Professional Documents
Culture Documents
Issued By
Transmission Maintenance Department
Transmission Power Division
Dubai Electricity and Water Authority
HAND BOOK
on EHV Over Head Line &
Under Ground Cable
Protective Regulations
TABLE OF CONTENTS
Dubai is one of the renowned The risk of damages due to contractor’s are very
high, due to Possible unauthorized and unsafe
cities within the Gulf countries, construction activities in the vicinity of the lines. In
as well as internationally, for the following consequences, it may lead to partial or
business, security & tourism, which full blackout in the Emirates of Dubai, if there are any
damages with lines.
is becoming one of the modern
citiy of the world. Therefore, To achieve Dubai government‘s vision of supplying
uninterrupted electricity, to our valuable customer(s)
reliability of Electricity becomes and to promote development activities, we feel it is
one of the basic requirements for quiet essential & noteworthy, sharing the information
modernization. which is of vital importance with contractor /
consultant & utility depts about “DEWA protective
rules & regulations” to protect Transmission lines from
unwanted damages.
Electricity is one of the basic needs, for the human
beings health, education, business, agriculture, Nevertheless, this handbook will streamline DEWA’s
transportation, communication, industrialization & regulations, to the contractor in the implementation
etc. This is to be considered a measuring parameter of works safety, quality near the Extg. Transmission
of the citizen’s living standard, industrialization lines, which will in turn support the purpose of the
and economic growth for a country. The mentioned contractors time & cost, which generally gets affected
parameters will affect, if there is shortage of electricity due to unprofessional work practices.
or frequent failure, due to any reasons.
This handbook will help the contractor / consultant
Transmission lines are the backbone of electricity & utility depts, with the information about the NOC
network which transmit power from generating requirements, DEWA Protective Rules & Regulations to
stations to distribution system, for supplying power to work in the vicinity of OHL & Cables lines, to avoid the
the customer. unexpected damage to Transmission lines & human
injury / death.
DEWA 400 / 132kV OHL & Cable lines are in open fields
and passing through desert / hilly terrain, urban areas We hope contractor / consultant / utility departments
and crossing roads / bridge / underpass / canals & & private parties will follow “DEWA protective rules
utility services etc. & regulations” and cooperate to achieve Dubai
governments vision of uninterrupted electricity supply,
in the Emirates of Dubai.
Note:
Power cables cannot be detected by cable detector,
when it is under shutdown/out of service.
EHV Over Head Line & Under Ground Cable Protective Regulations 9
TRANSMISSION LINES & ACCESSORIES
1. Tubular Monopole Tower – 400kV 2. Steel Lattice – 400kV, 132kV & Gantry
c. 400 / 132kV Gantry Tower d. 132kV Steel Lattice (Double Circuit Tower)
EHV Over Head Line & Under Ground Cable Protective Regulations 11
TRANSMISSION LINES & ACCESSORIES
132kV & Fibre Opticcable in 50cm Wide Trough in Congested Area Due to Inadiquate Space
EHV Over Head Line & Under Ground Cable Protective Regulations 13
TRANSMISSION LINES & ACCESSORIES
EHV Over Head Line & Under Ground Cable Protective Regulations 15
TRANSMISSION LINES & ACCESSORIES
Cable Laying Method Directly Buried 132kV Power / Pilot / F.O. Cable
EHV Over Head Line & Under Ground Cable Protective Regulations 17
TRANSMISSION LINES & ACCESSORIES
Note:
Joint is a weak point in transmission cable system. The b. Surface / Pole type route marker is installed for direct
joint area to be maintained and protected properly to buried or cable trough under any un-paved area.
ensure reliability of power supply.
c. Flush type cable route marker (Concrete) is installed
Power cable joint normally enclosed in 2.4 meter wide for direct buried or cable trough under any paved
concrete trough. Few Transition joints are enclosed in area, road way, parking etc with suitable marking for
UG Manholes and joint location is identified with red & straight and angle run, cable joint etc.
white route markers for all type of installation.
d. All type of route markers should be installed 50
1.4.2 Earth Link Boxes Meters interval for straight route.
This is one of the accessories for the transmission system
used for easy access to cable sheath test. 1.4.1 A 132kV Cable joint location
EHV Over Head Line & Under Ground Cable Protective Regulations 19
TRANSMISSION LINES & ACCESSORIES
1.4.4 Vertical mounted link box with steel bollard 1.4.5 Vertical mounted link box with steel crash
Protection barrier protection in road side
1.4.6 Surface / pole type route marker installed in 1.4.7 Flush type route marker at paved areas
every 50 m interval
1.4.9 Installation of Permanent Height limit gantry at road crossing tower location
EHV Over Head Line & Under Ground Cable Protective Regulations 21
TRANSMISSION LINES & ACCESSORIES
1.4.10 Installation of no parking Sign board at OHL to restrict the vehicle movement / parking in OHL corridor
1.4.11 Installation of no dumping Sign board at OHL to restrict the dumping of waste materials in OHL corridor
Hazards
Sl.No. Hazards
level
a Works within & around the Transmission Lines without obtaining NOC, violation High
of NOC condition & Method statement
d Usage of machinery for excavation over / in the close vicinity of Transmission High
lines
EHV Over Head Line & Under Ground Cable Protective Regulations 25
HAZARDOUS FACTORS WHILE WORKING NEAR
TRANSMISSION LINES
2.3 Precautionary Measures To Eliminate The Hazards
Hazards
Sl.No. Precautionary measures
level
a Contractor works within & around the Transmission lines to be allowed with Low
valid NOC & following all NOC conditions / method statement.
b All under ground cables should be identified & protect at the work areas. Low
c OHL clearance shall be confirmed & height limit gantry shall be provided to Low
work under OHL.
d Ensure manual excavation over / in the close vicinity of the Transmission lines. Low
3.2 Type Of NOC’s c. Trial Pit is a trench made across and over the
suspected location of underground cable,
trough, joint, etc. (Figure: 3.1.2)
3.2.1 Design NOC
d. Trial Pit should only be dig manually by hand to
Design NOC is a permission given to consultant to
ensure that the buried unconfirmed location of
proceed to the proposed project as indicated on
cables may not be penetrated and unaware.
the Tender Design Drawing which indicates the
(Figure: 3.1.3)
approximate locations and clearance of all the
existing transmission underground cables and e. Trial Pit Checklist should be satisfied before
overhead lines. initiation of digging Trial Pit. (Annex 3.1.1)
EHV Over Head Line & Under Ground Cable Protective Regulations 29
NOC FOR CONSTRUCTION WORKS
Fig 3.1.2 Locating 132kV cable through Trial Pit. Fig 3.1.3 Manual excavation for Trial Pit.
Locating the service by referring the NOC Manual excavation for trial pit to trace the service
Special Cases:
1. In case of 132kV cable not found (HDD area), DEWA
supervisor will write in the verification, that cable is
not found at x meter depth.
2. Additionally, coordinates from As-Built drg. can be
provided for trial pits.
3. Sensor method can be used for identification of
132kV cable.
EHV Over Head Line & Under Ground Cable Protective Regulations 33
NOC FOR CONSTRUCTION WORKS
i. If any landscaping work included under f. Details of tower protection (crash barrier)
the road project within the vicinity of the temporary height limit gantry, etc. safety
existing 400 / 132kV OHL / cable services arrangement to be provided if the works are
those details to be submitted. close to the OHL.
j. Clearance from the road signal post, street g. Underground structural works details like
light poles to the existing 400 / 132kV OHL / cable joint / duct bank.
cable to be provided. h. Clearance from the existing joint location to
k. If the 132kV Cable diversions / OHL rising the proposed joint lotion for LILO / Existing
included under the road contract, detailed cable diversion works.
drawing to be submitted. i. TLP staff verified Cable / OHL clearance
l. Access to the substation to be shown to the details.
drawing. (If the proposed road close to the j. If any additional information required other
substation). than the above to be provided.
m. TLP staff verified Cable / OHL clearance details.
n. If any additional information required other C. Installation of Pipelines.
than the above to be provided.
a. Posed scope of work drawing shall be
B. Installation of Electrical cable / trough furnished in details such as Main pipe, PVC
duct for control cables, RTU, Valve chamber
a. Proposed scope of work drawing to be Etc. to be submitted in scale (1:1000) with
submitted in scale (1:1000) with DLTM DLTM coordinates incorporating the Existing
coordinates incorporating the Existing 400 / drawing route, circuit names, cable joint /
132kV OHL / cable route, circuit names, and link box location.
cable joint / link box location.
b. Clearance from the proposed scope of work
b. Clearance from the proposed scope of work / excavation edge to the 132 / 400kV cable
/ excavation edge to the 132 / 400kV cable / trough edge and Horizontal and vertical
/ trough edge and Horizontal and vertical clearance from the OHL to the proposed
clearance from the OHL to the proposed scope of work, Horizontal clearance from the
scope of work, Horizontal clearance from the tower foundation to the excavation edge.
tower foundation to the excavation edge. c. ROW cross section details.
c. ROW cross section details. d. Method statement, crossing details, cable /
d. Method statement, crossing details, cable / trough protection details.
trough protection details. e. Clearance details of equipment / machinery
e. Clearance details of equipment / machinery to to be submitted along with method of
be submitted along with method of statement, statement, if the works are near / close to
if the works are near / close to the OHL. the OHL.
EHV Over Head Line & Under Ground Cable Protective Regulations 35
NOC FOR CONSTRUCTION WORKS
EHV Over Head Line & Under Ground Cable Protective Regulations 37
NOC FOR CONSTRUCTION WORKS
details of the services, (Water, Drainage, to the cable diversion to be marked on the
storm water, Irrigation pipelines Etc., drawing.
Etisalat duct, Electricity HV and LV) Crossing b. Cross section details of services crossing i.e.
details, Protection details to be submitted. mainly for water and other pressure pipe
j. If any landscaping work included under line crossings, Existing 132kV cable crossing,
the road project within the vicinity of the Road crossing etc. to be provided.
existing 400 / 132kV OHL / cable services c. Copy of RTA NOC to be attached with the
those details to be submitted. Final as Built Drawing along with ROW cross
k. Clearance from the road signal post, street section.
light poles to the existing 400 / 132kV OHL / d. Duct bank / Drilling portion including length
cable to be provided. and GPS coordinates.
l. If the 132kV Cable diversions / OHL raising e. Directional Drilling profile details with GPS
included under the road contract, Separate co ordinates (Separately for each drilling).
As built drawing to be submitted as per
f. Cable schedule showing the section wise
DEWA standard.(Standard requirements list
route length.
attached).
g. Pilot / F.O cable joint location marked with
m. The contractor and the consultant make
GPS coordinates and detailed section.
sure that back filling works over the
existing cable route where the construction h. Cable route layout inside the substation
related works carried out over / within the (if any).
vicinity of the 400 / 132kV OHL / cable area i. Updated substation layout showing new
and route markers displaced / removed / 132kV cable route along with existing (If any).
damaged during the work execution are j. Single line drawing showing cable in duct
replaced.(If any) bank area / protection with Inter lock tile /
n. Joint site inspection from TLM personnel Directly buried area.
may be required to confirm the above details k. Cable diversion contract No., Cable
provided. manufacture name, Cable test report, Data
o. Note:-If any work carried out without DEWA of cable laid, Cable type and size, No. Of
NOC or Violation of DEWA NOC conditions cables, Distance between cable centre to
during the work execution, such cases the centre and cable circuit Name.
clearance certificate may be not issued. l. Cable joint details i.e. Coordinates
(Four corners), Joint type, Jointer name and
J. Requirements of as built drawings for 400 /
date, Joint Manufacture name.
132kV OHL rising / Cable diversions
m. Spare Duct details. Duct coordinates, No.
a. Clearance from the B / L / ROW / Road edge
Of ways / layers, Duct inspection checklist
EHV Over Head Line & Under Ground Cable Protective Regulations 39
NOC FOR CONSTRUCTION WORKS
3.4 Transmission Line Maintenance NOC Conditions
A. 400 / 132Kv Cables
EHV Over Head Line & Under Ground Cable Protective Regulations 41
NOC FOR CONSTRUCTION WORKS
Contact details
Location DEWA Head office DEWA Hudaiba office DEWA Hudaiba office
20cm 20cm
DANGER DANGER
132kV LIVE CABLE 15cm 132kV LIVE CABLE 15cm
BELOW BELOW
Rear view
20cm 20cm
DANGER DANGER
132kV LIVE CABLE 15cm 132kV LIVE CABLE 15cm
75cm
BELOW BELOW
75cm
Front view
Front view
Danger Sign Boad
EHV Over Head Line & Under Ground Cable Protective Regulations 45
PROTECTIVE REGULATIONS & PRECAUTIONARY
MEASURES FOR THE PROTECTION OF TRANSMISSION LINES
7.1 132kV Power, Fiber Optic, and Pilot Cables in trough
a. Provide (3m x 1m x 0.3m) Pre cast Reinforced Concrete Class 40 / 20 Protection Slab over the trough. Extending
1mtr from the road edge. Figure: 4.1.6, 4.1.7
b. Protection Slab should be extended along the width 8. New service Road: New Service Road is allowed to run
of the proposed road and extended at least one longitudinally over Fiber Optic or Pilot Cables if the
meter from the edge of each side of the road. following requirements and additional protections /
spare duct are met and provided respectively:
c. Provide 4 x 150mm dia spare ducts inside the trough
and terminate the spare ducts to both ends of a. Providing the depth of existing Fiber Optic or Pilot
protection slab, for future use, without disturbing Cables is not less than 1.0 meter below the ground
the surface of the road. and protection tiles are installed over the cables.
Figure: 4.1.8.
7.2 132kV directly buried power / pilot / F.O cables
a. Each of the existing cable should be encased by new b. Providing Cable Joint Box outside the proposed
150 mm dia (split duct) and all ducts plus two spare service road, otherwise, it should be made inside
ducts should be encased by concrete to be called as approved type of manhole.
“Concrete Duct Bank”. Figure: 4.1.8
b. There concrete duct bank should extend at least one
meter away, from edges of the proposed road.
EHV Over Head Line & Under Ground Cable Protective Regulations 47
PROTECTIVE REGULATIONS & PRECAUTIONARY
MEASURES FOR THE PROTECTION OF TRANSMISSION LINES
Fig 4.1.9 Protection details for tiling on top of 132kV cable trough
Protection Slab Details For Road Construction On Top Of The 132kV Trough / Cable
9. Parking installation: Parking (Asphalted or c. Flush type cable route marker should be installed
Interlocking Tiles) is allowed above the existing 132kV over the cable route at maximum interval of 50
cables in trough or direct buried Fiber optic / Pilot meters for straight cable run. Figure: 1.4.7 (Pg 21)
Cables and the following requirements and additional
protections should be met and provided respectively. 10. Road widening: Existing protection & spare ducts
to be extended to the proposed road widening /
a. Providing of protection / spare duct as shown in the crossing area. New spare ducts (end to end) to be
Figure: 4.1.8 & 4.1.9. provided, if not possible and maintain minimum
1.0 meter either side of the proposed road edge.
b. No part of parking area should be constructed over Figure: 4.1.10
underground cable joint and flush type Link box.
Protection Slab Details For Road Widening On Top Of The 132kV Trough / Cable
11. No Blocking of Access: Entrance to DEWA substation be cleaned before demobilization. Figure: 4.1.11,
and access to DEWA Corridor should not be blocked 4.1.12, 4.1.13
for the new project / work by any means temporary
or permanently 13. Route markers: Route markers should not be
displaced / destroyed (will be charged) and to be
12. Backfilling: Backfilling of transmission cable route replaced / reinstated in the same place / position
to be carried out as per DEWA standard. Backfilling after after completion of the work with pole or
materials / excavated soil or any other materials flush type & tiled area to be provided with flush
which is used for placement of buried pipe shall not type route marker. after completion of the works -
be left at the site. The stored / dumped materials or Figure: 1.4.6, 1.4.7 (Pg 21)
soil shall be disposed immediately and the site shall
EHV Over Head Line & Under Ground Cable Protective Regulations 49
PROTECTIVE REGULATIONS & PRECAUTIONARY
MEASURES FOR THE PROTECTION OF TRANSMISSION LINES
14. As built drawings: As built drawing showing cable, joint / Link box position installation to the permanent
structures or land marks, to be provided after finishing the project.
Fig 4.1.11 Placing of cable Protection tiles during Fig 4.1.12 Placing of electrical warning tape during
backfilling backfilling
CBCH-INDS pilot finally back filled CBCH-INDS pilot finally back filled
Fig 4.1.14 - Temporary Height limit gantry under OHL At machinery working locations
EHV Over Head Line & Under Ground Cable Protective Regulations 51
PROTECTIVE REGULATIONS & PRECAUTIONARY
MEASURES FOR THE PROTECTION OF TRANSMISSION LINES
Fig 4.1.15
Fig 4.1.16
EHV Over Head Line & Under Ground Cable Protective Regulations 53
PROTECTIVE REGULATIONS & PRECAUTIONARY
MEASURES FOR THE PROTECTION OF TRANSMISSION LINES
3. Horizontal clearance: Minimum horizontal clearance of about 40m and 30m from tower concrete foundation
to edge of road and bridge to be ensured for 400kV and 132kV OHL respectively.
Fig 4.1.17
Minimum Horizontal Clearence From 400 / 132kV OHL Tower Foundation To The Edge Of The Road,
When The Line & The Road Is Running In Parallel
Fig 4.1.18
Minimum Vertical Clearence From Bottom Conductor of 400 / 132kV O / H Line To The Top Of The Road Level
For High Way / Secondary Road (considering a maximum conductor temperature of 80 degree Celsius)
EHV Over Head Line & Under Ground Cable Protective Regulations 55
PROTECTIVE REGULATIONS & PRECAUTIONARY
MEASURES FOR THE PROTECTION OF TRANSMISSION LINES
5. Permanent Crash Barrier: Permanent steel Crash 8. Removal of unwanted material: Leftover / Waste
barrier need to be provided, if the horizontal / debris materials should be removed from the OHL
clearance from the Tower concrete foundation to the Corridor, after the completion of work.
edge of the road / bridge is less than 40 m and 25 m
for dual carriage way and service roads respectively.
Fig 4.1.19 Permanent steel crash barrier for Tower Fig 4.1.21 Scaffolding provided at road crossing during
foundation protection Tower erection
6. Permanent Height limit gantry: Permanent heights 9. Parking of vehicle: Parking of Light / Heavy Vehicle
limit Gantry of about 5.5 - 6 m from the finished within the OHL corridor is prohibited.
road level to be provided at the road crossing
tower locations, at both sides of the road (Dual 10. Scaffolding protection: Scaffolding to be provided
Carriageway and service roads). Figure: 1.4.9 (Pg 23) for road crossing, during Tower Construction
activities Figure: 4.1.21
7. Access Road: DEWA’s Access road must be repaired
by the contractor, if damaged.
Minimum Horizontal Clearence For 11kV / 33kV / Etisalat / DU Duct and Pipe Laying With Parallel 132kV Cable In Trough
EHV Over Head Line & Under Ground Cable Protective Regulations 57
PROTECTIVE REGULATIONS & PRECAUTIONARY
MEASURES FOR THE PROTECTION OF TRANSMISSION LINES
4. Parallel installation: New cable installation is not 6. Any crossing of new 132kV / 11kV cables above
allowed to run parallel exactly above or below the Existing direct buried Transmission cable, existing
existing 132kV cables and troughs, irrespective cable to be protected by spilt duct and surround
of any vertical clearance but allowed besides concrete with spare duct to ensure that no load
(adjacent), provided the clearances should be will be transferred to the cables. (Figure: 4.1.8 -
complied as per the approved NOC. Pg 47). While crossing below the existing direct
buried Transmission cable, affected cable should
5. Crossing over: New cable crossing over the be protected in splict duct / wooden coffin box and
Existing trough is not allowed. All crossing shall be supported with cross beam & vertical steel angle /
underneath of the trough except joint area through nylon rope. (Figure: 4.2.2 & 4.2.3)
HDD only (Fig 4.2.5)
Fig 4.2.5 Directional drilling
Typical Protection for Single Group Of 132kV Oil File Filled Cables
EHV Over Head Line & Under Ground Cable Protective Regulations 59
PROTECTIVE REGULATIONS & PRECAUTIONARY
MEASURES FOR THE PROTECTION OF TRANSMISSION LINES
Fig 4.2.3 Protection of direct buried cable with Fig 4.2.4 Protection of 132kV trough by H-beam
supporting structure method for utility corssings
7. Crossing under trough: 132kV trough / direct buried 10. Entrance: Entrance to DEWA substation and access
cable to be protected as per approved method while to DEWA corridor should not be blocked for the
installation of duct bank by open cut method (if proposed project / work by any means temporary or
trench width exceeds 1.5 m) underneath of cable permanently
trough of 6 m length. (Figure: 4.2.4)
11. Backfilling: Backfilling of transmission cable route
8. GPS coordinates: For crossing existing 132kV cable to be carried out as per DEWA standard Backfilling
by HDD Method all existing Transmission services materials or any other materials to have been used
to be identified by trial pit. HDD entry / exit pit for placement. The excess materials or soil shall be
location shall be marked by GPS coordinates and disposed immediately and that site shall be cleaned
shall be verified by DEWA-TLP supervisor during T.P before the shift to next site. (Figure: 4.1.11, 4.1.12,
verification & before starting the construction work. 4.1.13 - Pg 50)
9. Diversion / LILO cable length: New cable length 12. Route markers: Route markers should not be displaced
for existing cable diversion & LILO should not be / destroyed (will be charged) and to be replaced /
less than 100m from joint to joint or joint to cable reinstated in the same place / position after after
termination at GIS. completion of the work with pole or flush type& tiled
area to be provided with flush type route marker. after
completion of the works Figure: 1.4.6, 1.4.7 (Pg no - 21)
2. Crash barrier: Temporary concrete crash barriers Fig 4.2.6 - Minimum horizontal clearance requirement
need to be installed around nearby tower for excavations near tower foundation
foundation. (Figure: 4.1.16) Pg 53
EXISTING G.L
5.0mtr.
Minimum Horizontal Clearence From 132 / 400kV / O / H Line Tower To Prop. Trench Excavaion
EHV Over Head Line & Under Ground Cable Protective Regulations 61
PROTECTIVE REGULATIONS & PRECAUTIONARY
MEASURES FOR THE PROTECTION OF TRANSMISSION LINES
EHV Over Head Line & Under Ground Cable Protective Regulations 63
PROTECTIVE REGULATIONS & PRECAUTIONARY
MEASURES FOR THE PROTECTION OF TRANSMISSION LINES
8.
Steel sleeve protection: Installation of High 11. Parallel installation: New pipeline installation is
pressure line crossing below of the 132kV cable.Pipe not allowed to run parallel exactly above or below
line need to be provided by suitable steel sleeve to the existing 132kV cables and troughs, irrespective
prevent pipeline breakage impact. (Figure: 4.3.2) of any vertical clearance but allowed besides
(adjacent), provided the clearances should be
complied as per the approved NOC.
Fig 4.3.2 Steel sleeve provided for high pressure
pipeline crossing 132kV cable 12. Trough cover opening: Crossing of pressurized pipe
line above the cable trough is not allowed as this
will obstruct opening of trough cover.
4. Sheet piling: Sheet piling or sand bags to be provided, 10.3 A minimum horizontal clearance of 100m from
while excavating near the tower foundation to avoid tower foundation to be ensured, for laying any
collapse of sand. (Figure: 4.2.7) Pg 62 proposed metallic pipe services at a nominal
diameter more than 450mm, as per DEWA
5. Earth conductor protection: Tower foundation Technical specification
earth conductor to be protected, while excavating
near the tower foundation.
EHV Over Head Line & Under Ground Cable Protective Regulations 65
PROTECTIVE REGULATIONS & PRECAUTIONARY
MEASURES FOR THE PROTECTION OF TRANSMISSION LINES
4.4 Construction Of Buildings, Boundary Wall, Temporary
Fencing And Interlocking
A. In the vicinity of existing 400 / 132kV Cable
1. Existing cable identification: Existing Transmission 5. Access Road: Access road to the building necessary
lines to be identified in the vicinity of new cable protection to be made for the existing cable route as
installation area, by trial pit and fix danger sign per the approved NOC.
board along the cable route & area to be barricaded,
before starting the work at site. Figure: 4.1.1, 4.1.2, 6. Shoring / Anchoring: Shoring / Anchoring should
4.1.3 (Pg no - 44) be minimum 2.0 M away from the existing cable /
Trough edge. Figure: 4.4.2
2. No Machinery Excavation: Machinery, construction
equipment / excavator / Vehicles etc. are not Fig 4.4.1 Transmission cable (400kV, 132kV)route
allowed to work / move or park over the cable route should not be enclosed by fence and no storage of
and use of heavy vibratory compaction is prohibited. any material over cable corridor
If any particular locations are required to cross over
the Extg.cables, then that portion separate NOC to
be obtained & cable route to be protected for the
crossing area. Only Manual excavation is allowed.
Figure: 4.1.4 (Pg no - 45)
EHV Over Head Line & Under Ground Cable Protective Regulations 67
PROTECTIVE REGULATIONS & PRECAUTIONARY
MEASURES FOR THE PROTECTION OF TRANSMISSION LINES
B. In the vicinity of Existing 400 / 132kV OHL
Note:
Width of the OHL corridor
varies from one to another
tower location.
20m - Minimum horizontal
clearance from 400kV
outer conductor
15m - Minimum horizontal
clearance from 132kV
outer conductor
1. Construction works inside corridor: Construction of 3. Access Road: DEWA access road along the line not to
building & any other activities are not allowed within be disturbed or damaged.
DEWA OHL Corridor. OHL corridor shall be confirmed
from TLMD NOC center. (Figure: 4.4.3) 4. Vehicle parking: Heavy machinery, vehicle or other
equipment are not allowed to park under / near the
2. Miscellaneous works inside corridor: Shoring / overhead line.
walls / Fence / Interlocking are not allowed within
OHL corridor. OHL corridor shall be confirmed from 5. Height limit gantry: Temporary height limit gantry
TLMD NOC center. to be installed, in case vehicles and equipment
require to pass / approach the OHL’s.
3. Prior intimation: Prior intimation to be given to 6. Clearance: Micro tunneling / Thrust boring /
DEWA 3 days advance prior to start the work and Directional drilling should have a minimum vertical
works to be carried out in the presence of DEWA TLP clearance of 2.0m from the bottom of the cable /
supervisor. (Format attached Pg.no - 31) trough and the horizontal clearance of 2.0m from
the edge of the cable / trough to the entry / exit pit.
4. No Machinery Excavation: Machinery, construction Drilling profile to be approved by DEWA TLMD.
equipment / excavator / Vehicles etc. are not
allowed to work / move or park over the cable route 7. Trough protection: While laying of steel sleeve / pipe
and use of heavy vibratory compaction is prohibited. line underneath of trough for crossing by open cut
If any particular locations are required to cross over method, 132kV cable trough to be supported with
the Extg.cables, then that portion separate NOC to suitable steel supports Figure: 4.2.4 (Pg no 60)
be obtained & cable route to be protected for the
crossing area. Only Manual excavation is allowed. 8. Entry / Exit pit: While making entry / Exit pit close
Figure: 4.1.4 (Pg no- 45) to 132kV cable for for drilling,132kV cable to be
protected by sheet piling. (Figure: 4.5.1)
EHV Over Head Line & Under Ground Cable Protective Regulations 69
PROTECTIVE REGULATIONS & PRECAUTIONARY
MEASURES FOR THE PROTECTION OF TRANSMISSION LINES
Fig 4.5.1 Transmission cable to be protected by sheet pilling during microtunnelling
4. Parallel installation: New cable installation is not 9. Service verification: All services to be identified
allowed to run parallel exactly above or below the by trial pit if duct laying by HDD method. GPS
existing 132kV cables and troughs, irrespective coordinates to be provided for TP locations & entry
of any vertical clearance but allowed besides / exit pit for the drilling. Before starting the drilling
(adjacent), provided the clearances should be works, the coordinates shown in the approved
complied as per the approved NOC NOC for entry / exit pit & trial pit locations to be
confirmed by TLP supervisor.
EHV Over Head Line & Under Ground Cable Protective Regulations 71
PROTECTIVE REGULATIONS & PRECAUTIONARY
MEASURES FOR THE PROTECTION OF TRANSMISSION LINES
10. Entrance: Entrance to DEWA substation and access 4. Sheet piling: Sheet piling or sand bags to be provided,
to DEWA corridor should not be blocked for the while excavating near the tower foundation to
proposed project / work by any means temporary or avoid collapse of sand. (Figure: 4.2.7) Pg 62
permanently.
5. Earth conductor protection: Tower foundation earth
11. Backfilling: Backfilling of transmission cable route conductor to be protected, while excavating near
to be carried out as per DEWA standard. Backfilling the tower foundation.
materials or any other materials to have been used
for placement. The excess materials or soil shall be 6. Access road: DEWA patrolling access road must be
disposed immediately and that site shall be cleaned repaired by the contractor, if damaged.
before the shift to next site. (Figure: 4.1.11, 4.1.12,
7. Removal of unwanted materials: Leftover / Waste
4.1.13 - Pg no 50)
/ debris materials should be removed from the OHL
12. Route markers: Route markers should not be Corridor, after the completion of work.
displaced / destroyed (will be charged) and to be
8. Parking of vehicle: Parking of Light / Heavy Vehicle
replaced / reinstated in the same place / position
over or beneath the Transmission services (Cable /
after after completion of the work with pole or
OHL) corridor is prohibited.
flush type& tiled area to be provided with flush
type route marker. after completion of the works
(Figure: 1.4.6, 1.4.7- Pg no - 21)
EHV Over Head Line & Under Ground Cable Protective Regulations 73
PROTECTIVE REGULATIONS & PRECAUTIONARY
MEASURES FOR THE PROTECTION OF TRANSMISSION LINES
B. In the vicinity of Existing 400 / 132kV OHL
1 Tree Plantation: No tree plantation is allowed within the OHL corridor. (Figure: 4.7.1)
Note: Width of the OHL corridor varies from one to another tower location.
No Tree Plantation Allowed Inside DEWA Transmission OHL Corridor
Fig 4.7.2
Minimum Clearance requirement for Lighting Pole Installation from OHL conductor
EHV Over Head Line & Under Ground Cable Protective Regulations 75
PROTECTIVE REGULATIONS & PRECAUTIONARY
MEASURES FOR THE PROTECTION OF TRANSMISSION LINES
b) Crash barrier: Temporary concrete crash 3 Construction parking:
barriers need to be installed around nearby
tower foundation. (Figure: 4.1.16 - Pg 53) a. Parking area construction is not allowed
within DEWA Transmission OHL Corridor. OHL
c) Excavations near Tower foundations: Minimum Corridor details shall be confirmed from TMD
horizontal distance of 5m to be ensured for any NOC center.
excavations near the concrete foundation of
the tower. (Figure: 4.2.6 - Pg 61) b. DEWA patrolling access road must be repaired
by the contractor, if damaged.
d) Minimum vertical clearance: Any poles /
structure erected in the vicinity of OHL should c. Leftover / Waste / debris materials should
have minimum falling clearance of 6.0 / 5.0 be removed from the OHL Corridor, after the
meter for 400 / 132kV lines. (Figure: 4.7.2) completion of work.
e) Access road: DEWA patrolling access road must d. Parking of Light / Heavy Vehicle within the OHL
be repaired by the contractor, if damaged. corridor is prohibited.
EHV Over Head Line & Under Ground Cable Protective Regulations 79
IMPLEMENTATION OF NOC CONDITIONS &
PRECAUTIONARY MEASURES
Figure: 5.4 - Site instruction Note
Figure: 5.5 -
Notice to stop work
EHV Over Head Line & Under Ground Cable Protective Regulations 81
IMPLEMENTATION OF NOC CONDITIONS &
PRECAUTIONARY MEASURES
5.6 Awareness Tool Box talk
Awareness TBT is conducted by DEWA TLM Engineer to contractors Engineer, safety Engineer, supervisor, machine
operators at site to create awareness about the safety precautionary measures to avoid lines abnormality or
damages. (Format attached Figure: 5.6)
Figure: 5.6 -
Tool Box talk format
EHV Over Head Line & Under Ground Cable Protective Regulations 85
ACTIONS AGAINST VIOLATORS
Table 6A
EHV Over Head Line & Under Ground Cable Protective Regulations 87
ACTIONS AGAINST VIOLATORS
Contractor performs violation at site repeatedly & accumulates say 20 points, as per the violations of NOC
conditions & protective regulations.
a. Action is taken against contractor pertaining to i. Similar procedural action will be taken in
Category A, as per Table 6B. accordance with the category - B & C, if the
contractor falls in those categories.
b. Contractors’ works are stopped in locations
wherever Notice to stop work was issued & new j. Except that in category ‘B’, The contractor shall
NOC issuance or suspension of issued NOC done. replace Safty Engineer and site supervisor of the
project.
c. Concerned utility / dept should take necessary
actions against the contractor against the k. In category ‘C’, the contractor shall replace
performed violations. The project Engineer, Safty engineer and site
supervisor of the project.
d. Action plan for safe construction works in the
close vicinity of the of Extg. Trans.lines neds to
be prepared by contractor & submitted to TLM-LP
for approval.
7.1.1 Prior Intimation, Supervision for trial pit work & verification for the trial pit : DEWA Work supervision /
Verification request format duly filled to be sent to DEWA “03” working days in advance by a) applying direct
with DEWA TLM-TLP office, 4th floor, DEWA customer service building, Hudaiba office (During DEWA office hours
7:30am to 2:30pm) b) by fax no 04-3984655 and c) by email tp.tlm@dewa.gov.ae, sample attached in page no.31.
7.1.2 Telephonic confirmation: To be done with concerned DEWA Engineer, after sending fax or email to ensure the
availability of DEWA supervisor on the requested date, by the telephone numbers 04-5066670 / 04-5066680.
7.1.3 Work Hours: Works should be carried out during DEWA working hours only. Special approval to be obtained
for emergency and very urgent works with justification to work beyond working hours.
7.2.1 Prior Intimation, supervision for OHL / Cable lines protection works: DEWA Work supervision request format
duly filled to be sent to DEWA 3 working days advance by a) applying direct with DEWA TLM-TLP office, 4th floor,
DEWA customer service building, Hudaiba office (During DEWA office hours 7:30am to 2:30pm) b) by fax no
04-3984655 and c) by email tp.tlm@dewa.gov.ae, sample attached in page no.31.
7.2.2 Telephonic confirmation: To be done with concerned DEWA Engineer, after sending fax or email to ensure
the availability of DEWA supervisor on the requested date, by the telephone numbers 04-5066670 / 04-5066680.
7.2.3 Work Hours: Works should be carried out during DEWA working hours only. Special approval to be obtained
for emergency and very urgent works with justification to work beyond working hours.
For clarification about services completion time & followup in English / Arabic, you can contact us on the following
telephone numbers : 04 5066670 / 04 5066680.
In this Hand Book, are explained the following items in different chapters in order to protect the existing 400 /
132kV Transmission Lines network as below:
1. Transmission Lines & Accessories
2. Hazardous factors while working near Transmission Lines
3. NOC for construction works
4. Protective Regulations & precautionary measures for the protection of Transmission Lines
5. Implementation of NOC conditions & precautionary measures
6. Legal Actions against violators
The above items will helps all contractors, consultant, utility depts & private parties for proceeding NOC
application, with proper method statement for safe construction works in & around the transmission lines.
Furthermore, all concern parties will get general / technical knowledge about the transmission OHL & Cable lines
and safety precautionary measures to avoid unwanted damages.
We hope contractor, consultant, utility departments & private parties will follow “DEWA protective rules &
regulations”, for the uninterrupted electricity supply, in the Emirates of Dubai.
EHV Over Head Line & Under Ground Cable Protective Regulations 91
SERVICES PROVIDED BY TLM
List Of Abbreviations
º NDRC Non Disruptive Road Crossing º TLM-LP Transmission Lines Maintenance - Lines Patrolling
For any clarification related to any information mentioned in the Hand Book, please send your queries / comments
to the following contact details:
Email : tp.tlm@dewa.gov.ae
Website : www.dewa.gov.ae
EHV Over Head Line & Under Ground Cable Protective Regulations 93