Dropped Mast
SAFETY ALERT # 21/09
August 2009
The Alerts are provided to all Drilling and Workover Operations Foremen and Liaisonmen so that we all learn from the
experiences of others. The knowledge of this incident could prevent similar ones from happening in the future.
Saudi Aramco policy requires the information in this Alert to be communicated to all crew members and documented on
morning reports.
What happened?
Consequences:
The following safety processes were found to be absent: No Game plan, no PTW process, no
JSA process, critical lift plan, PJSM and no Rigger I present for this critical lift operation.
1. Rig contractor to ensure line management staff is trained to the level of “competent
person” in their core HSE Administrative Control tools. a) PTW process, b) JSA process,
c) PJSM process, d) Aramco Lifting & Rigging standards.
2. Ensure rig contractors are following their own Safety Management System processes,
including the requisite documentation in alignment with Aramco Standards.
3. Review the Saudi Aramco Value Statement that gives safety an equal standing with the 10
core values.
4. Communicate to all personnel that safety will not be compromised for production interests.