Project:Construction of Extradosed Paira Bridge Project in Bangladesh

Subject : Pending submission from contractor for erection and procurement items

S.no Item

A)PERMANENT ITEMS
1 STU(Shock Transmission Unit)

2 POT/PTFE bearings

3 Elastomeric bearings

4 Stay cable

5 Stay cable anchorage

6 Stay cable Saddle and assembly

7 Temporary PT bars

8 Internal cables (strands)

9 Modular expansion joints

10 Strip seal expansion joint

11 miscellaneous items

B) TEMPORARY ITEMS( method statements, procedures, designs and dr

1 Viaduct Girder stressing methods

2 Viaduct girder erection

3 Deck slab shuttering and casting

Main bridge precast segment shuttering,


4 casting, stacking, lifting and erection
Erection of segments and temporary
5 supports

6 Launching Gantry system

7 Load testing of Launching gantry

8 Construction stage analysis


f Extradosed Paira Bridge Project in Bangladesh
on from contractor for erection and procurement items

Submission

A)PERMANENT ITEMS
Contractor has to submit revised design and drawings.

Contractor has to submit design and drawings .

Contractor has to submit design and drawings .

nil

Contractor has to submit design and drawings .

Contractor has to submit design and drawings .

Design and drawings

nil

Contractor has to submit design and drawings .

Contractor has to submit design and drawings .

Contractor has to submit drawings .

B) TEMPORARY ITEMS( method statements, procedures, designs and drawings)

Contractor has to submit method statement and drawings

Contractor has to submit method statement and drawings

Contractor has to submit method statement and drawings

Contractor has to submit method statement, design and


drawings
Contractor has to submit method statement, design and
drawings

Contractor has to submit method statement, design and


drawings
Contractor has to submit method statement, design and
drawings
Construction stage analysis, design and drawings including
pre and post camber details.
Date:16-03-2017

Agency details
Test witness
Certification
by Consultant

Contractor has to submit manufacturing agency,


experience details and test procedure.
YES
Contractor has to submit manufacturing agency,
experience details and test procedure.
YES
Contractor has to submit manufacturing agency,
experience details and test procedure. YES
Contractor has to submit manufacturing agency,
experience details and test procedure. YES
Contractor has to submit manufacturing agency,
experience details and test procedure.
YES
Contractor has to submit manufacturing agency,
experience details and test procedure.
YES
Contractor has to submit manufacturing agency,
experience details and test procedure. NIL
Contractor has to submit manufacturing agency ,
experience details and test procedure.
YES
Contractor has to submit manufacturing agency ,
experience details and test procedure. YES
Contractor has to submit manufacturing agency ,
experience details and test procedure. YES
Contractor has to submit manufacturing agency ,
experience details and test procedure.
NIL

es, designs and drawings)

NIL NIL

NIL NIL

NIL NIL

NIL NIL

NIL NIL

NIL NIL

YES YES

NIL NIL