SADDLE SUPPORT ( 8.4 M X 3.

25 M )
SCOPE OF WORK Quantity Unit Price Total Unit Price(Pesos)
1. EXCAVATION WORKS 1 lot 7200 7200
2. MANPOWER
Foreman 1 man 16800 16800
Mason 1 man 14400 14400
Helper 1 1 man 12000 12000
Helper 2 1 man 12000 12000

3. CONCRETING
40 kgs.Cement 67 bags 300 20100
Sand 5 cu.m 1440 7200
3/4 " Gravel 10 cu.m 1320 13200

4. REINFORCEMENT
86 pcs -12 mm dia. X 6 m. bars 458.112 kgs 79.2 36282.4704
76 pcs -10mm dia. X 6 m. bars 281.141 kgs 74.4 20916.8904
# 16 Tie wire 15 kgs 72 1080

5. CARPENTRY
2''X2''X 8' LUMBER 5 pcs 324 1620
4'X8'X 1/2'' PLYWOOD 4 pcs 1140 4560
1'' Cw Nails 4 kgs 57.6 230.4

6. CONSUMABLES 1 lot 10000 10000

TOTAL FOR ITEMS (1-6) 213,107.71


213107.7