Professional Documents
Culture Documents
37 3 7 PDF
37 3 7 PDF
1 INTRODUCTION
This paper details the design of rock bolt and shotcrete support of roofs of wide span tunnels in Sydney’s Hawkesbury
Sandstone at depths to approximately 60m. It provides a simplified analytical process for the method developed for the
Sydney Opera House Carpark (18 m spans) and which was used for the Eastern Distributor Tunnels (spans up to 24 m).
The methodology is essentially an extension to the linear arch theory.
Hawkesbury Sandstone is typically characterised by: horizontal bedding with typical spacing of 1 to 3 m; dominant
north-south and east-west trending steeply dipping joints; and a horizontal stress that is 1.5 to 2 times the vertical stress.
In the unweathered to slightly weathered state, the rock mass is typically medium strength (average rock mass UCS
about 20MPa), with an elastic modulus in the range 1000 to 3000 MPa. Bedding planes are often infilled with sandy
clays up to 20mm thick with typical friction angles of 20 to 30°.
2 DESIGN METHODOLOGY
The design methodology described in this paper is based on the work developed in Pells & Best (1991) and Pells et al
(1994). The underlying philosophy is to use the displacements derived from a jointed rock mass analysis to design rock
bolt reinforcement that provides greater capacity than the stresses derived from an elastic continuum analysis. Shotcrete
thickness is calculated based on techniques adapted from the work of Barrett & McCreath (1995) once the rock bolt
spacing has been determined.
The steps involved comprise calculating the following:
(i) Roof Beam Thickness. The minimum roof beam thickness for the tunnel span in question is assessed to limit
roof sag to acceptable levels. This is used to set the rock bolt length. As a first pass, the roof sag may be set between
10 to 50mm. Linear arch theory is used to calculate roof beam thickness.
(ii) Stresses. The induced stresses acting along and across the bedding planes are calculated as if the roof beam
was acting as an elastic continuum. Stresses can be calculated using beam theory and/or numerical solutions.
(iii) Excess Shear Stress. The excess shear stress is the difference between the induced shear stress from step (ii)
and the shear capacity of the bedding planes. This excess needs to be resisted by the rock bolts.
(iv) Shear. The induced relative horizontal movement or shear between beds is calculated as if the roof beam was
allowed to de-laminate and sag into the tunnel opening. This can be calculated using beam theory and/or numerical
solutions.
(v) Rock Bolt Contribution. The contribution of the rock bolt as a result of shear displacement calculated in step
(iv) can be calculated using published graphs such as Pells et al (1994), analytical solutions such as Pellet & Egger
(1996) and/or numerical solutions.
(vi) Factor of Safety. A FoS is calculated as the force resisting shear divided by the force causing shear calculated
in step (ii). If the shear induces unacceptable rock bolt loads, then either the bolt spacing can be reduced or the roof
beam thickness increased.
(vii) Shotcrete Thickness. The thickness of shotcrete required to support loosened blocks of sandstone between the
rock bolts is calculated with and without relying on adhesion of the shotcrete to the sandstone.
For the purpose of this paper however, the closed-form solution of Sofianos (1996) has been entered into an Excel
spreadsheet to provide a quick estimate of the roof deflection for various beam thicknesses of an 18 m span tunnel in
typical Hawkesbury Sandstone at a depth of about 35 m. The appeal of Sofianos’ solution is that checks against
crushing, shear and buckling are also made. Numerical analyses could be used for this and subsequent steps.
Figure 3 suggests a 5 to 6 m thick roof beam is required to limit maximum sag to between 10 and 15mm. A rock bolt
length of about 7m ensures a 1 m embedment length.
50
40
Deflection (mm)
30
20
10
0
10 11 12 13 14 15 16 17 18 19 20
Span (m)
2m bed 3 00 4 00 5 00 6 00
Figure 3: Roof sag as a function of tunnel span and bedding thickness for 35m depth
-0.8
-0.7
Induced Shear Stress (MPa)
-0.6
-0.5
-0.4
-0.3
-0.2
-0.1
0.0
0 2 4 6 8 10
Distance across span(m)
1mabove crown 2m 3m 4m 5m 6m
0.9
Bedding Plane Shear Capacity (MPa)
0.8
0.7
0.6
0.5
0.4
0.3
0.2
0.1
0.0
0 2 4 6 8 10
Distance across span (m)
1m above crown 2m 3m 4m 5m 6m
0.30
0.25
Excess Shear Stress (MPa)
0.20
0.15
0.10
0.05
0.00
0 2 4 6 8 10
Distance across span (m)
1mabove crown 2m 3m 4m 5m 6m
The shear movement along a bedding plane can therefore be given by:
dωL3 ( Lx ) 3 ( Lx ) 2 ( Lx )
D= - +
IE 6 4 12
where
d = bed thickness (m)
E = Young’s Modulus (kPa)
ω= vertical force acting on beam (weight plus surcharge) (kN)
L = span (m)
I= second moment of area (m4)
x = position along beam (distance from wall)
For our example, we have assumed that the tunnel roof is fully fixed but is free to displace axially a point 1.8m into the
abutment. Figure 7 presents the shear movement that occurs along a bedding plane 1m above the tunnel roof. As can
be seen the shear is greatest about a fifth of the span from the abutment.
7
Shear Displacement (mm)
0
0 2 4 6 8 10
Distance across span (m)
Figure 8 reproduces a figure taken from Pells et al (1994) which summarises the resistance provided by two types of
bolts as a result of shear movement along a bedding plane which has a dilatancy angle of 15°, typical of Hawkesbury
Sandstone. In our example, we can expect shear movements of up to 7mm, (Figure 7) which would mobilise a shear
resistance of 110kN in a 24mm diameter steel bar installed normal to the bedding plane; and 460kN in a 23mm
diameter high tensile capacity steel bar installed at 60° to the bedding plane. Note that the bolts in Figure 8 are fully
cement grout encapsulated. The bolt contribution can also be calculated using the technique of Pellet & Egger (1996).
Ca = 4σasa
where
σa = is the adhesive strength of the shotcrete to the substrate (MPa),
s = is the spacing between rock bolts (m),
a = is the distance around the perimeter of the shotcrete panel over which adhesive forces act (m).
(Barrett & McCreath suggest a is between 30 and 50 mm)
The authors are aware of recent testing for a tunnelling project, that suggest σa=1 MPa is readily achieved in good
quality Hawkesbury Sandstone with a 50 mm thick shotcrete layer. Therefore, for a bolt spacing of 1.75 m, Ca = 210
kN, which is equivalent to a 1.5 to 2.8 m thick block of sandstone 1.75 x 1.75 m square (see Figure 10, assuming σa=0.5
to 1 MPa).
Flexure (Mix 2)
This can be designed as a two-way thin slab. The maximum moment is at the edge of the slab and is limited by the
flexural strength of the shotcrete by the relationship:
1 1
M max = − ωs 2 (1 + ν ) = f y st 2
8 6
where
ω = is the uniformly distributed load (MN/m)
ν = is the Poisson’s Ratio of the shotcrete (assumed 0.15)
ƒy= is the residual flexural strength of the shotcrete (MPa)
t= is the shotcrete thickness (m)
50
40
20
10
0
0 0.5 1 1.5 2 2.5 3
Thickness of Rock Load (m)
Figure 10: Contact widths required as a function of rock load for various adhesive strengths and 1.75 m bolt spacing
– adhesive failure.
Figure 11 shows the relationship between rock load and shotcrete thickness. For a bolt spacing of 1.75m, a 130mm
thick layer of shotcrete can support approximately a 1m thick layer of loosened sandstone.
150
SFRS thickness (mm)
100
50
0
0 0.5 1 1.5
Thickness of Rock Load (m)
1mbolt spacing 1.5m 2m
Figure 11: Thickness of SRFS as a function of rock load for 1, 1.5 and 2 m bolt spacings – flexural failure
9.1 MATERIAL
The design of a shotcrete is largely determined by its material composition. The following is given as a starting point.
9.2 STRENGTH
A compressive strength target of 30MPa should be sought. A maximum of 50 to 60MPa should be specified to avoid
brittle failure of the steel fibres (Naaman & Sujivorakul 2001).
Mix 1 does not require a residual flexural strength because it functions in adhesion and then shear. Mix 2 requires a
residual flexural strength equivalent to 2MPa at 2mm deflection of the ASTM beam, or approximately 400 J at 40mm
deflection as measured by the Round Determinate Panel test.
9.3 GRADING
Grading of the aggregate is one of the biggest issues to achieve a pumpable, shootable and durable shotcrete. The
EFNARC grading envelopes are proposed as guidelines.
9.4 FIBRES
Fibre type is particularly important in Mix 2. Not all fibres can achieve the residual flexural strength. As there is so
much development being carried out in terms of fibres at this stage, specifications should only state that fibres are to be
used to achieve the desired performance. It appears that the direction the industry is taking is to use two types of fibres
(or perhaps more) to provide toughness at small and large deflections.
9.5 CEMENTITIOUS
Typically, tunnels in Hawkesbury Sandstone will not require very high strength shotcrete therefore flyash can be used
as a cement replacement. Flyash reduces shrinkage, improves workability and durability. EFNARC recommends
flyash can be a maximum of 30% of OPC although, Morgan et al (2001) suggests this typically should be 10%. An
example mix is: 400 kg/m3 of OPC cement, 60 kg/m3 of fly ash (15% of cement), and 200 litres/m3 of water. This mix
gives w/c ratio of 0.43.
9.6 ADDITIVES
A super performing shotcrete mix is usually not needed in Hawkesbury Sandstone and hence additives can easily be
kept to a minimum. The additives suggested are:
• silica fume – mainly to increase bond strength and reduce permeability and rebound, say 20 kg/m3 silica fume
(5% of cement content);
• air entraining admixture – to improve pumping, say admixture sufficient to achieve initial air content of up to
15%, although this may be reduced depending on the cost of the supplied mix; and
• alkali-free accelerator.
9.7 CURING
In the past, others proposed the high humidity of tunnels in Sydney as a means of ‘self-curing’. However, partial curing
produces much the same results as not curing (Bernard & Clements 2001). The authors recommend curing.
10 DESIGN
The above process leads to a roof support design comprising high capacity bolts at 1.75m centres and shotcrete of either
50mm thickness in good quality rock (Mix 1) or 130mm thickness (Mix 2) in poorer quality rock. The simplicity of the
process allows parametric studies to be rapidly completed. Detailed numerical models can now be carried out to
confirm the design.
11 CONCLUSION
A analytical method of designing rock bolt and shotcrete support of wide span tunnels in horizontally bedded sandstone
is described. The beauty of the methodology is that it follows engineering principles and arrives at a Factor of Safety
that can be used objectively to rank various bolting layouts. A solution using only closed-form equations is provided to
show how simple and fast a very good first pass roof support can be designed. The same methodology can be applied to
numerical models, such as FLAC and UDEC, to refine the design.
12 REFERENCES
Barrett, S.V.L. & McCreath, D.R. 1995. Shotcrete support design in blocky ground: towards a deterministic approach.
Tunnelling and Underground Space Technology, Vol 10 No 1, pp 79-89.
Beer, G. & Meek, J.L. 1982. Design curves for roofs and hanging-walls in bedded rock based on ‘voussior’ beam and
plate solutions. Trans IMM, 91, ppA18-A22.
Bernard, E.S. & Clements, M.J.K. 2001. The influence of curing on the performance of fibre reinforced shotcrete
panels. Proc. Int. Conf. on engineering developments in shotcrete.
Brady, B.H.G. & Brown, E.T. 1985. Rock mechanics for underground mining (page 217) George Allen & Unwin
Evans, W.H. 1941.The strength of undermined strata Trans IMM, 50, pp475-532.
Hutchinson, D.J. & Diederichs, M.S. 1996. Cablebolting in underground mines §2.18.12, BiTech Publishers.
Morgan, D.R., Heere, R., Chan, C., Buffenbarger, J.K. & Tomita, R. 2001. Evaluation of shrinkage-reducing
admixtures in wet and dry-mix shotcretes. Proc. Int. Conf. on engineering developments in shotcrete. .
Naaman, Ae & Sujivorakul, C. 2001.Pull-out mechanisms of twisted steel fibres embedded in concrete. Proc. Int. Conf.
on engineering developments in shotcrete.
Pellet, F. & Egger, P. 1996. Analytical model for the mechanical behaviour of bolted rock joints subjected to shearing
Rock Mech Rock Engineering No.29 (2), pp73-97.
Pells, P.J.N. & Bertuzzi, R. 1999. Permanent rockbolts – the problems are in the detail. 10th Australian Tunnelling
Conf.
Pells, P.J.N. & Best, R.J. 1991. Aspects of primary support design for tunnels in the Sydney Basin Trans IEAus.
Pells, P.J.N., Best, R.J. & Poulos, H.G. 1994. Design of roof support of the Sydney Opera House underground parking
station .Tunnelling and Underground Space Technology, Vol 9, No 2, pp201-207.
Poulos, H.G. & Davis, E.H. 1974. Elastic solutions for soil and rock mechanics Wiley & Sons.
Sofianos, A.I. 1996. Analysis and design of an underground hard rock voussoir beam roof. Int J Rock Mech Sci &
Geomech Abstr. 33 No2, 153-166.
Sterling, R.S. 1977. Roof design for underground openings in near surface bedded rock formations. PhD thesis.