Professional Documents
Culture Documents
03-What Are The Cover and The Deshuttring For The Following Concrete Elements ?
03-What Are The Cover and The Deshuttring For The Following Concrete Elements ?
1- Isolated Footing.
2- Combined Footing.
3- Stair.
02- Tests before and after casting ?
A- Before Casting:
1- Temperature test.
2- Slump test.
3- Cubic test.
B- After Casting:
1- Schmidt Hammer test.
2- Core test.
3- Load test.
03- What are the cover and the deshuttring for the following concrete elements ?
Cover Deshuttring
1 Footing 5 cm 1 Day
2 Tie Beams 2.5 cm 2 Day
3 Columns 2.5 cm 2 Day
4 Beams 2.5 cm 14 Days
5 Slabs 2.5 cm 12 Days
05- What is the name of the compaction test in the field and what is the
acceptable result ?
- Name : ........
- result : not less thant 95 %.
06- What are the types of cracks may be appears in a G+1 Building after
construction ?
10- What will you do if you have a G+1 Building with a Corrosion & .....?