,67

TUGAS BESAR BANGUNAN AIR


Achmad Nizar Fauzi (201510340311061)
𝑍
0,5 < = 1,05 < 2,0 » KP 02 Hal 76
ℎ𝑐

Maka, t = 2,4 hc + 0,4 z

t = 2,4 x 2,67 + 0,4 x 2,791

t = 7,52 m

- Tinggi ambang ujung (a)


𝑍
a = 0,28 hc √ℎ𝑐

a = 0,28 x 2,67 √2,791


2,67
a = 0,76 m
- Panjang kolam olak
Elevasi dasar kolam olak = Elevasi MA hilir – t
= + 68,094 – 7,52
= + 60,57
L = Elevasi tinggi bendung – Elevasi dasar kolam olak
L = +68,30. – 60,57
L = 7,73 m

Jadi, D = R = L = 7,73 m

TUGAS BESAR BANGUNAN AIR