PART 1 - GENERAL
1.1 Contract Documents
1.2 Work Included
1.3 Quality Assurance
1.4 Submittals
1.5 Performance Criteria
PART 2 - PRODUCTS
2.1 Delivery Storage & Handling
PART 3 - EXECUTION
3.1 Installation
2. PRODUCTS
2.1 Delivery, Storage and Handling
2.1.1 Deliver, store and handle materials in the proper manner to prevent damage.
Deliver materials in their original, unopened containers. Store as per
manufacturer's recommendation, protected from possible damage, the elements
and moisture with heavy plastic sheeting.
2.1.2 Remove and replace coverings as required during the course of the Project.
3. EXECUTION
3.1 Installation
3.1.1 Install fire rated assemblies in accordance with the Local Authorities' requirements
or if not available, British Standards. Test results shall be submitted for review
and be acceptable to the Architect prior to installation.
3.1.2 Installation shall also be in accordance with the Drawings and per manufacturer’s
instruction where applicable.
- END -