Professional Documents
Culture Documents
Chapter 11 PDF
Chapter 11 PDF
Notes
1. Rates include. - (a) Lead up to 100 m, for all materials for all Items.
(b) Cost of all materials including water.
(c) All lifts for all items
(d) Cost of mixing cement mortar.
(e) Cost of curing
2. Rates are Inclusive of raking of joints, preparation of surfaces, erection
and removal of scaffolding, finishing, curing and cleaning.
3. Measurements:- (i) Dimensions shall be measured correct to the nearest
cm. The area shall be calculated in sqm correct to two Places of decimal.
(ii) Measurement of wall plastering shall be taken between walls or partitions
(dimensions before plastering being taken) for length and from top of the
floor or skirting to ceiling for height. Depth of cornices or cover, if any,
shall be deducted.
(iii) Deductions:- For jambs, soffits, sills etc.; for openings not exceeding
0.5 sqm each In area, for ends of joists, beams, posts, girders, steps,
etc., not exceeding 0.5 sqm In area; and for openings exceeding 0.5
sqm and not exceeding 3 sqm each, deductions and additions shall be
made In the following manner:-
(a) No deduction shall be made for ends of joists, beams, posts
etc.and openings not exceeding 0.5 sqm each and neither additions
shall be made for reveals , jambs , soffits, sills etc. of these openings
nor for finish ( finish to plaster) around ends of joists , beams, posts
etc.
(b)Deductions for openings exceeding 0.5 sq m but not exceeding 3
sq m each shall be made as follows and no addition shall be made for
reveals, jambs, soffits, sills etc. of these openings.
(1)When both faces of wall plastered/pointed with same type of
plastered / pointed, deduction shall be made for one face only
(2) When two faces of wall are plastered/pointed with different types or
if one face Is plastered and the other pointed, deduction shall be
made from the plaster or pointing on the side on which the width of
reveal is less than that on the other side, but no deduction shall be
made from plaster or pointing on the other side. Where widths are
equal, deduction of 50 percent of area of opening on each face
shall be made from areas of plastering and / or pointing as the case
may be.
(3) When only one face is plastered and the other face is not plastered,
full deduction shall be made from plaster if width of reveal on
plastered side is less than that on unplastered side, but If widths of
reveal on both sides are equal or width of reveal on plastered side
Is more, on deduction shall be made nor any addition shall be
made for reveals, jambs, soffits, sills etc.
(4) When width of door frame is equal to thickness of wall or is
projecting beyond thickness of wall, full deduction for opening shall
be made from each plastered face of the wall.
(5) Plastering and pointing In C. M. 1:3 shall be done with prior written
permission of the Superintending Engineer/Chief Engineer.
(6) Thickness of plaster shall be exclusive of thickness of key i.e.
grooves or open joint in brick or stone work or space between
lathes. The minimum thickness over any portion of the surface shall
not be less than specified thickness by more than 3 mm.
(7) Only 10 or 15 mm thick plaster will be allowed for all thickness of
brick walls except on one side of 20 cm brick wall where 20 mm
thick plaster, if actually done, will be paid. Plaster more than 15
mm thick on brick work (except on one side of 20 mm thick brick
wall) and more than 20 mm thick on stone work shall be done with
prior written permission of the Superintending Engineer/Chief
Engineer.
(8)It is essential that mixes shall be used as soon as possible after
water has been added and that following working periods
recommended shall not be exceeded.
• (a) Cement mortar - 30 minutes
• (b) Cement lime mortar - 2 hours.
After completion of the finishing coat, the plaster shall be kept wet
for at least seven days.
Note :- (1) Where two or three coat plasters are adopted, as for as
possible the mix for the under coats should contain coarse sand
conforming to grading zone - II of I.S. 383 - 1970 and having
fineness modulus not less than 2.0.
Note :- (2) For single coat plaster the fineness modulus of sand
should as for as possible 1.5 and conforming to grading zone - IV of
I.S. 383-1970. Where only fine sand is available the fineness
modulus of sand may be improved by mixing the required
percentage of coarse sand. The strength of plaster mix gets
reduced with the reduction in the fineness modulus of sand.
(9) The following lndian Standards may be referred to: -
I. S. No. Title
383-1970 Coursed and fine aggregate from natural sources of
concrete (second revision) (Reaffirmed 2007)
I. S. No. Title
1661-1972 Code of practice for application of cement and cement –
lime plaster finishes(first revision) (Reaffirmed 2006)
2402-1963 Code of practice for external rendered finishes(Reaffirmed
2006)
2645-2003 Integral cement water proofing compound (first revision
)(with amendment No. 1)
2750-1964 Steel scaffoldings (with amendments No 1 to 3)
(Reaffirmed 2006)
3696(Pt. I)- Safety code for scaffolds and ladders : Part-1 Scaffolds.
1987 (Reaffirmed 2007)
8605-1977 Construction of masonry in dams. (Reaffirmed 1998)