RATE ANALYSIS FOR BRICKWORK

Downloaded from TheConstructor.Org

Wall Dimensions Length Width Height Area m2 Vol. m3


Half Brick Wall 16.0 m 0.0 m 0.5 m 7.2 0.828

Full Brick Wall 1.0 m 1.0 m 1.0 m 1.0 1.000

C/S Mortar Ratio 1 :4

Dry Mortar Qty 0.71

MATERIAL Qty. TK /Unit

Bricks 494 8
Cement Bags 6.53 500
Sand m 3
0.91 2500

LABOUR With Hand Mixing of Mortar Days

MASON 0.94 300


LABOUR 1.37 250
BAHISHTI (Water Carrier) 0.20 200

Prime Cost 10144.53

Scafolding
@2% of prime cost

Sundries
@3% of prime cost

CONTRACTOR PROFIT
Contractor Profit 15

TOTAL COST (TK) 12,24


AMT SUBTOT
(TK) AL (TK)
3952.00
3263.30
2264.73
9480.03

282
343
40

664.50

Amount
202.89
202.89

Amount
304.34
304.34

% 1597.76

12,249.52