Professional Documents
Culture Documents
and Procedure
Compiled by
Safety Trainees
PECL
15 January 2011.
2. Factories Act-Section 28
(1):Hoists and Lifts
(a) In a factory hoists and lifts
should be of :
3
The Factories Act, 1948
Sec:2(ca): Competent Person
Means:
A person or an institution recognised as such by
CIF for carrying out tests, examination and
inspections required to be done in a factory under
provisions of this Act regarding:
(v)qualifications and experience of person and
facilities available at his disposal;
(ii) qualifications and experience of persons
employed in such institution and facilities a/v
therein, with regard to conduct of such tests,
examinations and inspections, and more than
one person or institution can be recognised
as a competent person in relation to a factory.
4
The Factories Act,
1948
Sec:2(j): Machinery
Includes prime movers,
transmission machinery and
other appliances whereby power
is generated, transformed,
transmitted or applied.
5
Lifting Equipments:
Hydra’s
CRANES: limit switches
Fork lifts
Magnetic lift crane
Mobile cranes: wheel ,crawler
EOT
Gantry
Chain pully:spur gear,worm wheel
Winch machine 6
Lifting tackle:
Slings
Ropes
Shackles
Swivel
Rings
Couplers
Sockets, Eyebolts.
Frames & spreaders
Plate lifting clamps
7
Overview
Terms & definitions
Planning the lift
The lift
Landing the load
Do’s & Don’ts
Case study
Slinging methods
Safe slinging practice
8
Terms & Definitions
Competent person:
A person who has acquired, through a
combination of qualifications, training or
experience, the knowledge and skill to
perform the task required.
Grommet:
Endless wire rope sling.
MBL:
Minimum breaking load of the lifting tackle.
SWL:
Safe working load.
9
Definitions
Tag line:
A rope of suitable strength, construction
and length attached with an appropriate
recognised bend or hitch to the load,
used to control the load during lifting or
positioning.
Test certificate:
A certificate issued by an authorized
person
10
SIMPLE CHAIN PULLEY
BLOCK
11
Planning the lift
e s se ntia l
p e r a t i o n is
e l i f tin go rr ie d out
a n ni ng th e l if t is ca
P l th a t th
e n s ur e f f ic ie n t ly
to l y a n de
sa fe
12
Planning the lift
13
Planning the lift
The following points must be
considered during planning:
Where the load is to be picked up from
Where the load is to be placed
What areas to be passed over
Any obstructions in the way
How the load is to be slung
How the slings are to be removed and
access to them
14
Planning the lift
For complex lifts, following points may have
to be considered:
Special lifting accessories such as spreader
beams to ensure that the load is safely lifted and
without damage to the product (large
machineries, generators, etc.)
Special connectors to connect special built in
connecting points. The operations may involve:
Turning loads over or standing them upright
Using more than one crane to lift a load.
15
The lift
After slinging but before lifting, the following
must be considered
16
The lift
After slinging but before lifting, the following
must be considered
Are all personnel clear of the load?
Is the landing site prepared to take the
load?
If required, is hand/tag lines attached to
the load?
17
Check Before Lifting
Now lift the load a short distance above the
ground and check that:
The load is balanced and stable.
The legs of the slings are at correct angles.
Any packing pieces used, are in place and
sound.
The load itself is not stressed, especially when
lifting packing cases, timber etc, which can fail
under the loads applied due to lifting.
18
Landing the load
Before landing the load check that:
The landing area will take the weight of the load.
There is sufficient space for the load.
There are strips of timber or similar on which to
land the load such that the slings can be easily
removed by hand.
The load should be landed gently to
ensure that it is not damaged and
that the crane does not receive any
shock loading.
19
Do’s & Don’ts
Always Never
Ensure that only
Wrap tag line around
authorized
slingers/signalers attach hand or body.
or detach loads, or signal Leave a suspended load
the crane operator. unattended.
Discuss operations with Pass loads over people.
the crane operator Ride or climb on
(special operations). suspended loads.
Ensure that the capacity Stand or walk beneath
of the crane is sufficient. the loads.
Seek expert advice when Use pipes to support
using eye bolts, plate for landing the load
clamp etc.
Use tag line always
20
SWL OF SLINGS
SAFE INCLUDED SAFE
WORKING ANGLE θ WORKING
LOAD OF LOAD
SLING WITH ANGLEθ
G = 10 TON at 90 10 TON
90
160 3.45 TON
140 6.80 TON
22
SLING ANGLES AND SAFE WORKING LOADS
.
When L = S
Sling angle is 60˚
23
SLING ANGLES AND SAFE WORKING LOADS
Calculating SWL
H is the vertical
distance from the
saddle
of the hook to the top of
the load.
L is the distance
measured along the
sling from the saddle of
the hook to the
top of the load.
The ratio H/L will be
same as the ratio h/l
24
SLING ANGLES AND SAFE WORKING LOADS
Determining
capacity of 2-Leg
Bridle
Hitch
SWL
= SWL (of single
vertical hitch) X H/L
X2
25
SLING ANGLES AND SAFE WORKING LOADS
26
SLING ANGLES AND SAFE WORKING LOADS
Determining
capacity of 3-Leg
Bridle
Hitch
SWL
= SWL (of single
vertical hitch) X H/L
X3
When sling legs are
not of equal length
use smallest H/L
ratio.
27
SLING ANGLES AND SAFE WORKING LOADS
Determining capacity
of 4-Leg Bridle
Hitch
Load may be carried by
only 3 legs while
the fourth merely
balances it. Therefore
the recommended SWL
is:
SWL
= SWL (of single
vertical hitch) X H/L X 3
When sling legs are not
of equal length
use smallest H/L ratio.
28
SLING ANGLES AND SAFE WORKING LOADS
Determining capacity
of Single Basket
Hitch
For Vertical legs (fig A):
SWL = SWL (of single
vertical hitch) X 2
29
SLING ANGLES AND SAFE WORKING LOADS
Determining capacity
of Double Basket
Hitch with inclined
angles
SWL
= SWL (of single
vertical hitch) X H/L X 4
30
SLING ANGLES AND SAFE WORKING LOADS
Determining
capacity of Double
Wrap
Basket Hitch
Depending on the
configuration, SWLs
are the same for the
Single Basket Hitch
or the Double Basket
Hitch.
31
SLING ANGLES AND SAFE WORKING LOADS
SWL
= SWL (of single
vertical hitch) X H/L
X
A/B X 2
32
SLING ANGLES AND SAFE WORKING LOADS
Determining
capacity of Double
Wrap
Choker Hitch
Depending on the
configuration, SWLs
are the same for the
Single Choker Hitch
or the Double Choker
Hitch.
33
Endless Sling choker Hitch Endless or Grommet Sling in
Configuration Vertical Hitch
34
SLING ANGLES AND SAFE WORKING LOADS
Endless Sling in
Double Basket
Hitch
Configuration
35
Endless or Grommet Slings Standard Eye-to Eye slings
36
SLING ANGLES AND SAFE WORKING LOADS
37
Effect of sling angle on
Webbing
38
Twisted Eye Slings
39
What can happen, if, adequate
safety is not observed?
40
A case study 1
The incident:
In June 2003, a tragic incident
occurred at one of the oil and gas
development site in Algeria, resulting
in one fatality and two injuries.
The incident occurred during the assembly
of an onshore drilling rig. A large section
of the rig was being lifted when a lifting
chain failed.
41
A case study 1
Actual measurement to
hook position was 9.43 m.
43
Case Study 2
Job : erection of gantry crane beams
Description of Accident:
Two beams of 11.5m X 1.5m X 0.75m
weighing about 6 tones were lying on
concrete sleepers.
Out of two beams one beam was lying on
sleeper in horizontal position.
The other beam was in vertical position and
was to be positioned to make alignment with
the first beam.
44
45
Case Study 2
Job : erection of gantry crane beams
Description of Accident:
Slings were placed around the vertical beam.
Mr. XYZ went up the beam to adjust the sling.
He adjusted the sling and stood in between the
two beams.
In the meantime someone gave signal to lift the
beam.
Crane operator lifted the beam by about 4 mm
up its position.
46
Case Study 2
Job : erection of gantry crane beams
Description of Accident:
During that operation beam swayed
towards the first beam and Mr. XYZ was
caught between the two beams.
On hearing the scream, crane driver
placed the beam back on its original
position.
47
Case Study 2
Job : erection of gantry crane beams
Description of Accident:
Mr. XYZ got up and tried to get out of
two beams but he stumbled and fell
down on sleepers, got injury near left
eyebrow.
He was taken to hospital, but was
declared as dead.
48
Case Study 2
49
Case Study 2 - Investigation
50
Learning from the incidents
Apart from lifting machine, it
is also necessary to take care
of lifting tackles and lifting
procedure
51
Safe Slinging Practice
52
Safe Slinging Practice
C.G.
53
Safe Slinging Practice
54
Safe Slinging Practice
55
Safe Slinging Practice
Unstable
The load will shift until the
CG is under the hook.
The hook is not over
the centre of gravity This will make landing the load
very difficult, and could cause
major problems in crainage
56
Safe Slinging Practice
500 500
Kg Kg
1000 1000
Kg Kg
707 707
Kg Kg 1932 1932
Kg Kg
90 90
45 45 30 30 15 15
57
How to identify the correct
angle?
At 45 degrees, H = L
58
Safe Slinging Practice
Balanced ¼” off 1/2” off 3/4” off Point
load centre centre centre loading
Can carry Can carry Can carry Can carry Can carry
100% of 88% of 80% of 70% of 40% of
rated load rated load rated load rated load rated load
Safety latches
omitted 59
Safe Slinging Practice
Softeners, padding or use of blocking..
60
Safe Slinging Practice
61
Unsafe Slinging
62
Unsafe Slinging
63
Unsafe Slinging
64
Unsafe Slinging
Is it right method
to extend a chain
sling?
65
Unsafe Slinging
66
Sling storage
67
Hand Signals
When should the crane operator
follow hand signals?
A crane operator should always move
loads according to the established code
of signals, and use a signaler.
Hand signals are preferred and
commonly used.
68
Hand Signals
Who can give the hand signals?
a person qualified to give crane signals
to the operator,
there should be only one designated
signaler at a time,
a crane operator should move loads only
on signals from one signaler,
69
Responsibility of the signaler
The signaler must:
be in clear view of the crane operator,
have a clear view of the load and the
equipment,
keep persons outside the crane's
operating area,
never direct a load over a person.
70
Standard Hand Signals For
Controlling Overhead Cranes
With forearm
vertical, forefinger
pointing up, move
hand in small
horizontal circle
HOIST
71
Standard Hand Signals For
Controlling Overhead Cranes
LOWER
72
Standard Hand Signals For
Controlling Overhead Cranes
Arm extended
forward, hand open
and slightly raised,
make pushing
motion in direction
of travel.
BRIDGE TRAVEL
73
Standard Hand Signals For
Controlling Overhead Cranes
TROLLEY TRAVEL.
Palm up, fingers
closed, thumb
pointing in direction
of motion, jerk hand
horizontally.
TROLLEY TRAVEL
74
Standard Hand Signals For
Controlling Overhead Cranes
Arm extended,
palm down, hold
position rigidly.
STOP
75
Standard Hand Signals For
Controlling Overhead Cranes
Use one hand to give
any motion signal
and place other
hand motionless in
front of hand giving
the motion signal.
(Hoist Slowly shown
as an example.)
MOVE SLOWLY
76
Standard Hand Signals For
Controlling Overhead Cranes
Crane operator
spreads both
hands apart –
palms up.
MAGNET DISCONNECTED
77
Finally, we must remember….
78
Objective Of Good Slinging
The sling and its method of use should
be suitable for the load.
The method of attachment of the sling
to the load and the sling to the lifting
appliance should be secure.
No part of the sling should be
overloaded either by the weight of the
load or by the method of slinging.
79
Objective Of Good Slinging
The slinging method should ensure
that the load is secure and that the
load will not fall from the sling.
The load should be balanced and stable
and should not violently change its
attitude when lifted.
The load must not be damaged by, or
cause damage to, the sling.
80
If we remember & achieve
this Objective…..
The probability of
accident will be
minimum
Sling storage
82
83