Site Instruction

CONTRACT DETAILS
Project: SH16 Causeway Alliance Project Project No: 200140
Contractor: XXXXXXXXXX
Date:
Contract No: 950XXXXX Variation / Adjustment No: SI XXX

SITE INSTRUCTION DETAILS

Details Cost Code


If space is insufficient, attach separate schedule

Tick box
1. This instruction is deemed to be included in the contract
works.
2. Please proceed with this instruction with the price for the
work to be submitted within 5 working days
3. No work is to commence until a variation for this scope is
approved and issued

APPROVALS

For the Constructor JV: Signature:


Name: xxxxxxxxx

Title: Variation Order Or Other Contract Adjustment (Short Version) Date Published: 31/10/2011 Page 1 of 1
ID: 001346 Version: 2
Project Management System / N5012 - Uncontrolled Document when Printed
SH16 Causeway Alliance http://ourway.lc.local/index.htm?pmsId=10972