Professional Documents
Culture Documents
CIVIL/STRUCTURAL
TABLE OF CONTENTS
Page No
1.0 INTRODUCTION 3
1.1 General 3
1.2 Design Approach 3
1.3 Soils and Foundation Engineering 4
O:\WINWORD\3DG\C12\015-02.DOC PAGE 1 OF 37
5.1 Negative Skin Friction 20
5.2 Soil Freeze, Relaxation, and Pile Retapping 22
5.3 Pile Heave 24
12.0 REFERENCES 33
LIST OF FIGURES 36
O:\WINWORD\3DG\C12\015-02.DOC PAGE 2 OF 37
1.0 INTRODUCTION
1.1 General
O:\WINWORD\3DG\C12\015-02.DOC PAGE 3 OF 37
depending on local conditions.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 4 OF 37
The types of piles can be categorized by either the method of
installation or by material composition. Figure 1 shows the basic
types of piles categorized by material composition. The details of
each pile type are described in following subsections.
Timber piles have a relatively low cost per foot and are easy to
handle. They are best suited as friction piles in relatively loose
granular material. Timber piles are subject to possible damage
during driving, are difficult to splice, and are vulnerable to decay
unless properly treated.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 5 OF 37
2.2.1 Concrete Pile Types
O:\WINWORD\3DG\C12\015-02.DOC PAGE 6 OF 37
2.2.1.1 Cast-in-place Piles
There are three basic installation methods: (1) the dry method, (2)
the casing method (often combined with a slurry), and (3) the slurry
displacement method. The dry method is applicable in those soils
where the drilled hole will remain open for the placement of
concrete. When caving or sloughing of the soil can occur, such as
with soft soils of low shear strength, or granular soils with no
cohesion, or below the water table, the casing method is frequently
used. For this method, a temporary casing or liner is installed
through the layer of unstable soil and sealed off in a stratum of
impermeable soil. If the layer of unstable soil is relatively thick, it
may be necessary to use a drilling mud slurry to maintain the hole
until the casing can be set. If soil conditions permit, the slurry is
removed with a bailing bucket after the casing has been set and
normal drilling proceeds. Concrete is placed in the dry by
conventional methods. If the slurry cannot be removed, the slurry
displacement method is used. For this method a drilling mud slurry
is used to maintain the hole until the concrete can be placed. The
drilling mud can be formed by adding bentonite (and water if
necessary) to the drill hole and mixing it by rotation of the auger,
although it is preferable and more common to premix the slurry
before it is pumped into the hole. Under some subsoil conditions, a
natural slurry can be formed with the cohesive soils being drilled.
Concrete is then placed by tremie or pumping methods to fill the
hole from the bottom up to displace the slurry.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 7 OF 37
high allowable loads can be achieved and design loads may be
governed by the structural capacity of the pile shaft.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 8 OF 37
2.2.1.1.2 Cased Driven Steel Shell Cast-in-place Piles
The driven steel shell cast-in-place concrete piles have some basic
advantages, such as on-the-job length flexibility, internal inspection
after being driven, and protection of fresh concrete. The pile is
capable of being driven to high resistance, commonly to loads of 40
to 100 tons. Mandrel driven piles have the added advantage of
high impedance and stiffness, which results in higher load capacity
than when top driven with the same hammer. They are, however,
difficult to splice after concreting, difficult to redrive (special
precautions need to be taken) and thin shells can be damaged by
driving adjacent piles, or by driving the shell through cobbles,
boulders or fill material.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 9 OF 37
Full-length precast concrete piles can be made and driven, or
sections can be assembled into full pile lengths either during or
before driving. Most of these sectional concrete piles are
assembled during driving through the use of various basic types of
joints or splicing methods. For these basic methods, a considerable
number of special systems have been proposed, many of which are
commercially proprietary (See Reference 1).
O:\WINWORD\3DG\C12\015-02.DOC PAGE 10 OF 37
2.2.2 Concrete Pile Design
O:\WINWORD\3DG\C12\015-02.DOC PAGE 11 OF 37
cap. For design, embedments of 20 to 30 inches are usually
employed for strands, and they are treated as the equivalent
conventional steel reinforcement. For tension piles,
embedments are generally 30 to 40 inches.
C. For a fixed condition at the pile head, the pile head may be
extended up into the cap up to one foot but no less than 6
inches. The surface of the pile head should be roughened
and cleaned before concreting.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 12 OF 37
,
Compressive stresses should be limited to 0.8 f c 1 minus prestress
,
and the tension stresses should be limited to 6 f c 2 plus prestress,
,
where f c 3 is the concrete compressive strength. For additional
discussion, see References 7, 8, 9, 10 and 11 and Section 3.2.
This category includes those piles for which the sole structural
material is steel, such as H sections, special sections, and pipe not
filled with concrete (See Fig.1). Driving stresses for this type of pile
should be limited to minimize inelastic pile deformations.
H-sections most commonly are rolled (HP shapes) but can be built
O:\WINWORD\3DG\C12\015-02.DOC PAGE 13 OF 37
up. HP shapes are manufactured in various sizes and weights. If
the piles are built up, they should be of the H-section type, with web
and flanges of the same thickness. Rolled H-sections are produced
in standard mill lengths of 40 to 60 ft. but can be furnished by
special order to lengths of over 100 ft. H-piles can be readily
spliced on the job to whatever lengths are required.
Where the pipe pile is not filled with concrete, the structural material
is entirely steel. Concrete-filled pipe piles were discussed in
Section 2.2. Pipe used for piling is manufactured in various
diameters and wall thicknesses. In this category, pipe piles are
generally driven open-ended, and the soil inside the pipe is not
cleaned out. Typically, large-diameter piles for offshore structures
are in this category.
B. H-piles and pipe piles may require a driving shoe for hard
driving.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 14 OF 37
low resistivity, particularly in fill soils above the water table.
For the above reasons, pile driving formulas are generally not very
reliable. While the Hiley-type formulas have been recommended
for general use (Reference 2), these appear to underestimate the
capacities of very heavy or very long piles. Measured compression
is often less than the computed value due largely to nonuniformity
O:\WINWORD\3DG\C12\015-02.DOC PAGE 15 OF 37
resulting from wave action in the length of the pile. The wave
equation indicates that stresses in the pile may somewhat exceed
those obtained by the Hiley-type formula. Use of traditional
dynamic formulas is not recommended, except in special situations
where results have been correlated with load tests.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 16 OF 37
Calculation of pile capacity by static methods is, under almost all
circumstances, an approximation. It should only be used for
preliminary estimates of load capacity and pile length. The wave
equation analysis, probe piles, dynamic pile measurements and pile
load tests must be used in the final analysis to verify that the pile
design loads have been achieved with an adequate factor or safety.
Batter piles are used where earthquake forces do not control and
where lateral loads exceed the lateral capacity of vertical piles.
Other methods such as passive soil pressures against the cap or
mat are typically used to resist high lateral seismic loads.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 17 OF 37
stratum. In the design of a batter-pile foundation, the sum of the
horizontal components of the allowable axial capacities must equal
or exceed the applied lateral loads including a suitable factor of
safety.
It is common practice to assume that the batter piles carry all the
lateral loads. In fact, all the piles in a group will carry some of the
lateral forces if there is any continuity in the pile cap; hence, there
will be both bending and axial stresses in the pile. When there are
both vertical and batter piles in a group subjected to both horizontal
and vertical loads (or when the loads on the group are eccentric), a
group analysis should be performed to determine the loads carried
by each pile.
A more exact method, which requires the use of a computer for the
solution of a pile group with batter piles, is presented in Reference
30 and also in Reference 27 with an example problem. This
method of pile-group analysis is based on the following
assumptions:
O:\WINWORD\3DG\C12\015-02.DOC PAGE 18 OF 37
B. All piles behave similarly.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 19 OF 37
beams embedded in an elastic medium. For this type of analysis a
modulus of horizontal subgrade reaction must be established. It is
recommended that strain-dependent stiffness of the soil be included
(p-y approach) to estimate lateral resistance of piles, and to
calculate moments, etc.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 20 OF 37
the internal shear strength of the soil, the pile shape, and the weight
of the fill or surcharge causing the downdrag. Negative skin friction
can overstress the pile and cause settlement if not properly
considered. Geotech should be consulted whenever fills are to be
placed around pile foundations or when it is expected that a
negative skin friction load will occur.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 21 OF 37
experimentally. When piles are driven to friable shale and
relaxation occurs, the piles should not be overdriven or subjected to
prolonged hard driving. Prolonged hard driving could aggravate
and continue the relaxation due to progressive breakup of the
shale. Driving should stop as soon as the tip encounters sound
shale.
If soil freeze has occurred, and all other factors are equal, the retap
penetration resistance will be higher than the final resistance
measured during initial driving. In some cases, the pile may refuse
to penetrate further. In other cases, prolonged redriving may break
the soil freeze, and then the pile will drive more easily. If retapping
is done only to ensure an adequate penetration resistance or to
check on soil freeze, it is not necessary to continue redriving until
the soil freeze is broken. Retapping or redriving of uncased cast-in-
place piles should not be permitted. Redriving of concreted shell
piles is permissible only if the proper reinforcement and hammer-
pile cushion systems are used. For pipe or monotube piles not
originally driven with an internal mandrel, the concrete filling
provides a much stiffer pile with higher impedance, and results in a
more effective transmission of hammer energy. A wave equation
analysis will show the comparable final resistances for the loads
involved.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 22 OF 37
When displacement-type piles are driven in soft, saturated,
cohesive soils, ground heave adjacent to the pile may occur,
especially when such piles are closely spaced. Under such
conditions the possibility of pile heave should be checked. This can
be done by taking accurate elevation readings on the tops of
installed piles before and after adjacent piles have been driven. For
corrugated pile shells, such check-level readings should be taken
both on the top of the shell and on a telltale pipe resting on the
closure plate at the pile point. Upward movement of the tops of
such shells may be caused by stretching the shell and may not be a
problem.
The specifications may limit the amount of pile heave that can occur
before redriving is required, or they may specify that all heaved
piles be redriven. The specifications may require that piles be
redriven to the original penetration resistance or tip elevation or
both. Point-bearing piles should be reseated, but for friction piles,
heave may not be critical. If ground or pile heave occurs, the
effects on existing adjacent structures should be observed. Pile
heave can be controlled or eliminated by predrilling through the soft
material, by increasing the pile spacing, or by installing
nondisplacement-type piles. The inspector should record the
results of heave-level readings and all redrive data.
Pile load tests are performed to determine or verify capacity for one
or more of the following reasons:
O:\WINWORD\3DG\C12\015-02.DOC PAGE 23 OF 37
selected load is reached. This load is the minimum required
factor of safety times the working load. Typical factors of
safety range from 2.0 to 3.0.
It is now common practice to take pile tests to over two times the
design capacity, holding each incremental load for a shorter period
of time than in the standard test. Telltales and/or strain gages at
the bottom and sometimes at the middle of the pile provide an
accurate picture of the stress and movements in the pile at those
sections. Skin friction distribution and the amount of skin friction
versus end bearing can be deduced from the readings. These test
results used in conjunction with the PDA can provide a reliable
basis for pile driving criteria for production piles.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 24 OF 37
Load tests can be made prior to or early in production pile driving.
Usually this decision depends on the number of piles being
installed, the design load, and the variability of the soil conditions.
In most cases, probe piles should be installed at designated
locations to determine the pile length to be ordered or verify or
establish the installation criteria. Pile load tests may be conducted
on selected probe piles. Probe piles, test piles, and production
piles should all be installed with the same equipment, methods, and
techniques. Accurate records of probe pile installation, including
complete details of the equipment used, must be kept. Special
dynamic measurements may also be required to verify hammer
energy, pile stresses, and dynamic capacity. Typical pile test
programs performed by Bechtel are given in References 21, 22, 23,
24 and 25.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 25 OF 37
reduces danger of settlement, materially reduces heaving, and
permits the tips of subsequently driven piles to reach desired tip
elevations. In most cases, proper spacing provides higher load
carrying capacities for piles in a group, thus reducing the number of
piles required. Pile spacing less than three pile diameters center-
to-center should be avoided.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 26 OF 37
caps may behave in a manner similar to that of a deep beam or
deep bracket (Reference 44). In this case the "strut and tie"
concept discussed in Reference 45 should be considered when
detailing reinforcing. Section 10.7 of ACI 318 and Reference 46
can be used as a guide in determining if deep beam/bracket effects
need to be reviewed.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 27 OF 37
On a double acting diesel hammer, or a closed-end hammer, a
second combustion chamber at the top of the hammer is used to
drive the ram downward.
The two most common drilling methods for cast-in-place piles are
augers and rotating buckets. These are best suited in soil free of
tree roots, cobbles and boulders. For soil that is difficult to
excavate, a grab type rig is often used.
Water jetting may be used with caution to aid pile driving. The
influence of jetting on soil properties and the consequent interaction
of soil and pile after installation must be carefully considered from
the soil mechanics aspect. Predrilling is sometimes used to
facilitate pile placement. Excellent descriptions of pile driving and
drilling equipment are contained in References 2, 18, and 19.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 28 OF 37
It is required that continuous records be kept during installation of
all piles. The pile driving inspector will maintain a complete driving
record of each pile driven. The following information, as a
minimum, shall be included:
E. Length of pile taken into the leads, any splices made, and
additional lengths added
H. Number of blows per foot for each pile driven for the full
length of the pile
After all piling is completed the Soils Engineer should issue a final
report certifying that the piles as installed satisfy the installation
criteria.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 29 OF 37
and one should be prepared by the Civil/Structural Group. A pile
driving record form should be prepared prior to driving. Pile driving
data should be entered on the reports in the order driven, so the
sequence of driving is preserved for future evaluation.
The items listed below are of a general nature, but are included as
a further aid to the Pile Inspector.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 30 OF 37
I. Give special consideration to such items as underwater
driving, soil lubrication and jetting, heaving, protection and
pouring of concrete, concrete test cylinders, permissible
shell damage, inspection of drilled piles, and any specific
items peculiar to the site.
12.0 REFERENCES
O:\WINWORD\3DG\C12\015-02.DOC PAGE 31 OF 37
of Concrete Piles, Reported by ACI Committee 543, Journal
of ACI, No. 8, Proceedings V 70, August 1973.
9. Hirsut, T.J., L.L. Lowery, H.M. Coyle, and C.H. Samson, Pile
Driving Analysis by One Dimensional Wave Theory: State of
the Art, Highway Research Record No. 333, Pile
Foundations, 1970.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 32 OF 37
17. Meyerhof, G.G., Bearing Capacity and Settlement of Pile
Foundations, ASCE Journal of the Geotechnical Engineering
Division, No. 102 GT3, 1976.
24. Pile Load Test Report, Belle River Plant Area, Belle River
Units 1 and 2, Bechtel Job 10539, February 1978.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 33 OF 37
30. Aschenbrenner, R, Three Dimensional Analysis of Pile
Foundations, Journal of the Structural Division, ASCE, Vol.
93, ST1, February 1967.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 34 OF 37
36. Broms, B.B., Lateral Resistance of Piles in Cohesive Soils,
Journal of Soils Mechanics and Foundations Div., ASCE,
Vol. 90 SM2, March 1964.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 35 OF 37
45. Adebar, P., D. Kuchman, and M. Collins, Strut-and-Tie
Models for the Design of Pile Caps: An Experimental Study,
ACI Structural Journal, January-February 1990.
O:\WINWORD\3DG\C12\015-02.DOC PAGE 36 OF 37
Figure 1. Basic Pile Types
O:\WINWORD\3DG\C12\015-02.DOC PAGE 37 OF 37