Status of Work, Package – II, Matracon

Date: 30-05-2018

Total Completed Balance


Activity Progress (%)
(M) (M) (M)

Carriage Way
Aggregate Base 6,100 5,650 450 92

Asphaltic Base 6,100 5,850 450 92

Asphaltic Wearing
6,100 5,650 450 92
Course

T.P Paint 6,100 4,063 2,037 66


Lane
Marking C.R Paint 4,900 Nil 4,900 0

MBS Corridor
Aggregate Base 2,894 2,750 144 95

Asphaltic Base 2,894 1,837 1,057 63

Asphaltic Wearing
2,894 482 2,412 16
Course

NJ Barrier 5,835 5,560 250 95

Fence 7,000 2,700 4,300 39

Lane Marking 3,400 Nil 3,400 Nil

Bus Station /E&M Work


G-13/G-14 Station Civil Work about 70% completed, Slow Progress
(9+300) E&M Placing order for procurement in Progress, Detail enclosed.
N-5 Station Civil Work about 50% completed, Slow Progress
(11+210) E&M Placing order for procurement in Progress, Detail enclosed.