ONE STOREYED R.

C BUILDING

Actual Bill of Ouantity

No Particular Quantity Per Rate Amount (Ks)

1 Cement 198 Bags 9900 1,960,200

2 Shingle 9.62 Sud 90000 865,800

3 Brick 8500 No 210 1,785,000

4 Sand 9.7 Sud 30000 291,000

5 Sand Filling 10 Sud 30000 300,000

6 Jungle Wood 0.5 Ton 2200000 1,100,000

7 5 Ply Wood 22 Sht 19500 429,000

8 Nails 3 Nos 5200 15,600

9 Ø 16 mm M.S Rod 2 Ton 1750000 3,500,000

10 Ø 10 mm M.S Rod 1 Ton 1720000 1,720,000

11 Ø 8 mm M.S Rod 6 Coils 126500 759,000

12 18 G Binding Wire 3 Coils 120000 360,000

13 Anchor Bolt 24 Nos 3400 81,600

14 12 mm MS Plate 9" x 9" 6 Nos 12600 75,600

15 H 150 x 75 (12 m) 2 Nos

Total Materials Cost 13,242,800