You are on page 1of 1

BOQ Summary Page 1 of 1

BOQ SUMMARY

Project Name: MMC

Element :  Beam

No. Material Unit Quantity Rate र Cost र


1 Concrete M40 (cum) 42.54 8000.00 340317
Sub Total 42.54 3,40,316

2 Rebar T8 (Fe500) (kg) 1014.04 60.00 60842


3 Rebar T10 (Fe500) (kg) 46.18 60.00 2771
4 Rebar T12 (Fe500) (kg) 144.44 60.00 8666
5 Rebar T16 (Fe500) (kg) 2427.50 60.00 145650
6 Rebar T20 (Fe500) (kg) 452.54 60.00 27152
7 Rebar T25 (Fe500) (kg) 812.26 60.00 48736
8 Rebar T32 (Fe500) (kg) 826.04 60.00 49562
Sub Total 5722.99 3,43,379

9 Shuttering (sq.M) 228.45 600.00 137072


Sub Total 1,37,071

Grand Total 8,20,768

Design Metrics
1 Consumption : Reinforcement/Concrete ratio = 134.53 kg/cum
2 Concrete % M40 = 100.00 % 
3 Shuttering  = 5.37 sqm/cum