You are on page 1of 4

Input Detail

Typical Geometry
Section Plan

GL. Pha 0.2


Phu 0.4

Pb Fb Lb

Fh Pw
Fw
Lh Fw
Lw Lw

Dimensions
Lean Footing Pedestal
Width(w) 3.1 3 0.4
Depth(b) 1.8 1.7 1.7
Height(h) 0.05 0.4 0.6

F.G.L. CD (+) 4.200 m B.O.F. CD (+) 3.200 m


Water Level CD (+) 1.200 m T.O.G. CD (+) 4.500 m
Neccessity of P.E. Film. Not Necessary

Excavation & Backfill Information


Excavation Slope 1: 0.0 Vertical Excavation Excavation Depth 1.05 m

Physical Properties
Structure Concrete fck = 40 MPa Lean Concrete fck = 20 MPa
Re-bar fy = 245 kN/m2
BM Calculation Sheet
Structure : Sleeper
FWBS Item Calculation Unit Quantity Remark
1. Excavation Fw x Fb x Excavation Depth Vertical
(above Water level) 3 x 1.7 x 1.05 = 5.355 m3 m3 5.355 excavation

2. Lean Concrete Lw x Lb x Lh
(fck = 20 MPa) 3.1 x 1.8 x 0.05 = 0.279 m3 m3 0.279

3. Concrete Footing
(fck = 40 MPa) Fw x Fb x Fh
3 x 1.7 x 0.4 = 2.04 m3

Pedestal
Pw x Pb x Ph
0.4 x 1.7 x 0.6 = 0.408 m3

Total
Footing + Pedestal = 2.04 + 0.408 = 2.448 m3 m3 2.448

4. Grout Pw x Pb x Thk
(Thk = 25 mm) 0.4 x 1.7 x 0.025 = 0.017 m3 m3 0.017

5. Form Work Footing


2 x {( Fw x Fh ) + ( Fb x Fh )}
2 x {( 3 x 0.4 )+( 1.7 x 0.4 )} = 3.76 m2

Pedestal
2 x {( Pw x Ph ) + ( Pb x Ph )}
2 x {( 0.4 x 0.6 )+( 1.7 x 0.6 )} = 2.52 m2
BM Calculation Sheet
Structure : Sleeper
FWBS Item Calculation Unit Quantity Remark

Total
Footing + Pedestal = 3.76 + 2.52 = 6.28 m2 m2 6.28

6. Backfill Excavation - Concrete Volume * + Pedestal Volume above Ground * including


(Excavated Soil) lean con'c
Pedestal volume above ground volume
Pw x Pb x Pha
0.4 x 1.7 x 0.2 = 0.136 m3

Total
5.355 - 2.727 + 0.136 = 2.764 m3 m3 2.764

7. Bitumen Coating Footing


( Fw x Fb ) + 2 x {( Fw x Fh ) + ( Fb x Fh )}
- ( Pw x Pb )
( 3 x 1.7 ) + 2 x {( 3 x 0.4 )
+ ( 1.7 x 0.4 )} - ( 0.4 x 1.7 ) = 8.18 m2

Pedestal
2 x {( Pw x Phu ) + ( Pb x Phu )}
2 x {( 0.4 x 0.4 )+( 1.7 x 0.4 )} = 1.68 m2

Total
Footing + Pedestal = 8.18 + 1.68 = 9.86 m2 m2 9.86
BM Calculation Sheet
Structure : Sleeper
FWBS Item Calculation Unit Quantity Remark
8. Re-bar ton BBS

9. Anchor Bolt EA 4 Vendor


supply
10.Sliding Plate EA 2 Vendor
supply
11.Construction Joint ( Pw x Pb )
( 0.4 x 1.7 ) = 0.68 m2 m2 0.68

You might also like