You are on page 1of 12

SEAOC 2012 CONVENTION PROCEEDINGS

ASCE 41-13: Seismic Evaluation and Retrofit Rehabilitation of


Existing Buildings

Robert Pekelnicky, SE
Degenkolb Engineers
San Francisco, CA

Chris Poland, SE, NAE


Degenkolb Engineers
Oakland, CA

Abstract nonlinear analysis of all types of building structures were


provided. Prior to those documents, seismic evaluation and
For the past 3 years the ASCE/SEI Standards Committee on retrofit was left solely to the judgment of the practitioner as
Seismic Rehabilitation has been working to combine ASCE he or she attempted to use standards intended for new
31-03 into ASCE 41-06 while also updating both standards. building design to evaluate and retrofit existing buildings.
The result of that humongous effort is the soon-to-be released
ASCE 41-13: Seismic Evaluation and Retrofit of Existing Following the publication of both ATC 14 and FEMA 273,
Buildings. The new combined standard has eliminated any the Federal Emergency Management Agency (FEMA) began
inconsistencies that previously existed between the two to support efforts to transition those documents from
standards. Now the user decides if they want to go forward guidelines into national standards. Those efforts produced
with lower performance objectives traditionally used for updated documents in pre-standard form (FEMA 178, 1992;
existing buildings, as was the case within ASCE 31 or an FEMA 310, 1998; and FEMA 356, 2000). In addition to
equivalent hazard to a new building, similar to the Basic altering the text of those documents to be enforceable
Safety Objective in ASCE 41. In addition, the Tier 1 standards language, many technical updates were also
checklists have been significantly modified and reorganized. incorporated. Also, the displacement based analysis
The use deficiency-only procedures (Tier 2) have been procedures from FEMA 273 were simplified and
greatly expanded to regular buildings of greater heights. incorporated into FEMA 310 to bring some consistency to the
Plus, there have been a number of significant technical two documents.
changes including updated analysis provisions with more
emphasis on nonlinear response history analysis, provisions The standardization efforts culminated with the publication of
for bucking restrained braced frames, expanded liquefaction ASCE 31-03 Seismic Evaluation of Existing Buildings in
provisions, a new foundation rocking analysis procedure, 2003 and then in 2006 with ASCE 41-06 Seismic
substantially updated URM provisions, and a full updated Rehabilitation of Existing Buildings. These documents were
Chapter on Seismic isolation and Energy dissipation. produced following ASCE’s standards development process,
which required significant balloting of both pre-standard
documents through a diverse committee of practitioners,
Introduction academics, and industry representatives followed by a public
comment period. All comments made throughout the process
ATC 14 (1987) and FEMA 273 (1997) were both landmark were responded to by the ASCE/SEI Standards Committee on
documents. Each represented major turning points in how the Seismic Rehabilitation. In one instance significant public
profession addressed evaluating the seismic hazards posed by comments to ASCE 41-06 led to the publication of a
existing buildings and mitigating those hazards through supplement to that document (ASCE, 2008).
retrofit. ATC 14 created the concept of screening buildings
for potential deficiencies which had been observed in similar From ATC 14 through ASCE 31-03 and from FEMA 273
buildings in major earthquakes to increase a building’s risk to through ASCE 41-06, these documents have found
life safety. FEMA 273 was the first time that “displacement- widespread use throughout the profession, especially in
based” methodologies were set forth and guidelines for California and within the Federal Building Standards RP4,

1
RP6 and RP 8. Regulatory agencies, such as OSHPD and technical updates to ASCE 41 should be made, another was
DSA, public building owners, such as the US General Service tasked with looking at what updates and simplifications could
Administration, and the Department of Veterans Affairs, be made to the ASCE 31 Tier 1 screening, and the last was
have directly referenced or permitted the use of these tasked with determining if the documents should be
documents to evaluate and retrofit existing buildings. combined or stay as separate, but well-coordinated standards.
Once the ASCE 41 subcommittee determined the technical
As the documents were used more and more, inconsistencies updates needed, it created technical issue teams to address all
were discovered between ASCE 31 and ASCE 41. Many of of those updates.
the inconsistencies were intentional. The most significant
being the ingrained philosophy that existing buildings should Combined Standard
be given a break when being evaluated and therefore not be
held to the same standards as a new building. While another The committee chose to combine the standards into one
philosophy held that if someone choses to carry out a seismic document and coordinate the evaluation and retrofit
retrofit, they should do so to a performance level procedures. The combined standards retains the three-tired
commensurate with a new building unless some other approach found in ASCE 31-03, while relying on the
performance objective is intentionally and explicitly chosen. technical provisions in ASCE 41-06 as the basis for all the
Other inconsistencies were created because of the analytical procedures.
simplification of the ASCE 41 analysis procedures and
member acceptance criteria in ASCE 31. Lastly, The Tier 1 Screening is essentially the same as it was in
inconsistencies were created because the base documents, ASCE 31-03, with some reorganization and technical changes
ATC 14 and FEMA 273, were transitioned into standards to the checklists. Those changes are discussed in more detail
documents on different schedules, out of phase with each later in the paper. The Screening is still intended as the first
other, with some differences in the committee membership pass that one would make through the building to get familiar
making those revisions. with it. It is intended only to be used as an evaluation method
and not for retrofit design.
Another issue of consternation within the profession was the
inconsistencies between ASCE 41 and ASCE 7 (2010). The Tier 2 “Deficiency-Based” procedure is now intended to
Many of these inconsistencies had been known since the be used for either evaluation or retrofit. As before, the user
publication of FEMA 273 and relate to the fundamentally can go further in evaluating all the potential deficiencies
different applications of the two standards. The different identified in the Tier 1 screening or simply chose to fix those
applications led to differences in procedures between the two potential deficiencies with a retrofit design. Unlike ASCE
documents. Because ASCE 7 was written for use in the 41-06, there is no difference in building size when a
design of new structures, it can employ “force-based” deficiency-based retrofit can be used versus when a
procedures which utilize a global building ductility factor, the deficiency-only evaluation can be performed. Previously the
R-factor, based on the details of construction. ASCE 41 uses retrofit requirements were significantly more restrictive.
“displacement-based” procedures which assess the ductility
of each element action (shear, flexure, etc.) individually In order to eliminate inconsistencies within the document, the
because the ductility of the individual elements in the specific Tier 2 analysis procedures and ASCE 31-03m-factors
structural system may not be consistent with each other. were eliminated. The user is pointed to the subsequent
Irrespective of discrepancies within procedures, the intended sections of the standard that are used for Tier 3 for analysis
performance objective for a typical Risk Category II building procedures and m-factors. The benefit to this is that there is
is the same in ASCE 7 as the Basic Safety Objective in ASCE no difference between Tier 2 and Tier 3 in terms of force
41. Also, because ASCE 7 does not contain specific demands or member acceptance criteria. The only issue with
guidance on the use of nonlinear analysis procedures, ASCE this is that users of ASCE 31-03 who are not familiar with
41 has often been used as the basis for new building designs ASCE 41 procedures may find it difficult at first due to all the
which utilized nonlinear analyses. additional material they have to read and greater number of
possible m-factors. The committee made every possible
When the standards committee met in December 2009 to effort to alleviate this by providing a detailed flow chart and
kick-off the update cycle for ASCE 31 and 41, the specific pointers throughout the chapter that contains the Tier
aforementioned inconsistencies were at the forefront of 2 procedures to the appropriate sections in the rest of the
everyone’s mind. Another topic that garnered a lot of standard. The benefit, of course, is a better analysis because it
discussion was a proposition to combine ASCE 31 and 41 is more specific.
into one standard. At that meeting, the committee broke up
into 3 subcommittees. One was tasked with looking at what

2
In merging the two documents, the committee felt that the building in an altered state and adjusting the alterations until
“Full-Building” Tier 2 in ASCE 31-03 was really no different the building’s evaluation meets the desire performance
than a systematic evaluation. Since the Tier 3 procedure was objective. Therefore there is no difference between a Tier 2
thought to be a systematic (as opposed to deficiency-based) or Tier 3 evaluation or retrofit. The analysis procedures and
evaluation or retrofit, it was felt that there was no need for acceptance criteria are the same. If the user wishes to carry
this separate procedure. Therefore the “Full-Building” Tier 2 out an evaluation or retrofit with the intention of accepting
procedure was eliminated, so Tier 2 now only refers only to higher risk of collapse or lesser performance, as was the case
“Deficiency-Based” procedures and where one would with ASCE 31-03, then the user must now explicitly choose
previously have performed a “Full-Building” Tier 2, they a lesser seismic hazard or a lesser performance level.
now perform a Tier 3 evaluation.

The Tier 3 procedure is intended to be a systematic analysis New Earthquake Hazard Parameters
of the building, which can be used either for evaluation or
retrofit. The Tier 3 procedure encompasses all four analysis As discussed earlier, it has been a commonly accepted within
(Linear Static, Linear Dynamic, Nonlinear Static, and the profession to evaluate existing buildings to a lower force
Nonlinear Dynamic) procedures from ASCE 41-06. The user level than new buildings. The most common way this was
can chose to apply any procedure, subject to specific carried out was to use 75% of new building design forces.
limitations for each procedure. However, the permission to That concept was contained with ATC-14 and carried through
use a new building design standard for Tier 3, which was to ASCE 31-03. In the Tier 2 procedures in ASCE 31-03 the
permitted in ASCE 31-03, has been eliminated because the 75% factor was actually buried within the m-factors. Those
new building standard cannot be properly applied to an m-factor were approximately 1.33 (1/0.75) times their ASCE
existing building unless a completely new structural system is 41-06 counterparts, with some additional simplifications.
provided. Then in the Tier 3 procedure of ASCE 31-03, the user was
explicitly directed to use a standard such as ASCE 41-06 or
The outline of the new standard is as follows: ASCE 7-05 and multiply the demand forces by 0.75.

Chapter 1 General Requirements The committee agreed that the philosophy of permitting
Chapter 2 Seismic Performance Objectives and existing buildings to be evaluated, and even upgraded, to a
Ground Motions lower hazard should be retained. There are a number of
Chapter 3 Evaluation and Retrofit Requirements reasons for this, which are discussed in detail in the ASCE
Chapter 4 Tier 1 Screening . 41-13 Chapter 2 commentary. They are:
Chapter 5 Tier 2 Deficiency-Based Evaluation and
Retrofit • Permitting buildings recently built to not be
Chapter 6 Tier 3 Systematic Evaluation and Retrofit immediately rendered deficient when there are
Chapter 7 Analysis Procedures and Acceptance minor changes to the new design standards.
Criteria
Chapter 8 Foundations and Geologic Site Hazards • The increased risk due to the lower hazard is
Chapter 9 Steel acceptable because of the presumption that an
Chapter 10 Concrete existing building has a shorter remaining life than a
Chapter 11 Masonry new building.
Chapter 12 Wood and Cold-Formed Steel
Chapter 13 Architectural, Mechanical, and Electrical • The cost of retrofitting to achieve commensurate
Components performance can be disproportional to the increased
Chapter 14 Seismic Isolation and Energy Dissipation benefit as opposed to doing something to make the
Chapter 15 System-Specific Performance Procedures building better by mitigating the most egregious
Chapter 16 Tier 1 Checklists deficiencies.
Appendix A Guidelines for Deficiency-Based
Procedures With the decisions to retain the philosophy of allowing
Appendix B Use of ASCE 41-13 within Mitigation existing buildings to be evaluated and possibly upgraded to a
Programs lower hazard than new buildings, the question then became
what that hazard should be. While the 0.75-factor has been
The new standard is based on the philosophy that engrained within the profession for many years, it is
procedurally there is no difference between evaluation and somewhat arbitrary. The committee chose to follow the path
retrofit design. Retrofit design is simply evaluating a put forth in the 2010 California Building Code in the section

3
on accepted seismic performance for state-owned building
which utilized different return period seismic hazard The committee chose to retain the BSE-X designation for the
parameters instead of the 0.75-factor. seismic hazards. Therefore, the 5%/50 hazard was named the
BSE-2E and the 20%/50 hazard was named the BSE-1E. The
In Section 3417 of the CBC two reduced earthquake hazards suffix “E” was introduced to designate that these are reduced
are stipulated to correspond to the BSE-1 and BSE-2 hazards hazards associated with existing buildings.
in ASCE 41-06.
Since ASCE 41-06 had a performance objective that was
In ASCE 41-06 the BSE-2 hazard is the same as the ASCE 7- commensurate with what was commonly accepted for new
05 Maximum Considered Earthquake (MCE), which is an buildings, the committee felt it important to retain the option
earthquake with a 2% probability of exceedance in 50 years to have performance objectives equivalent to new buildings
(a 2,475-year return period), 150% of the mean deterministic standards. Therefore the committee chose to include a
earthquake, or some pre-determined “water-level” parameters second pair of seismic hazard parameters which would be the
(see Part 2 of the 2009 NEHPR for discussion on the “water- Risk Adjusted MCE (MCER) and the Design Basis
level” parameters). The BSE-1 is the lesser of an earthquake Earthquake (DBE) from ASCE 7-10. These hazards were
with a 10% probability of exceedance in 50 years (a 475-year named the BSE-2N and BSE-1N respectively, with the “N”
return period) or 2/3 of the BSE-2 parameters. suffix indicating new building standards equivalent hazards.

The stipulated reduced hazard for existing state owned Table 1 shows the short period, SXS, parameter for the four
buildings in the 2010 CBC is an earthquake with a 5% different hazards and Table 2 shows the long period, SX1,
probability of exceedance in 50 years (a 975-year return parameter for the four different hazards. These unpublished
period) for the BSE 2 and for the BSE-1 is an earthquake results were produced by Nico Luco at USGS for the
with a 20% probability of exceedance in 50 years (a 225-year Committee.
return period).
Table 1 – Short Period Hazard Parameters
BSE-2N BSE-2E BSE-2 BSE-1N BSE-1E BSE-1
Region City
MCER 5%-50yr E/N 2/3 x MCER 20%-50yr E/N
Los Angeles 2.40 1.76 0.73 1.60 0.84 0.53
Northridge 1.69 1.46 0.87 1.13 0.81 0.72
Southern California

Long Beach 1.64 1.18 0.72 1.10 0.57 0.52


Irvine 1.55 1.04 0.67 1.03 0.53 0.52
Riverside 1.50 1.29 0.86 1.00 0.79 0.79
San Bernardino 2.37 2.39 1.01 1.58 1.28 0.81
San Luis Obispo 1.12 0.78 0.70 0.74 0.39 0.52
San Diego 1.25 0.85 0.68 0.84 0.31 0.37
Santa Barbara 2.83 2.16 0.76 1.89 0.87 0.46
Ventura 2.38 1.73 0.73 1.59 0.82 0.52
Oakland 1.86 2.14 1.15 1.24 1.19 0.96
Northern California

Concord 2.08 2.06 0.99 1.38 1.08 0.78


Monterey 1.53 1.11 0.72 1.02 0.54 0.53
Sacramento 0.67 0.45 0.67 0.45 0.27 0.60
San Francisco 1.50 1.51 1.00 1.00 0.85 0.85
San Mateo 1.85 1.71 0.93 1.23 0.85 0.69
San Jose 1.50 1.58 1.05 1.00 0.97 0.97
Santa Cruz 1.52 1.23 0.81 1.01 0.67 0.67
Santa Rosa 2.51 2.39 0.95 1.67 1.02 0.61

4
Table 2 – Long Period Hazard Parameters
BSE-2N BSE-2E BSE-2 BSE-1N BSE-1E BSE-1
Region City
MCER 5%-50yr E/N 2/3 x MCER 20%-50yr E/N
Los Angeles 0.84 0.61 0.72 0.56 0.30 0.69
Northridge 0.60 0.51 0.85 0.40 0.29 0.73
Southern California

Long Beach 0.62 0.43 0.69 0.41 0.21 0.70


Irvine 0.57 0.38 0.66 0.38 0.20 0.73
Riverside 0.60 0.51 0.85 0.40 0.30 0.75
San Bernardino 1.08 1.02 0.94 0.72 0.51 0.70
San Luis Obispo 0.43 0.30 0.71 0.28 0.15 0.70
San Diego 0.48 0.31 0.65 0.32 0.13 0.67
Santa Barbara 0.99 0.74 0.75 0.66 0.31 0.61
Ventura 0.90 0.64 0.71 0.60 0.30 0.67
Oakland 0.75 0.79 1.06 0.50 0.43 0.86
Northern California

Concord 0.73 0.71 0.97 0.49 0.37 0.75


Monterey 0.56 0.40 0.72 0.37 0.19 0.68
Sacramento 0.29 0.20 0.68 0.20 0.12 0.77
San Francisco 0.64 0.62 0.97 0.43 0.32 0.75
San Mateo 0.86 0.72 0.84 0.57 0.32 0.64
San Jose 0.60 0.55 0.92 0.40 0.33 0.82
Santa Cruz 0.60 0.46 0.77 0.40 0.24 0.69
Santa Rosa 1.04 0.97 0.94 0.69 0.40 0.60

As can be seen from the tables there are some locations performance objectives, ASCE 41-13 retains the Enhanced
where the ratio of new to existing demand is close to .75; Performance Objective and Limited Performance Objective
showing little change. There are isolated cases where it is categories.
higher or lower. . This is a consequence primarily of the
deterministic caps imposed on the ASCE 7-10 MCER. The The Basic Performance Objective for Existing Buildings
committee felt that obviously the “E” hazard should never be (BPOE) uses the BSE-1E and BSE-2E hazard levels. Unlike
greater than the “N” hazard, and thus the “E” hazards would ASCE 41-06, the BPOE is not a single performance
be capped at the “N” hazard values. The committee did not objective, but rather a table of different performance
believe that a different deterministic cap for the “E” hazards objectives based on the Risk Category that would be assigned
was appropriate. For regions where there is little to no to a building. The decision to map the performance
difference between the BSE-2N and BSE-2E, it was believed objectives to Risk Categories was made because the
that signified the seismic hazard to be great enough that the widespread use of ASCE 31-03 and ASCE 41-06 had led to
existing buildings should not be given the traditional break. numerous building codes, various federal state and local
jurisdictions, and engineers to do their own mapping of the
Risk Categories to performance objectives, without
ASCE 41-13 Performance Objectives consistency. The committee felt that it was important for
there to be some standardization of this practice and therefore
The concept of marrying seismic hazard levels with structural it was brought into the BPOE. Table 3 summarizes the
and nonstructural performance levels to create a performance BPOE.
objective was retained in ASCE 41-13. Both ASCE 31-03
and ASCE 41-06 had various performance objectives set This set of performance objectives are intended to be the one
forth explicitly. ASCE 41-13 has two sets of explicitly that approximates the performance objectives within ASCE
defined performance objectives, the Basic Performance 31-03 which accepted a higher level of risk. The BPOE is
Objective for Existing Buildings (BPOE) and the Basic used for all three tiers of evaluations. With Tier 1 and Tier 2
Performance Objective Equivalent to New Building only requiring evaluation at the BSE-1E level and Tier 3
Standards (BPON). In addition to those two sets of explicit requiring evaluation at both the BSE-1E and BSE-2E levels.

5
SEAOC 2012 CONVENTION PROCEEDINGS

Table 3 – Basic Performance Objective for Existing Buildings (BPOE)


Tier 1 Tier 2 Tier 3

Risk Category BSE-1E BSE-1E BSE-1E BSE-2E

Collapse Prevention
Life Safety Structural Life Safety Structural
Life Safety Structural Structural Performance
Performance Performance
I & II Performance Nonstructural
Life Safety Nonstructural Life Safety Nonstructural
Life Safety Nonstructural Performance Not
Performance Performance
Performance (3-C) Considered
(3-C) (3-C)
(5-D)

Damage Control Structural Limited Safety


See Note 1 for Structural Damage Control Structural
Performance Structural Performance
Performance Performance
Position Retention Nonstructural
III Position Retention Position Retention
Nonstructural Performance Not
Nonstructural Performance Nonstructural Performance
Performance Considered
(2-B) (2-B)
(2-B) (4-D)

Immediate Occupancy Life Safety Structural


Immediate Occupancy Immediate Occupancy
Structural Performance Performance
Structural Performance Structural Performance
Position Retention Nonstructural
IV Position Retention Position Retention
Nonstructural Performance Not
Nonstructural Performance Nonstructural Performance
Performance Considered
(1-B) (1-B)
(1-B) (3-D)

The reason that Tier 1 and Tier 2 only need to have one configuration was developed which must be met in order for
seismic hazard check while Tier 3 requires a check of two one to be able to use the deficiency-based provisions.
hazard levels relates to the fundamental basis of the
deficiency-based procedures. The deficiency-based However, for a Tier 3 systematic procedure which is intended
procedures are based on decades of observations of actual to be used universally regardless of the building
damage to buildings in major earthquakes worldwide. The configuration, size or structural system, the dual-earthquake
original documentation is contained in ATC 14. Because of a check is necessary to ensure sufficient robustness and margin
lack of specific strong motion records, all events were of safety beyond the design-level earthquake. This covers
considered equal even though many were likely BSE 2 level those buildings which are outside of the historic data.
events. It is fair to conclude that since the procedures were
calibrated to a BSE 1 level event and many of the buildings The concept of permitting the user to perform a seismic
actually experienced a BSE 2 level events successfully, only retrofit or target an evaluation to a level greater or less than
a one level check would be needed. the Basic Performance Objective has been retained. The
Enhanced Performance Objective remains as any level
It is important to recognize that the inventory of damaged greater than the BPOE. Some example application of an
buildings used to infer the deficiency-based procedure was Enhanced Performance Objective are retrofitting for a Risk
mostly of moderate size and height. The committee felt that a Category higher than the building would normally be
similar limitation was needed to designate when the assigned, an evaluation using a higher seismic hazard than
deficiency-only procedures could be used. A number of stipulated, or a retrofit to a higher structural or nonstructural
criteria regarding the building’s size, structural system, and performance level using the same earthquake hazards as the
BPOE table calls for.

6
are based on the Risk Category that would be assigned to the
ASCE 41-13 retains the Limited Performance Objective and building based on the applicable building code or ASCE 7.
keeps the two specific subsets – Reduced Performance Table 4 presents the BPON.
Objective and Partial Retrofit Objective. The Reduced
Performance Objective is the opposite of the Enhanced Because the BPON is designed to be equivalent to a new
Performance Objective. The evaluation or retrofit targets a building, only a full-building systematic evaluation or
performance level, uses a seismic hazard, or is for a Risk upgrade can be used. The seismic hazards used for this
Category less than the BPOE. The Partial Retrofit Objective performance level are the BSE-1N and BSE-2N. While there
means that some, but not all of the seismic deficiencies are have not been definitive studies done on the specific
mitigated. equivalence between the two standards, the committee felt
that by targeting Collapse Prevention in the MCER, one is
A new performance objective included in ASCE 41-13 is the achieve the similar performance to what is spelled out in the
Basic Performance Objective Equivalent to New Building commentary in the 2009 NEHRP Provisions. Specifically,
Standards (BPON). This set of performance objectives is Table C11.5-1 in the 2009 NEHRP Provisions was used as
intended to provide a link between ASCE 7 and ASCE 41 the basis for the BPON.
when a seismic evaluation or upgrade is required to be
equivalent to a new building. The performance objectives

Table 4 – Basic Performance Objective Equivalent to New Building Standards (BPON)


Seismic Hazard Level
Risk Category BSE-1N BSE-2N

Life Safety Structural


Collapse Prevention Structural
Performance;
Performance;
I & II
Position Retention Nonstructural
Nonstructural Performance Not
Performance
Considered
(5-D)
(3-B)

Damage Control Structural Limited Safety Structural


Performance; Performance;

III Position Retention Nonstructural Nonstructural Performance Not


Performance Considered

(2-B) (4-D)

Immediate Occupancy Structural Life Safety Structural


Performance; Performance;

IV Operational Nonstructural Nonstructural Performance Not


Performance Considered

(1-A) (3-D)

7
Structural Performance Levels
The Life Safety performance level is where nonstructural
The three main structural performance levels, Immediate components are damaged and dislodged from their position,
Occupancy (IO), Life Safety (LS), and Collapse Prevention but the consequences of the damage do not pose a risk to life
(CP) have not been changed from ASCE 41-06. There are, safety. Major falling hazards are still anchored. The ASCE
however, two new, specifically defined, performance levels – 41-13 Life Safety level is significantly less than what was
Damage Control and Limited Safety. Those new levels were termed Life Safety in ASCE 31-03 and 41-06. To determine
necessary to describe the target structural performance levels what was a true life safety hazard the committee relied upon
for Risk Category III structures in both the BPOE and FEMA-E74 (2011) and their collective experiences observing
BPON. Damage Control is the level halfway between IO and damage following major earthquakes.
LS and Limited Safety is the level halfway between LS and
CP.
Deficiency-Based Procedures
The performance ranges between IO and LS and LS and CP,
which were defined in ASCE 41-06 as Damage Control and There were many updates to the deficiency-based procedures.
Limited Safety, have been renamed Enhanced Safety The most significant update was the limitations on when
Performance Range and Reduced Safety Performance Range these types of procedures could be used. In ASCE 31-03,
in order to avoid the confusion with the newly created there was a table which indicated under which height Tier 1
performance levels. and deficiency-only Tier 2 Evaluation would be permitted.
There was a similar table in ASCE 41-06 Chapter 10 which
Nonstructural Performance Levels indicated when the simplified rehabilitation, which just
corrected ASCE 31-03 identified deficiencies, could be used.
There were significant changes to the nonstructural That concept was retained, but most of the height limits were
performance levels. There were two main reasons for the increased. Also, as stated earlier, the same table now applies
changes. The first was the recognition that many of the items to both evaluation and upgrade. Table 5 contains some
identified in ASCE 31-03 and ASCE 41-06 as life safety examples of the changes for systems in regions of high
hazard have never been documented in past earthquakes to seismicity.
actually be life safety hazards. The second one was the
realization that the performance levels in ASCE 31-03 and Table 5 – Height Limits for Deficiency-Base Procedures in
ASCE 41-06 did not match those in ASCE 7. High Seismicity for Life Safety Performance
ASCE 31-03 ASCE 41-06 ASCE 41-13
Steel
In ASCE 41-13, there are now only three specific Moment 3 3 8
nonstructural performance levels – Operational, Position Frames
Retention, and Life Safety. These revised performance levels Steel
simplify the nonstructural provisions in ASCE 41-13 and Braced 6 3 8
make them consistent with ASCE 7. Frames
Concrete
Not
The Operational performance level is the same as was Moment 6 8
Permitted
defined in ASCE 41-06. The nonstructural components are Frames
in a state following the earthquake such that they can resume Concrete
6 3 8
their pre-earthquake function. This performance level is Shear Walls
Light Frame 2 2 4
consistent with what the intended performance of
Tilt-up 2 2 2
nonstructural components should be when Ip = 1.5 in ASCE 7
URM No Limit 2 4
based on the 2009 NEHRP Provisions’ commentary.

The Position Retention performance level is where the The increase in height limits came primarily from the
nonstructural elements are damaged and may not function, additional experiences that have come from observing
but they are secured in place following the earthquake. This coming buildings in major earthquakes over the past 20 years.
performance level is intended to match the intended Prior to this update, theses tables had never really been
performance of nonstructural components when Ip = 1.0 in reviewed or revised since they were originally conceived in
ASCE 7 based on the 2009 NEHRP Commentary. This the mid 1990’s.
means that elements that do not require bracing per ASCE 7
because of the building being in a lower seismic hazard area Another major change was when mixed systems can be
will now not require bracing per ASCE 41-13. evaluated and retrofit using deficiency-based procedures. A

8
mixed system, in ASCE 41-13 context, is a system which has more specific way. Additionally, the change in the definition
different lateral force resisting elements in one direction. of Nonstructural Life Safety and coordination of levels of
Examples could be a tilt-up shear wall building with an seismicity with ASCE 7 led to a significant paring back of the
interior steel braced frame or a seven-story steel moment nonstructural Life Safety checklist.
frame over a three story concrete shear wall building. There
are now explicit provisions in ASCE 41 when you can Recognizing that existing buildings can vary from what their
consider those types of buildings in a deficiency-based drawings indicate due to construction deviations, alterations
evaluation or retrofit. When the mixed system is a or just deterioration, the committee added more detailed
horizontal combination of systems, the performance level is direction on minimum on-site investigation and condition
Life Safety or lower, the diaphragm is flexible, and the assessment. All the checklist statements related to condition
building is below the more restrictive height limit of the assessment have been moved to this section. The purpose of
different systems one can use the deficiency-based this section is to place the responsibility on the evaluating
procedures. For vertical combinations, the performance level engineer for verifying the condition of the structure and
is Life Safety or lower, and the building is below the more confirming the completeness and adequacy of the available
restrictive height limit of the different systems one can use drawings.
the deficiency-based procedures
The last major change to the Tier 1 Screening was an
Tier 1 Screening updating of the Benchmark Building table and an expansion
of the requirements for benchmarking a building. The table
There were major organizational changes to the Tier 1 which indicates what the earliest code a building could be
Checklists. A significant editorial effort was undertaken to designed to which permits it to be deemed to comply with a
simply and streamline the Tier 1 Screening. The first major specific performance objective was updated. Specifically, the
change was the creation of a Basic Configuration Checklist, benchmark year for concrete buildings was moved up from
which contains all the statements for Very Low seismicity, the 1976 UBC to the 1994 UBC due in part to observations
about building configuration regularity and the geologic and from the 2011 Christchurch Earthquakes. There were also a
foundation components, which were common to all building series of requirements set forth that one must meet in order to
types and unnecessarily repeated in each ASCE 31-03 benchmark a building. They relate to verifying the accuracy
checklist. Following that, there are checklists specific to each and completeness of the existing drawings with respect the
common building type. benchmark code, minimum field verification of the existing
drawings, condition assessment, and a confirmation of no
All the structural checklists were reorganized so that there is geologic hazards at the site.
one checklist for Life Safety and one separate, stand-alone
checklist for Immediate Occupancy for each common Tier 2 Evaluation/Retrofit
building type. Also, there are no longer separate checklists
for buildings with stiff or flexible diaphragms. Lastly, the Conceptually there were no major changes to the Tier 2
checklist statements are ordered such that the items for Low procedure. The crux of the procedure is still to simply
Seismicity come first, followed by Moderate and finally with evaluate the identified potential deficiencies from the Tier 1
High. Therefore someone evaluating a building in a region of screening or to retrofit them. The major change, however, is
Moderate seismicity need not read through a number of in the procedures used to do that.
statements that don’t apply.
As discussed earlier, in an effort to bring consistency to the
The nonstructural checklist was condensed down to one evaluation and retrofit procedures and for consistency
single checklist. Each checklist statement has a marker between Tier 2 and Tier 3, the simplified analytical methods
which indicates which level of seismicity and performance of ASCE 31-03 were abandoned for the more detailed
level (LS or IO) the statement is required to be checked for. procedures within ASCE 41. Recognizing that this was a
significant change, the chapter which presents the Tier 2
In addition to the editorial changes, there were a number of procedures was completely re-written to provide as much
technical updates to the checklists. Most of the technical guidance as possible to the specific sections of the analysis,
updates related to paring back the Life Safety checklist foundation, or material chapters where the user needs to go to
requirements. The committee undertook a detailed review of find the information to carry out the specific evaluation or
all the checklist statements, questioning whether each retrofit procedure for each specific deficiency.
statement was really an observed life safety issue or not. This
lead to a number of statements being moved from LS to IO-
only or being revised to address the life safety concern in a

9
The material found in Chapter 4 of ASCE 31-03 which significant update of the foundation rocking procedures and
provided commentary on the Tier 1 and Tier 2 deficiencies yielding at the soil-foundation interface. The last was an
has been retained, but moved to Appendix A. update to the soil-structure interaction provisions.

The most significant update to the liquefaction procedures is


Technical Updates a new three-step structural analysis procedure to assess the
consequences of liquefaction. Observations from the 2010
While the combination and reformatting of ASCE 31-03 and and 2011 Christchurch Earthquakes were that numerous
ASCE 41-06 took up a considerable amount of the structures were damaged by liquefaction, but did not collapse.
committee’s time, there were still a number of significant The new liquefaction analysis procedures allow the engineer
technical changes that were made to the provisions. Chapters to first evaluate the structure assuming no liquefaction occurs
8 through 14 contain the bulk of the analysis procedures, and then a second time with ground motions and foundation
material and foundation modeling parameters and acceptance parameters that have been altered due to liquefaction.
criteria. The format of those chapters is essentially Following that analysis, the anticipated lateral spread and
unchanged from ASCE 41-06. All the technical updates have differential settlements are imposed on the structure and it is
been incorporated into those chapters. assessed to determine if it can remain stable under those.

The following is a brief, high-level summary of the technical There has been a significant change to how foundation
changes to those chapters. rocking and yielding at the soil-foundation interface are
addressed. ASCE 41-06 decoupled the two actions and had
Analysis separate checks for each. In reality this never occurs. If the
soil is stiff, rocking will dominate the response. If the soil is
The most significant change to the analysis chapter was the soft, then yielding of the soil will govern. However, neither
expansion of the nonlinear response history analysis will occur independent of the other. The new rocking
provisions. There have been significant advances in this procedures provide m-factor tables and nonlinear acceptance
analysis method and it has found more widespread use within criteria for these actions as a function of the gravity load on
the profession since the provisions were originally written in the foundation and the stiffness of the underlying soil.
FEMA 273. The new provisions seek to clarify the number
of ground motion records needed, how to select and apply The soil-foundation-structure interaction (SFSI) material,
damping, and how to apply the output to evaluation. There which was first introduced in ASCE 41-06 and based on
was clarification made to permit the modeling of force- material from FEMA 440 (2005), was reviewed and revised.
controlled elements in the nonlinear model and permitting NIST funded a significant effort related to SFSI which will be
them to fail and allow force redistribution provided gravity published soon as ATC-84 (2012). Based on work done in
load support is not compromised. that project, the kinematic effects provisions (base-slab
averaging and embedment) were revised and some limitations
There were also some modifications made to allow for placed on them.
greater use of the linear procedures. In ASCE 41-06 there
were certain irregularities which prohibited the use of the Steel
linear procedures. Those irregularity triggers have been
relaxed. The only major changes to the steel section were the
introduction of provisions for buckling restrained braced
There was also a significant change made to the knowledge- frames and the modification of some of the acceptance
factor, which reduces the element capacities based on a lack criteria for braced frames.
of testing and other information about the building. Now if
the user has a good set of construction drawings and is Concrete
evaluating or upgrading to Life Safety or lower performance,
then the knowledge-factor can be taken as 0.9 instead of 0.75. There were only minor chances to the concrete chapter
related to minimum reinforcement in shear walls, biaxial
Geotechnical/Foundation column effects, rebar testing requirements and concrete core
sampling requirements.
There were three major updates to the Geotechnical and
Foundation chapter. The first was revisions to the Wood & Cold-Formed Steel
liquefaction section and a new structural analysis procedure
to assess the consequences of liquefaction. The second was a

10
The Wood and Cold-Formed Steel (CFS) Light Frame Consistency with ASCE 7
provisions had some formatting changes. Provisions for
wood and CFS were separated. Additionally, the applicable In addition to creating the BPON, referencing the MCER, and
reference standards where one can find capacities for wood aligning the nonstructural performance levels, the committee
and CFS elements were updated. made several changes to better align ASCE 41-13 with
ASCE 7. The most significant of those changes related to the
Masonry seismic hazard science, the site specific response spectra, and
response history scaling. Regardless of the return period
There were some significant changes to the masonry chapter, chosen for the seismic hazard, ASCE 41-13 requires the same
many of which were prompted by observations from the 2010 attenuation relations and other ground motion science be
and 2011 Christchurch Earthquakes. Bed joint sliding was used as is required in ASCE 7. The seismic hazard
reintroduced as a deformation-controlled action. The parameters should all be “Maximum Direction.” When a site
provisions and acceptance criteria for wall and pier rocking specific response spectrum is used, the scaling with respect to
were updated. There were also updates related to diagonal the USGS response spectrum will be the same as in ASCE 7.
tension, out-of-plane actions, and anchorage to masonry
walls. Another very significant change to align ASCE 41-13 with
ASCE 7-10 was the correlation of ASCE 41-13 Levels of
Seismic Isolation & Energy Dissipation Seismicity with the ASCE 7-10 Seismic Design Categories
(SDC). This eliminates confusion and helps greatly in the
Both the Seismic Isolation and Energy Dissipation provisions coordination of the nonstructural performance levels. Below
were revised. The provisions for Seismic Isolation were is the new ASCE 41 Levels of Seismicity with the
revised to permit the use of upper and lower-bound isolator corresponding ASCE 7 SDC.
properties in design and then specifying tolerances as
opposed to requiring testing of the isolators before design Very Low SDC A
could be completed. Along with this change were changes to Low SDC B
the quality control requirements for isolator manufacturers. Moderate SDC C
There were also modifications to the design and quality High SDC D, E, & F
control requirements for energy dissipation devices. Lastly,
the peer review requirements were reduced from a panel to There are some other modifications throughout ASCE 41 to
one independent peer reviewer. align with ASCE 7. The out-of-plane wall anchorage force
equations have been updated to correlate with the changes
that were made to ASCE 7-10. There were some changes
System-Specific Procedures made to align the nonlinear response history provisions of the
two standards.
One of the last changes to ASCE 41-13 was the creation of a
new chapter for system-specific procedures. The impetus for
this chapter was what to do about the special procedure for
unreinforced masonry buildings found in ASCE 31-03. That
procedure has been in use for many years and the committee Summary
wished to retain it. Because the procedure is specific to a
system which has a combination of elements of different When published, ASCE 41-13 will represent a new state of
materials, it could not be easily brought into any one of the the practice in seismic evaluation and retrofit of existing
material chapters. Therefore, it was placed in a new chapter. buildings. The new standard combines seismic evaluation
and retrofit into one document and brings consistency to the
The intention is that as more of these system specific process. The new standard has incorporated many technical
procedures are developed they would eventually be placed advances which have occurred in the past six years along
into this chapter. The requirement being that the procedure with lessons learned from many recent earthquakes.
must be able to be utilized in conjunction with a seismic
hazard level specified in the standard and the performance
target of the procedure must be declared in terms of one of
the levels in the standard.

11
Acknowledgements CBC, 2010, Title 24, California Code of Regulations, Part 2
– California Building Code, California Building Standards
Over 100 practitioners, academics, and industry Commission, Sacramento, California.
representatives participated in the ASCE/SEI Standards
Committee for Seismic Rehabilitation. Unfortunately space FEMA 178, 1992, NEHRP Handbook for Seismic Evaluation
prohibits listing everyone, but their names can be found in of Existing Buildings, Federal Emergency Management
ASCE 41-13. However the enormous effort that was Agency, Washington, D.C.
undertaken to combine and update the standards could not
have been accomplished without the painstaking volunteer FEMA 273, 1997, Guidelines to the Seismic Rehabilitation of
work of several key individuals. Peter Somers and Brian Existing Buildings, Federal Emergency Management
Kehoe each led subcommittees and were members of the Agency, Washington, D.C.
steering committee with the paper authors. Fred Turner,
Mark Moore, Chris Tokas, Charles Roeder, Ken Ellwood, FEMA 310, 1998, Handbook for the Seismic Evaluation of
Phil Line, Bonnie Manley, and Ron Mayes all led various Buildings: A Prestandard, Federal Emergency Management
technical issue teams. Mike Mahoney from FEMA provided Agency, Washington, D.C.
support for the effort which greatly moved the process along.
Jennifer Goupil, Jim Rossberg, Paul Sgambati, and Lee FEMA 356, 2000, Prestandard and Commentary for the
Kusek of the American Society of Civil Engineers were Seismic Rehabilitation of Buildings, Federal Emergency
instrumental in moving the standard along and allowed the Management Agency, Washington, D.C.
committee to meet its extremely aggressive schedule.
FEMA 440, 2005, Improvements of Nonlinear Static Seismic
Analysis Procedures, Federal Emergency Management
References Agency, Washington, D.C.

ASCE 31-03, 2003, Seismic Evaluation of Existing FEMA 750, 2009, NEHRP Recommended Seismic Provisions
Buildings, American Society of Civil Engineers, Reston, for New Buildings and Other Structures, Federal Emergency
Virginia. Management Agency, Washington, D.C.

ASCE 41-06, 2006, Seismic Rehabilitation of Existing FEMA E-74, 2011, Reducing the Risks of Nonstructural
Buildings, American Society of Civil Engineers, Reston, Earthquake Damage – A Practical Guide, Federal
Virginia. Emergency Management Agency, Washington, D.C.

ASCE, 2008, Supplement No. 1 to ASCE 41-06 Seismic


Rehabilitation of Existing Buildings, American Society of
Civil Engineers, Reston, Virginia.

ASCE 41-13, 2013 Publication Anticipated Seismic


Evaluation and Upgrade of Existing Buildings, American
Society of Civil Engineers, Reston, Virginia. Public
Comment Edition available through the American Society of
Civil Engineers.

ASCE 7-10, 2010, Minimum Design Loads for Buildings and


Other Structures, American Society of Civil Engineers,
Reston, Virginia.

ATC 14, 1987, Evaluating the Seismic Resistance of Existing


Buildings, Applied Technology Council, Redwood City,
California.

ATC 83, 2012, Soil-Foundation-Structure Interaction for


Building Structures. National Institute of Science and
Technology. Gaithersburg, Maryland.

12

You might also like