Professional Documents
Culture Documents
2018 - CPM Exam Notes PDF
2018 - CPM Exam Notes PDF
Trichirapalli
bjblessi@gmail.com
“Project management involves the coordination of one time work by a team
of people who often have never previously worked together”
• Communication is insufficient
WHAT IS A PROJECT?
• Examples :
• New business
WHAT IS MANAGEMENT?
• Thirdly it states that manager uses people and other resources. For
example a manager who wants to increase the sales, might try not only to
increase the sales force, but also to increase advertising budget.
• And fourthly, it states that management involves the act of achieving the
organization's objectives
PROJECT MANAGEMENT:
1. Ensure that one person, and only one person, is responsible for the project
scope, budget and schedule
2. Don't begin work without a signed contract, regardless of the pressure to
start
3. Confirm that there is an approved scope, budget, and schedule for the
project
4. Lock in the project scope at the beginning and ensure there is no scope
5. Make certain that scope is understood by all parties, including the owner
6. Determine who developed the budget and schedule, and when they
were prepared
7. Verify that the budget and schedule are linked to the scope
8. Organize the project around the work to be performed, rather than trying
9. Ensure there is an explicit operational work plan to guide the entire project
10. Establish a work breakdown structure that divides the project into
responsibilities for all 12. Build the project staff into an effective team that
14. Budget all tasks; any work worth doing should have compensation
15. Develop a project schedule that provides logical sequencing of the work
resolved
18. Document all work, because what may seem irrelevant at one point in
20. Keep the client informed; they pay for everything and will use the project
upon completion
PROJECT PLANNING
• A project plan is a model of the process that the project team intends to
follow to realise the project objectives. It brings together a number of
important aspects of this process including its scope, timing, cost, and
associated risks.
• The project plan can be viewed as a type of ―contract‖ between the
project team members and other stakeholders. It defines‖ the process by
which the objectives will be achieved, and the responsibilities in carrying
out this process.
• Project plans also underpin a number of other key project management
functions including estimating and forecasting, options analysis and
decision making, and performance monitoring and control
Business leaders realized that they needed a system that will help them
manage large-scale projects. They needed a well-structured methodology
that would help them bridge gaps and ensure a consistent work pattern. As a
result, traditional project management was developed. Its ultimate goal was
to make sure all the tasks are carried out in predetermined orderly sequence.
Gantt chart gives you a simple overview of a project. It is one of the most
useful ways of presenting tasks and activities of the project on a timeline.
Left part of the Gantt chart shows the project activities and the top shows the
time scale. Each activity is presented with a bar. A bar’s position tells us about
the beginning, duration, and end of the activity.
Today, we mainly use Gantt chart to track project schedules and make
project management less stressful. Gantt chart helps us understand the
relationship between tasks more clearly, keep all the team members on the
same page, and successfully complete project.
Gantt Chart comes with a lot of benefits: it lets you organise your thoughts,
gives you a clear layout of what you’re doing, helps you set a realistic time
frame, and it’s highly visible.
There are many project constraints and the three most frequent ones are
time, cost, and scope. They are a part of every project and together they
In the initiation phase, it’s important to specify all the steps of the project
development including what WILL be was done and what WILL NOT be done.
If you want to keep the project under control, you need to allocate some
time and carefully plan and define the scope.
Time
Time is an invaluable resource. While we can control the processes and make
necessary changes to improve them, we cannot control time. One of the
biggest challenges each project manager has to face is to use time
efficiently, keep the project on schedule, and reach the desired objectives.
Cost
As a project manager, you should define the budget in the early stage of the
project and then compare it with the figure your customer initially offered. If
the client decides to spend a certain amount of money that doesn’t match
your requirements, you can prepare a business proposal which will include
the estimates of the total cost of the project. This proposal helps the customer
base his decision on more accurate estimates.
All three constraints are interconnected and depend heavily on one another.
Once you reduce the time allocated for the project, the cost increases. Also,
the scope of the project dictates the pace and a number of resources
necessary to realize and successfully complete the project.
The area inside the triangle represents the quality and it’s the ultimate
objective of every project delivery. A good project manager will find the way
how to control all three constraints of the triangle and produce the best
quality.
(a) Scheduling or progress charts, which show the sequence of job progress
(b) Load charts which show the work assigned to a work group or allocated
to machines
(c) Record charts which track the actual time spent and delays, if any
BAR CHART:
In a vertical bar graph, values of the independent variable are plotted along
a horizontal axis from left to right. Function values are shown as shaded or
coloured vertical bars of equal thickness extending upward from the
horizontal axis to various heights. In a horizontal bar graph, the independent
variable is plotted along a vertical axis from the bottom up. Values of the
function are shown as shaded or coloured horizontal bars of equal thickness
extending toward the right, with their left ends vertically aligned.
The following are advantages and disadvantages of bar graph
Advantages
show each data category in a frequency distribution
display relative numbers/proportions of multiple categories
summarize a large amount of data in a visual, easily interpretable form
make trends easier to highlight than tables do
estimates can be made quickly and accurately
permit visual guidance on accuracy and reasonableness of
calculations
accessible to a wide audience
Disadvantages
often require additional explanation
fail to expose key assumptions, causes, impacts and patterns
can be easily manipulated to give false impressions
PROGRESS CHART:
Refer http://www.conceptdraw.com/examples/construction-progress-chart-
sample
Load Chart:
WORK BREAKDOWN T
Work breakdown process involves splitting of the project works into its
manageable constituents arranged in a hierarchical order till desired
level.
Work breakdown levels are categorized into sub-projects, tasks, work
packages, activities and operations.
These levels depend upon the plan type, the nature and complexity of
The work break down levels are broadly categorized into five levels
o Sub-project level
o Task level
o Work-package level
o Activity level
o Operational level
Each level has certain features associated with it. However level
categorization is broad concept and at time their overlapping may become
unavoidable.
Sub-Project level: Sub projects are derived by dividing the project work into
Independent large volume mini projects or task groups. For example, in
housing project each group of major works which can progress in a
systematic manner, without interference from other works can be termed as
a sub-project e.g. Block-1,Block 2 etc.,
Task level: The project or sub-project work can be split up into various tasks.
A task is an identifiable and deliverable major works. A task is supported by its
design package. Each task is assigned with time and cost objectives and
provided with planned resources e.g. Floor 1, Floor 2 etc.,
Work Package level: A project task can be further sub divided into one or
more work packages. Each work package contains sizable, measurable, cost
able and controllable package of work like Civil works, Plumbing works,
Electrical works etc.,
Task level: Work packages further be broken down into various identifiable
jobs, operations and processes, which consume time and resources are
necessary for completion like Sub structure works, Super structure works,
External development works etc.
No Scope Overlap
The work breakdown schedule should not contain items that have duplicate
scope of other items. This may seem obvious, but you’d be surprised how
easy it is sometimes. Let’s say you’re building a house and the
excavation contractor and the foundation contractor both want to bring
earthmoving equipment to the site. In the work breakdown structure, both
items contain excavation. Maybe some efficiencies can be realized through
this planning process.
Number of Layers
The best way to know if you’ve gone to the right amount of detail is to ask
yourself if the element can be reliably estimated. At that point, elaborating
further simply creates difficulty in tracking and managing small work items.
In general, I would suggest the lowest level of a WBS be no smaller than
about 40 hours. Any less, and you’re micromanaging and introducing
inefficiencies.
The limit on the high end would be when you can no longer track and control
the project effectively. Big work items with multiple deliverables will limit
project control and make it difficult to track the project.
Identification
According to the PMI, a proper work breakdown structure element has three
parts:
1. Identification: Preferably an identification number, for reference.
2. Description: The name and/or a brief overview of the element.
3. Person responsible: Someone on whom final responsibility for the work
rests.
This is the minimum amount of information, although a project manager is
certainly free to include other information such as schedule and budget.
Since the WBS is primarily a graphical tool, these three items, and any other
information for each task, are included in a supporting document called the
WBS dictionary.
Roles and Responsibilities
As described above, it is a minimum requirement for the WBS to identify
responsible people for each WBS element.
Start and Finish Dates
An optional, but frequently used, piece of information that can be added to
the WBS is the schedule start and finish dates for each item. Although the WBS
should not be used as a schedule planning tool, start and finish dates can be
added after the schedule planning and used for tracking. So long as the
project manager realizes the the creation of the WBS is focused on proper
sub-division of the work, not time and schedule planning, this can be a useful
piece of information in the WBS.
Budget
Similar to the start and finish dates, the budget for the work item can be
included in the WBS. It is optional, but frequently used. The project manager
should realize that the WBS is not a costing or estimating tool, but once the
estimating has been done the budget can be placed in the work breakdown
structure for easy reference.
http://www.projectengineer.net/8-ideas-for-great-work-breakdown-
structures/
NETWORKING:
“A project network is a graph depicting the sequence in which a project's
terminal elements are to be completed by showing terminal elements and
their dependencies”
• CPM (Critical Path Method) is a mathematical algorithm that helps to
analyse, plan, and schedule complex projects.
• Each project consists of a number of tasks and activities that are
interconnected and essential for project’s success
• CPM is a powerful tool that allows identifying the longest path of
planned tasks necessary to meet the deadlines and identify the early
start and finish dates.
• By determining the critical path, you will know which activities are
critical in completing the project, and which ones won’t have any
serious impact on the project development and can be delayed.
ELEMENTS OF NETWORK:
Event :
An event represents the accomplishment of some task.
• In a network diagram, beginning and ending of an activity are
represented as events.
• Each event is represented as a node in a network diagram.
• An event does not consume any time or resource. Each network
diagram starts with an initial event and ends at a terminal event.
• Each node is represented by a circle and numbered by using the
Fulkerson's Rule.
Activity:
• An activity is a physically identifiable part of a project, which consumes
both time and resources.
• Activity is represented by an arrow in a network diagram.
a) The head of an arrow represents the start of activity and the tail
of arrow represents its end.
• Activity description and its estimated completion time are written along
the arrow.
• An activity in the network can be represented by a number of ways:
a) (i) by numbers of its head and tail events (i.e. 10-20 etc.), and
b) (ii) by a letter code (i.e. A, B etc.).
• All those activities, which must be completed before the start of
activity under consideration, are called its predecessor activities.
• All those activities, which have to follow the activity under
consideration, are called its successor activities.
Dummy Activity
• An activity, which is used to maintain the pre-defined precedence
relationship only during the construction of the project network, is
called a dummy activity.
• Dummy activity is represented by a dotted arrow and does not
consume any time and resource .
• An unbroken chain of activities between any two events is called a
path.
RULES FOR DRAWING NETWORKS:
Rule 1: Each activity is represented by one and only one arrow in the
network.
Rule 2: No two activities can be identified by the same end events.
• Earliest start time (EST): This is the earliest time an activity can be started,
assuming that all the activities prior to it have taken place as early as
possible. EST = EET
• Latest start time (LST): This is the latest time an activity can start consistent,
with the completion of the project in the stipulated time. LST = LET-d.
• Earliest finish time ( EFT): It is the earliest time by which an activity can be
completed, assuming that all the activities prior to it begin at their ESTs.
EFT =EET+d
• Latest Finish time (LFT): It is the latest time by which an activity must be
completed to ensure the completion of project within the stipulate time.
LFT = LET.
Float:
The difference between the latest start time (LST) and the earliest start time
(EST) of an activity is called as float or activity slack. Float is a measure of the
amount of time by which the start of an activity can be delayed consistently
with the completion of the project on time.
Total float:
Amount of time you can delay any given activity without delaying the
project end date Total float = (LF - EF)
LST = LETj - d
Free Float: amount of time you can delay an activity without delaying the
earliest start of succeeding activity
FF = ESTj - d – ESTi
FF = EETj - d – EETi
Interference Float : It is the overlap time between LFT of an activity and EST
of the succeeding activity.
IF = LFT j - EST i
IF = LETj – EETi
THREE MISTAKES U COULD POSSIBLY DO:
1. LOOPING ERRORS
2. DANGLING ERRORS
(PTO)
3. REDUNDANCY ERRORS
TASK DEPENDENCIES
CPM Benefits
• Provides a graphical view of the project.
• Predicts the time required to complete the project.
• Shows which activities are critical to maintaining the schedule and
which are not.
CPM Limitations
• While CPM is easy to understand and use, it does not consider the time
variations that can have a great impact on the completion time of a
complex project.
• CPM was developed for complex but fairly routine projects with
minimum uncertainty in the project completion times.
• For less routine projects there is more uncertainty in the completion
times, and this uncertainty limits its usefulness.
PROBABILITY
• Probability theory provides a mathematical Foundation to concepts
such as “probability”,“uncertainty”,“randomness”,“vari-
ability”,“chance”and “risk”.
• Probability theory is important to empirical scientists because it gives
them a rational frame work to make inferences and test hypotheses
based on uncertain empirical data.
• Probability theory is also useful to engineers building systems that have
to operate intelligently in an uncertain world
PERT charts are tools used to plan tasks within a project – making it easier to
schedule and coordinate team members accomplishing the work.
PERT charts were created in the 1950s to help manage the creation of
weapons and defence projects for the US Navy. While PERT was being
introduced in the Navy, the private sector simultaneously gave rise to a similar
method called Critical Path.
PERT is similar to critical path in that they are both used to visualize the
timeline and the work that must be done for a project. However with PERT,
you create three different time estimates for the project: you estimate the
shortest possible amount time each task will take, the most probable amount
of time, and the longest amount of time tasks might take if things don’t go as
planned.
2. Variance = tb – ta
6
3. Standard Deviation =
2. SCHEDULING:
3. ALLOCATION OF RESOURCES:
4. CONTROLLING:
• Final phase
• Arrow diagrams and time charts are done for periodic progress reports.
CONSTRUCTION COST:
The cost of work unit which may be an activity, a work item or a work
package is composed of one or more cost elements. The cost elements
include labour costs, materials costs, plant and machinery costs,
administration costs and other expenses.
DIRECT COST:
These are costs of materials, labour and other expenses which can be
identified with the execution of an item of work or activity.
Direct cost of permanent work item = Direct material cost + Direct labour cost
+ other direct expenses
Material: For example, materials used in concrete work of specified concrete
mix can be both measured, and its cost allocated to concreting activity in
terms of costs of cement, sand, aggregate, admixture and water, per cubic
meter of ready mix concrete.
INDIRECT COST:
Indirect cost includes all cost which is attributable to a given project but
cannot be identified with the performance of specific activity or work
packages. In other words, all costs other than direct costs are covered under
indirect costs. The range of indirect costs, depending upon the nature of the
project, may vary from 7.5% to 35% of the total costs.
These include all indirect manpower, indirect materials and other indirect
expenses incurred by each production responsibility centre also concerned
with providing technical and logistic support to the production centres.The
expenses related to operations and services rendered by the home office.
These costs include consultant’s fee, legal expenses, licensing charges, visits,
entertainment taxes, insurances and a share of the home office running
expenses
3.Most likely time (M): the best estimate of the time required to
complete a task, assuming condition that everything precedes as normal.
COST SLOPE:
It is the slope of the direct cost curve, approximated as a straight line in order
to have a single cross slope.
CS = Cc-Cn / tn – tc = ΔC /Δt
2. Determine:- Cost slope for various activities and arrange them in the
ascending order of cost slope.
3. Compute:- Direct cost for the network with normal duration of activities.
4. Crash:- The activities in the critical path as per ranking i.e starting with the
activity having the lowest slope.
8. Find: - Find total cost of the project at every stage by adding indirect costs
to the direct costs determined above.
10. Pick Up:-The optimum duration corresponding to which least total project
cost is obtained.
RESOURCE PLANNING:
The resources of an organization consist of people, materials, equipment,
knowledge and time. Organizations typically have limited resources;
therefore, trade-offs on what project resources are expended and when are
made every day within organizations.
Resource histogram:
It is a popular planning tool because it gives a good visual presentation
which is easy to assimilate and understand. The pre requisites for drawing a
histogram are
RESOURCE SMOOTHING: