You are on page 1of 5

BACK UP VOLUME COR ABUTMENT

DIMENSI PANJANG VOLUME


NO SKET GAMBAR
(M) (M) (M3)

COR BETON ABUTMENT

V1 = 3.80 x 4.80 x 7.10 = 129.50

V2 = 0.50 x 2.00 x 0.20 x 7.10 = 1.42

V3 = 0.50 x 2.00 x 0.20 x 7.10 = 1.42

V4 = 3.20 x 1.20 x 7.10 = 27.26

V5 = 0.90 x 0.75 x 0.25 x 7.10 = 1.20

V6 = 0.50 x 0.30 x 0.50 x 7.10 = 0.53

V7 = 2.40 x 1.00 x 7.10 = 17.04

V8 = 2.00 x 0.30 x 7.10 = 4.26

V9 = 0.85 x 0.25 x 7.10 = 1.51

V10 = 0.60 x 1.06 x 7.10 = 4.52

V11 = 0.90 x 0.40 x 7.10 = 2.56

JUMLAH = 191.22 M3

JUMLAH 2 ABUTMENT = 382.44 M3


DIMENSI PANJANG VOLUME
NO SKET GAMBAR
(M) (M) (M3)

COR BETON SAYAP ABUTMENT

V1 = 2.00 x 0.28 x 0.35 = 0.20

V2 = 4.15 x 2.00 x 0.35 = 2.91

V3 = 0.50 x 0.75 x 0.40 x 0.35 = 0.05

V4 = 1.30 x 0.90 x 0.35 = 0.41

V5 = 1.55 x 2.00 x 0.35 = 1.09

V6 = 0.50 x 2.00 x 1.75 x 0.35 = 0.61

V7 = 0.50 x 0.20 x 2.00 x 0.35 = 0.07

JUMLAH 5.33 M3

Volume Total Cor Beton 2 Sayap Abutment = 10.66 M3


DIMENSI PANJANG VOLUME
NO SKET GAMBAR
(M) (M) (M3)

BEKISTING ABUTMENT
1,3 0,6

V1 = 1.50 x 6.40 x 1.00 = 9.60 0,25 0,4 0,2

V2 = 0.50 x 2.00 x 0.30 x 1.00 = 0.30 11

0,9
V3 = 0.50 x 2.65 x 0.30 x 1.00 = 0.40
10

1,06
V4 = 6.07 x 1.75 x 1.00 = 10.62 9

0,3
8

V5 = 0.50 x 0.89 x 0.25 x 1.00 = 0.11 7

0,6
5 6
V6 = 0.50 x 0.60 x 0.89 x 1.00 = 0.27

0,89
V7 = 2.60 x 0.60 x 1.00 = 1.56

V8 = 2.00 x 0.30 x 1.00 = 0.60

V9 = 0.85 x 0.25 x 1.00 = 0.21

5,77
4

V10 = 0.60 x 1.06 x 1.00 = 0.64

V11 = 0.90 x 0.40 x 1.00 = 0.36

LUASAN = 24.67 M2

0,3
2 3

H1 = 1.50 x 10.00 = 15.00


1
H2 = 2.67 x 10.00 = 26.70

1,5
H3 4.90 x 10.00 = 49.00
2 1,75 2,65
6,4

H4 1.06 x 10.00 = 10.60

H5 1.15 x 10.00 = 11.50

H6 1.96 x 10.00 = 19.60


LUASAN 132.40 M2

VOLUME = 24.67 x 2.00 x 2.00 = 98.67

132.40 x 1.00 x 2.00 = 264.80

TOTAL = 363.47 M2