KWASA Land, Plot C8 - Cost Saving Estimate on Slope Option

Item 1 - Extra Cost for Slope Option


Rate Amount
Descriptions Unit Quantity
(RM/unit) (RM)

Extra Excess Cut Due to Forming of Slope


a. m3 40,000 15.00 600,000.00
Along Boundary
b. Extra Pile Wastage for SP450 m 504 310.00 156,240.00
c. Extra Pile Wastage for SP600 m 438 140.00 61,320.00
817,560.00

Item 2 - Omission of RC Wall


Rate Amount
Descriptions Unit Quantity
(RM/unit) (RM)
a. Concrete (wall & base) m3 1,251 380.00 475,380.00
3
b. Lean concrete m 54 285.00 15,390.00
c. Rebar kg 313,076 3.50 1,095,766.00
d. Formworks m2 3,690 40.00 147,600.00
e. Waterstop m 236 30.00 7,080.00
f. Waterproofing system m2 2,789 40.00 111,560.00
1,852,776.00

Saving (Item 2 - Item 1) = 1,035,216.00