L 2.00 M fc' 21.00 MPa D 1.50 M DL 1.20 B 2.00 M fy 414.00 MPa qnet 250.00 kPa LL 1.60 t 300 mm qa 144.00 kPa WTftg 28.80 kN EQ 1.00 c. c. 75 mm d soil 18.00 kN/M3 b 0.85 1 WL 1.00 Column Dimensions SERVICE LOADS CL 300 mm Axial Loads Moment X Moment Y CB 300 mm PDL 131.00 kN MXDL 1.00 kN-M MY DL 0.00 kN-M Reinforcing Bar PLL 50.00 kN MXLL 1.00 kN-M MYLL 0.00 kN-M FL 16 mm PEQ 60.00 kN MXEQ 0.00 kN-M MYEQ 0.00 kN-M FB 16 mm PWL 0.00 kN MXWL 0.00 kN-M MYWL 0.00 kN-M NL 10 No. of c.c. - conc. cover DL - Dead Load EQ - Earthquake Load D - depth of soil if considered NB 10 bars NL/NB- no. of bars along L or B LL - Live Load WL - Wind Load d soil - soil density if considered
CHECK FOR BEARING CAPACITY
A. GRAVITY LOADS P 6Mx 6My q = + + A LB2 BL2 P CL q = 53.95 < qnet = 250 ok soil CB B. GRAVITY + LATERAL LOADS P 6Mx 6My q = + + A LB2 BL2 D q = 68.95 < 1.3qnet = 325 ok d Mx c X d = 201 mm fua = 76.40 kPa My Pu = 297.20 kN fub = 76.40 kPa B Mux = 2.80 Kn-M fuc = 72.20 kPa t Y Muy = 0.00 Kn-M fud = 72.20 kPa a L b Pu/LB = 74.30 kPa fuave. = 74.30 kPa
CHECK FOR ONE WAY SHEAR (BEAM SHEAR@CRITICAL SECTION)
0.649 0.649 Vu = fumax[(L-CL)/2-d][(B-CB)/2-d] = 32.1797564 kN nu = Vu/fbd = 0.29 MPa na = fc' / 6 = 0.76 MPa > nu = 0.29 ok
CHECK FOR TWO WAY SHEAR (PUNCHING SHEAR)
0.251001 2.004 Vu = Pu-qu*Ap = 278.550626 kN np = Vu/fbd = 0.81 MPa na = fc' / 3 = 1.53 MPa > np = 0.81 ok
CHECK FOR FLEXURAL (BENDING) CAPACITY
REINFORCEMENT ALONG L DIRECTION REINFORCEMENT ALONG B DIRECTION 2 As = 2,010.62 mm As = 2,010.62 mm2 r = 0.00500 r = 0.00500 rmin = 0.00200 < r ok rmin = 0.00200 < r ok rmax = 0.01626 > r ok rmax = 0.01626 > r ok
a = 23.32 0.85 a = 23.32 0.85
Mcap = f0.85fc'aBd(1-a/2d) = 141.85 Mcap = f0.85fc'aLd(1-a/2d) = 141.85 Mu = L - CL 2 = 55.20 Mu = B - CB 2 = 55.20 qu ( B )( ) qu ( L )( ) 2 2 2 2 Mcap > Mu ok Mcap > Mu ok
CHECK FOR DEVELOPMENT LENGTH
REINFORCEMENT ALONG L DIRECTION REINFORCEMENT ALONG B DIRECTION 201.06 201.06 Ldreq = 0.02Abfy = 363 mm Ldreq = 0.02Abfy = 363 mm fc' fc'
Ldprov = [(L-CL)/2]-cc = 775 mm Ldprov = [(B-CB)/2]-cc = 775 mm
Ldprov > Ldreq ok Ldprov > Ldreq ok
CHECK FOR BEARING ON FOOTING
A1 90000 A2 1218816 3.68 2 Pc = f0.85fc' A A2 = 2,249 kN > Pu = 297.2 kN safe 1 A1