You are on page 1of 9

Power System Protection

Protection Coordination

Protection coordination Peak value of inrush current


1
Relay operating characteristics and their ^ 12.0
setting must be carefully coordinated in IRush
order to achieve selectivity. The aim is ba- ^ 11.0
IN
sically to switch off only the faulted com-
ponent and to leave the rest of the power 10.0
2 system in service in order to minimize sup-
9.0
ply interruptions and to assure stability.
8.0
Sensivity
Protection should be as sensitive as possi- 7.0
3 ble to detect faults at the lowest possible 6.0
current level.
At the same time, however, it should 5.0
remain stable under all permissible load,
overload and through-fault conditions. 4.0

4 3.0
Phase-fault relays
2.0
The pick-up values of phase o/c relays are
normally set 30% above the maximum 1.0
load current, provided that sufficient short-
5 circuit current is available. 2 10 100 400
This practice is recommmended in particu- Rated transformer power [MVA]
lar for mechanical relays with reset ratios
of 0.8 to 0.85.
Time constant of inrush current
Numerical relays have high reset ratios
near 0.95 and allow therefore about 10%
6 lower setting. Nominal power 0.5 . . . 1.0 1.0 . . . 10 >10
Feeders with high transformer and/or [MVA]
motor load require special consideration.
Time constant 0.16 . . . 0.2 0.2 . . . 1.2 1.2 . . . 720
Transformer feeders [s]
7 The energizing of transformers causes
inrush currents that may last for seconds,
depending on their size (Fig. 113).
Fig. 113: Transformer inrush currents, typical data
Selection of the pickup current and as-
signed time delay have to be coordinated
so that the rush current decreases below High-resistance grounding requires much An even more sensitive setting is applied
8 the relay o/c reset value before the set more sensitive setting in the order of in isolated or Peterson-coil-grounded net-
operating time has elapsed. some amperes primary. works where very low ground currents occur
The rush current typically contains only The ground-fault current of motors and with single-phase-to-ground faults.
about 50% fundamental frequency compo- generators, for example, should be limited Settings of 20 mA and less may then be
nent. to values below 10 A in order to avoid iron required depending on the minimum
burning. ground-fault current.
9 Numerical relays that filter out harmonics
Sensitive directional ground-fault relays
and the DC component of the rush current Residual-current relays in the star point
can therefore be set more sensitive. The connection of CTs can in this case not be (integrated in the relays 7SJ512, 7SJ55
inrush current peak values of Fig. 113 will used, in particular with rated CT primary and 7SA511) allow settings as low as 5 mA.
be nearly reduced to one half in this case. currents higher than 200 A. The pickup
value of the zero-sequence relay would
10 Ground-fault relays
in this case be in the order of the error
currents of the CTs.
Residual-current relays enable a much A special zero-sequence CT is therefore
more sensitive setting, as load currents do used in this case as ground current sensor.
not have to be considered (except 4-wire The window-type current transformer
circuits with single-phase load). In solidly 7XR96 is designed for a ratio of 60/1 A.
and low-resistance grounded systems a The detection of 6 A primary would then
setting of 10 to 20% rated load current is require a relay pickup setting of 0.1 A
generally applied. secondary.

6/62 Siemens Power Engineering Guide · Transmission and Distribution · 4th Edition

WWW.EECM.MIHANBLOG.COM
Power System Protection
Protection Coordination

Differential relays (87)


Transformer differential relays are normally Time in seconds
set to pickup values between 20 and 30% 1
rated current. The higher value has to be 10000
chosen when the transformer is fitted
with a tap changer. 1000
Restricted ground-fault relays and high-
resistance motor/generator differential re- 100 2
lays are, as a rule, set to about 10% rated
current. 10

Instantaneous o/c protection (50) 1


This is typically applied on the final supply
.1 3
load or on any protective device with suffi-
cient circuit impedance between itself and
the next downstream protective device. .01
The setting at transformers, for example,
must be chosen about 20 to 30% higher .001
than the maximum through-fault current. 0 1 2 3 4 5 6 7 8 9 10
4
Current in multplies of full-load amps
Motor feeders
The energizing of motors causes a starting Motor starting current High set instantaneous o/c step
current of initially 5 to 6 times rated cur-
rent (locked rotor current). Locked rotor current Motor thermal limit curve 5
A typical time-current curve for an induction Overload protection characteristic Permissible locked rotor time
motor is shown in Fig. 114.
In the first 100 ms, a fast decaying assy- Fig. 114: Typical motor current-time characteristics
metrical inrush current appears additional-
ly. With conventional relays it was current 6
practice to set the instantaneous o/c step
for short-circuit protection 20 to 30% Time
above the locked-rotor current with a short-
time delay of 50 to 100 ms to override the 51
asymmetrical inrush period.
Numerical relays are able to filter out the 7
asymmetrical current component very fast
so that the setting of an additional time 51 51
delay is no longer applicable.
The overload protection characteristic
should follow the thermal motor character- 8
istic as closely as possible. The adaption is Main
to be made by setting of the pickup value 0.2–0.4 seconds
and the thermal time constant, using the Feeder
data supplied by the motor manufacturer.
Further, the locked-rotor protection timer
has to be set according to the characteristic Current 9
motor value. Maximum feeder fault level

Fig. 115: Coordination of inverse-time relays


Time grading of o/c relays (51)
The selectivity of overcurrent protection
be high for mechanical relays (about 0.1 s) If the same characteristic is used for all re- 10
is based on time grading of the relay oper-
and negligible for numerical relays lays, or when the upstream relay has a
ating characteristics. The relay closer to
(20 ms). steeper characteristic (e.g. very much over
the infeed (upstream relay) is time-delayed
normal inverse), then selectivity is automati-
against the relay further away from the
cally fulfilled at lower currents.
infeed (downstream relay). Inverse-time relays (51)
This is shown in Fig. 116 by the example For the time grading of inverse-time relays,
of definite time o/c relays. the same rules apply in principle as for the
The overshoot times takes into account definite time relays. The time grading is
the fact that the measuring relay contin- first calculated for the maximum fault level
ues to operate due to its inertia, even and then checked for lower current levels
when the fault current is interrupted. This (Fig. 115).
may

Siemens Power Engineering Guide · Transmission and Distribution · 4th Edition 6/63

WWW.EECM.MIHANBLOG.COM
Power System Protection
Protection Coordination

1 Operating time
52 M

51
2 M

52 F 52 F
51 51
3 F F

0.2–0.4
Time grading
4
Fault Fault Interruption of
inception detection fault current

5 I> t51F t52F


Circuit-breaker
Set time delay Interruption time

6 Overshoot*
tOS
I> Margin tM
t51M

* also called overtravel or


7 coasting time

t51M – t51F = t52F + tOS + tM

8 Time grading tTG

Example 1
9
Mechanical relays: tOS = 0.15 s
Oil circuit-breaker t52F = 0.10 s tTG = 0.10 + 0.15 + 0.15 = 0.40 s
Safety margin for measuring errors,
etc.: tM = 0.15
10
Example 2

Numerical relays: tOS = 0.02 s


Vacuum breaker: t52F = 0.08 s
tTG = 0.08 + 0.02 + 0.10 = 0.20 s
Safety margin: tM = 0.10 s

Fig. 116: Time grading of overcurrent-time relays

6/64 Siemens Power Engineering Guide · Transmission and Distribution · 4th Edition

WWW.EECM.MIHANBLOG.COM
Power System Protection
Protection Coordination

Calculation example
The feeder configuration of Fig. 117 and Example: Time grading of inverse-time relays for a radial feeder
the assigned load and short-circuit currents 1
are given. Load
Numerical o/c relays 7SJ60 with normal A F4 B F3 C F2 13.8 kV/ Fuse: D F1
inverse-time characteristic are applied. 0.4 kV 160 A
The relay operating times dependent on Load
13.8 kV
current can be taken from the diagram or
1.0 MVA
L.V. 75. 2
derived from the formula given in Fig. 118.
51 7SJ60 51 7SJ60 51 7SJ60 5.0%
The IP /IN settings shown in Fig. 117 have Load
been chosen to get pickup values safely
above maximum load current. Station Max. Load Iscc. max.* CT ratio Ip/IN ** Iprim*** Iscc. max.
I /Ip =
This current setting shall be lowest for [A] [A] [A] Iprim
the relay farthest downstream. The relays 3
further upstream shall each have equal or A 300 4500 400/5 1.0 400 11.25
higher current setting. 2690 200/5 1.1 220 12.23
B 170
The time multiplier settings can now be
calculated as follows: C 50 1395 100/5 0.7 70 19.93

Station C: D – 523 – – – – 4
*) Iscc.max. = Maximum short-circuit current
■ For coordination with the fuses, we
** Ip/IN = Relay current multiplier setting
consider the fault in location F1. *** Iprim = Primary setting current corresponding to Ip/IN
The short-circuit current related to
13.8 kV is 523 A. Fig. 117
This results in 7.47 for I/IP at the o/c 5
relay in location C.
■ With this value and TP = 0.05 The setting values for the relay at station B
are herewith t [s]
we derive from Fig. 118
an operating time of tA = 0.17 s ■ Current tap: IP /IN = 1.1 100
This setting was selected for the o/c relay ■ Time multiplier TP = 0.11 6
to get a safe grading time over the fuse on Given these settings, we can also check 50
the transformer low-voltage side. the operating time of the relay in B for a 40
The setting values for the relay at station C close-in fault in F3: 30
are therefore: The short-circuit current increases in this Tp [s]
20
■ Current tap: IP /IN = 0.7 case to 2690 A (see Fig. 117). The corre-
sponding I/IP value is 12.23.
7
■ Time multipler: TP = 0.05 10
■ With this value and the set value of 3.2
Station B: TP = 0.11 5
The relay in B has a back-up function for we obtain again from Fig. 118 4
the relay in C. an operating time of 0.3 s. 1.6
3
The maximum through-fault current of 8
1.395 A becomes effective for a fault in Station A: 2 0.8
location F2. ■ We add the time grading interval of
For the relay in C, we obtain an operating 0.3 s and find the desired operating time 1 0.4
time of 0.11 s (I/IP = 19.9). tA = 0.3 + 0.3 = 0.6 s.
We assume that no special requirements
for short operating times exist and can
Following the same procedure as for the 0.50
0.4 0.2 9
relay in station B we obtain the following
therefore choose an average time grading values for the relay in station A: 0.3
interval of 0.3 s. The operating time of the 0.1
■ Current tap: IP /IN = 1.0 0.2
relay in B can then be calculated:
■ Time multiplier: TP = 0.17
■ tB = 0.11 + 0.3 = 0.41 s 0.05
■ Value of IP /IN = 1395 A = 6.34
■ For the close-in fault at location F4 we 0.1 10
obtain an operating time of 0.48 s.
220 A
0.05
see Fig. 117.
■ With the operating time 0.41 s
2 4 6 8 10 20
and IP /IN = 6.34, Normal inverse I/Ip [A]
we can now derive TP = 0.11 0.14
from Fig. 118. t= . Tp [s]
(I/Ip)0.02 – 1

Fig. 118: Normal inverse time-characteristic of


relay 7SJ60

Siemens Power Engineering Guide · Transmission and Distribution · 4th Edition 6/65

WWW.EECM.MIHANBLOG.COM
Power System Protection
Protection Coordination

1
= 16.000 kA
Iscc = 1395 A
Iscc = 2690 A
Imax = 4500 A
I – 0.4 kVmax

Setting range Setting


IN
A
t [min]
t [s]

2 400/5 A I>> Ip = 0.10 – 4.00 xIn Ip = 1.0 xIn


100 I>, t 7SJ600 Tp = 0.05 – 3.2 s Tp = 0.17 s
I>>= 0.1 – 25. xIn I>> = ∞
5
1 52
2
3 Bus-B
10
5 200/5 A I>> Ip = 0.10 – 4.00 xIn Ip = 1.1 xIn
2 I>, t 7SJ600 Tp = 0.05 – 3.2 s Tp = 0.11 s
4 I>> = 0.1 – 25. xIn I>> = ∞
1 52
5 IA>,t
Bus-C
2 IB>,t
100/5 A Ip = 0.10 – 4.00 xIn Ip = 0.7 xIn
5 .1 IC>,t I>>
5 I>, t 7SJ600 Tp = 0.05 – 3.2 s Tp = 0.05 s
I>> = 0.1 – 25. xIn I>> = ∞
2 52
.01
6
5 13.8/0.4 KV
fuse
2 TR 1.0 MVA
5.0%
.001
7 10 2 5 100 2 5 1000 2 5 10 4 fuse VDE 160 HRC fuse 160 A
13.80 kV
I [A] 0.40 kV
1000 2 5 10 4 2 5 10 5 2

8
Fig. 119: O/c time grading diagram

The normal way Note:


9 To prove the selectivity over the whole
To simplify calculations, only inverse-time
characteristics have been used for this ex-
range of possible short-circuit currents, it is ample. About 0.1 s shorter operating times
normal practice to draw the set operating could have been reached for high-current
curves in a common diagram with double faults by additionally applying the instanta-
log scales. These diagrams can be manual- neous zones I>> of the 7SJ60 relays.
10 ly calculated and drawn point by point or
constructed by using templates.
Today computer programs are also availa-
ble for this purpose. Fig. 119 shows the re-
lay coordination diagram for the example
selected, as calculated by the Siemens
program CUSS (computer-aided protective
grading).

6/66 Siemens Power Engineering Guide · Transmission and Distribution · 4th Edition

WWW.EECM.MIHANBLOG.COM
Power System Protection
Protection Coordination

Coordination of o/c relays with fuses


and low-voltage trip devices
The procedure is similar to the above de- 1
scribed grading of o/c relays. Usually a Time MV
time interval between 0.1 and 0.2 seconds
Inverse relay 51
is sufficient for a safe time coordination.
Very and extremely inverse characteristics
are often more suitable than normal in- 2
verse curves in this case. Fig. 120 shows Other Fuse
typical examples. consumers
Simple consumer-utility interrupts use a
power fuse on the primary side of the sup-
ply transformers (Fig. 120a).
In this case, the operating characteristic of n 3
the o/c relay at the infeed has to be coordi- a
LV bus
nated with the fuse curve.
Very inverse characteristics may be used 0.2 seconds
with expulsion-type fuses (fuse cutouts) Fuse
while extremly inverse versions adapt bet-
ter to current limiting fuses. a) 4
In any case, the final decision should be Maximum fault available at HV bus Current
made by plotting the curves in the log-log
coordination diagram.
Electronic trip devices of LV breakers have
Time
long-delay, short-delay and instantaneous MV bus 5
zones.
Numerical o/c relays with one inverse time 50
o/c relay 51
and two definite-time zones can be closely
adapted (Fig. 120b). I1>, t1

Secondary I2>, t2 n
a
breaker
0.2 seconds LV bus 7
I>>

b)

Maximum fault level at MV bus Current 8

Fig. 120: Coordination of an o/c relay with an MV fuse and a low-voltage breaker trip device
9

10

Siemens Power Engineering Guide · Transmission and Distribution · 4th Edition 6/67

WWW.EECM.MIHANBLOG.COM
Power System Protection
Protection Coordination

Grading of zone times


The first zone normally operates unde-
1 Operating
layed. For the grading of the time intervals
time
of the second and third zones, the same
Z3A rules as for o/c relays apply (see Fig. 116).
t3 For the quadrilateral characteristics (relays
Z2A Z2B 7SA511 and 7SA513) only the reactance
2 t2
values (X values) have to be considered
Z1A Z1B Z1C for the reach setting. The setting of the
t1
R values should cover the line resistance
~ ZLA-B ZLB-C ZLC-D
and possible arc or fault resistances. The
arc resistance can be roughly estimated
A B C D Load as follows:
3 Z1A = 0.85 • ZLA-B Load Load

Z2A = 0.85 • (ZLA-B+Z1B)


Z3A = 0.85 • (ZLA-B+Z2B) IArc x 2kV/m
RArc =
Iscc
Min
4 Fig. 121: Grading of distance zones
IArc = arc length in m
Iscc Min = minimum short-circuit current

X Fig. 123
D
5
X3A ■ Typical settings of the ratio R/X are:
C
– Short lines and cables (≤ 10 km):
X2A R/X = 2 to 10
B – Medium line lengths < 25 km: R/X = 2
6 – Longer lines 25 to 50 km: R/X = 1
X1A

Shortest feeder protectable by


distance relays
7 The shortest feeder that can be protected
by underreach distance zones without the
need for signaling links depends on the
shortest settable relay reactance.
A R1A R2A R3A R
8
XPrimary Minimum =
VTratio
= XRelay Min x [Ohm]
CTratio
9 Fig. 122: Operating characteristic of Siemens distance relays 7SA511 and 7SA513
XPrim.Min [Ohm]
Coordination of distance relays Where measured line or cable impedances Imin = [km]
are available, the reach setting may also be X’Line [Ohm/km]
The reach setting of distance times must
extended to 90%. The second and third
take into account the limited relay accuracy
zones have to keep a safety margin of
10 including transient overreach (5% accord-
about 15 to 20% to the corresponding
Fig. 124
ing to IEC 60255-6), the CT error (1% for
zones of the following lines. The shortest
class 5P and 3% for class 10P) and a secu-
following line has always to be considered The shortest setting of the numerical
rity margin of about 5%. Further, the line
(Fig. 121). Siemens relays is 0.05 ohms for 1 A
parameters are normally only calculated,
not measured. This is a further source of As a general rule, the second zone should relays, corresponding to 0.01 ohms for
errors. at least reach 20% over the next station to 5 A relays.
ensure back-up for busbar faults, and the This allows distance protection of distribu-
A setting of 80–85% is therefore common
third zone should cover the largest follow- tion cables down to the range of some
practice; 80% is used for mechanical relays
ing line as back-up for the line protection. 500 meters.
while 85% can be used for the more accu-
rate numerical relays.

6/68 Siemens Power Engineering Guide · Transmission and Distribution · 4th Edition

WWW.EECM.MIHANBLOG.COM
Power System Protection
Protection Coordination

Breaker failure protection setting


Most digital relays of this guide provide the
BF protection as an integral function. The
62
BF
1
initiation of the BF protection by the inter-
nal protection functions then takes place
via software logic. However, the BF protec-
tion function may also be initiated from
outside via binary inputs by an alternate 2
protection. In this case the operating time 50
of intermediate relays (BFI time) may have BF
to be considered. Finally, the tripping of A
N
the infeeding breakers needs auxiliary re- Breaker failure protection, P1 D
lays which add a small time delay (BFT) to logic circuit O 3
the overall fault clearing time. R
This is in particular the case with 1-and-
P2
1/2-breaker or ring bus arrangements P1 : primary P2 : alternate
where a separate breaker failure relay protection protection
(7SV600 or 7SV512) is used per breaker
(see application example 10).
Fig. 125 4
The deciding criterion of BF protection
time coordination is the reset time of the
current detector (50BF) which must not be
exceeded under any condition of current
interruption. The reset times specified in Fault incidence BFI =
breaker failure
the Siemens digital relay manuals are valid Normal interrupting time initiation time 5
for the worst-case condition: interruption (intermediate
of a fully offset short-circuit current and Current relays, if any)
low current pick-up setting (0.1 to 0.2 detector
(50 BF) BFT =
times rated CT current). Protect. Breaker inter. reset time Margin breaker failure
The reset time is 1 cycle for EHV relays tripping time
(7SA513, 7SV512) and 1.5 to 2 cycles for time time (auxilary relays,
6
(1~) (2,5~)
distribution type relays (7SJ***). (1~) (2~) [2,5~] if any)
[2~] [2~]
Fig. 126 shows the time chart for a typical [4~]
breaker failure protection scheme. The
stated times in parentheses apply for
(5~) (2~)
transmission system protection and the 0,5~ [8~] 0,5~ [4~] 7
times in square brackets for distribution
system protection.
BFI BF timer (F) (62BF) BFT Adjacent
breaker
Total breaker failure interrupting time int. time

(9~) [15~]
8

Fig. 126

10

Siemens Power Engineering Guide · Transmission and Distribution · 4th Edition 6/69

WWW.EECM.MIHANBLOG.COM
Power System Protection
Protection Coordination

High-impedance differential Differential relay Stability with external faults

protection: Verification of design The differential relay must be a high- This check is made by assuming an exter-
1 impedance relay designed as sensitive nal fault with maximum through-fault
current relay (7VH80/83: 20 mA) with current and full saturation of the CT in the
The following design series resistor. If the series resistor is faulted feeder. The saturated CT ist then
data must be established: integrated in the relay, the setting values only effective with its secondary winding
may be directly calibrated in volts, as with resistance RCT, and the appearing relay volt-
2 CT data the relays 7VH80/83 (6 to 60 V or 24 to age VR corresponds to the voltage drop of
The CTs must all have the same ratio and 240 V). the infeeding currents (through-fault
should be of low leakage flux design ac- current) at RCT and RL. The current at the
Sensitivity
cording to Class TPS of IEC 44-6 (Class X relay must under this condition safely stay
of BS 3938). The excitation characteristic For the relay to operate in case of an inter- below the relay pickup value.
and the secondary winding resistance are nal fault, the primary current must reach a In practice, the wiring resistances RL may
3 to be provided by the manufacturer. minimum value to supply the set relay not be equal. In this case, the worst
The knee-point voltage of the CT is required pickup current (IR-set), the varistor leakage condition with the highest relay voltage
to be designed at least for two times the current (Ivar) and the magnetizing currents (corresponding to the highest relay current)
relay pick-up voltage to assure dependable of all parallel-connected CTs (n·ImR). must be sought by considering all possible
operation with internal faults. Low relay voltage setting and CTs with low external feeder faults.
magnetizing demand therefore increase
4 the protection sensitivity.
Setting
The setting is always a trade-off between
1 2 3 n sensitivity and stability. A higher voltage
Voltage limitation by a varistor setting leads to enhanced through-fault
is required if: stability, but, also to higher CT magnetizing
5 RCT RCT RCT RCT
and varistor leakage currents resulting con-
sequently in a higher primary pickup cur-
VRmax = 2 2VKN (VF –VKN) > 2kV
rent.
RL RL RL RL IFmax Through A higher voltage setting also requires a
with VF = (RCT + 2·RL + RR) higher knee-point voltage of the CTs and
N
therefore greater size of the CTs.
6 Fig. 129 A sensitivity of 10 to 20% IN is normal for
motor and transformer differential protec-
RR tion, or for restricted ground-fault protection.
Varistor
With busbar protection a pickup value
87B Calculation example: ≥ 50 % IN is normally applied.
An increased pickup value can be achie-
7 Given: n = 8 feeders
ved by connecting a resistor in parallel to
Fig. 127 N = 600/1 A the relay.
VKN = 500 V
Varistor
RCT = 4 Ohm
Sensitivity: ImR = 30 mA (at relay setpoint) Voltage limitation by a varistor is needed if
8 peak voltages near or above the insulation
IFmin = N·(IRset + Ivar + n·ImR) RL = 3 Ohm (max.) voltage (2 kV) are to be expected. A limita-
Stability: IRset = 20 mA tion to 1500 V rms is then recommended.
RR RR = 10 kOhm This can be checked for the maximum in-
IFThrough max < N· ·I ternal fault current by applying the formula
RL + RCT Rset IVar = 50 mA (at relay setpoint)
shown for VR-max.
N = CT ratio
9 Sensitivity: A restricted ground-fault protection may
IRset = Set relay pickup current normally not require a varistor, but, a bus-
IVar = Varistor spill current IFmin = N·(IRset + Ivar + n·ImR) bar protection in general does.
ImR = CT magnetizing current at The electrical varistor characteristic can be
IFmin = 600 ·(0.02 + 0.05 + 8·0.03) expressed as V=K·IB. K and B are the varis-
relay pickup voltage 1
tor constants.
10 V IFmin = 186 A (31% IN)

VKN Stability:
VKN =CT knee
point voltage RR Relay K B Varistor
IFmaxThrough < N· ·I
RL + RCT Rset setting type
VR =RR·IRset
VR VKN ≥ 2·VR IFmax Through < 600 · 10,000 ·0.02 V rms
1 3+4
≤125 450 0.25 600A/S1/S256
IFmax Through < 17 kA (28·IN)
ImR Im 125–240 900 0.25 600A/S1/S1088

Fig. 128 Fig. 130 Fig. 131

6/70 Siemens Power Engineering Guide · Transmission and Distribution · 4th Edition

WWW.EECM.MIHANBLOG.COM

You might also like