Professional Documents
Culture Documents
Urugan Kembali
V = P x L x T + P x L x T
= 19.12 x 0.8 x 1.8 + 15.92 x 0.8 x 1.8
= 52.418 M3
PEKERJAAN BETON
Lantai Kerja t = 5 cm
V = P x L x T + P x L x T
= 6.27 x 3.98 x 0.05 + 5.7 x 3.5 x 0.05
= 2.4202 M3
Plat Tutup t = 12 cm
V = P x L x T + P x L x T
= 6.07 3.78 x 0.12 + 6.2 x 3.3 x 0.12
= 5.6694 M3
Plat Lantai AF t = 5 cm
V = P x L x T x n
= 1.3 x 1 x 0.05 x 6
= 0.39 M3
Sloof 15/30
V = P x L x T
= 37.02 x 0.15 x 0.3
= 1.6659 M3
Balok B1 15/30 cm
V = P x L x T
= 36.99 x 0.15 x 0.3
= 0.9987 M3
Balok Gantung 15/30 cm
V = P x L x T
= 6 x 0.15 x 0.3
= 0.27 M3
Balok B2 24/30 cm
V = P x L x T
= 13.4 x 0.24 x 0.3
= 0.5789 M3
Balok B3 12/15 cm
V = P x L x T
= 14.88 x 0.12 x 0.15
= 0.2678 M3
Kolom K1 15/15 cm
V = P x L x T
= 18.29 x 0.15 x 0.15
= 0.4115 M3
Kolom K2 15/24 cm
V = P x L x T
= 15.33 x 0.15 x 0.24
= 0.5519 M3
Kolom K3 24/24 cm
V = P x L x T
= 13.14 x 0.24 x 0.24
= 0.7569 M3
PEKERJAAN PASANGAN
Pasangan 1/2 Batu Bata Campuran 1Pc : 3Ps
V = P x L + P x L + P x L
= 4.2 x 0.5 + 3 x 0.72 + 15.57 x 1.2
= 22.944 M2
Pasangan 1 Batu Bata Campuran 1Pc : 3Ps
V = P x L + P x L + P x L
= 6 x 2.2 + 3 x 2.35 + 10.4 x 2.35
= 44.69 M2
Pasangan Botol Plastik
V = P x L x T x n
= 1.3 x 1 x 0.8 x 5
= 5.2 M3
Pipa Kuras Ø6"
V = P
= 11.9
= 11.9 M1
Filter Arang Bakar
V = P x L x T x n
= 1.3 x 1 x 0.5 x 1
= 0.65 M3
Plesteran Dalam 1Pc : 3Ps
inlet = L x T x N
= 7.2 x 0.65 x 1
= 4.68 M2
seatler = L x T + L x T + L x T
= 3.19 x 3 + 10.3 x 2.845 + 2.5 x 3
= 46.374 M2
gutter = L x T x N
= 8 x 0.95 x 1
= 7.6 M2
BR,AF,ARANG,OUTLET = L x T x N
= 1.3 x 1 x 12
= 15.6 M2
Buffler = L x T x N
= 3 x 1.05 x 2
= 6.3 M2
Vtotal = 80.554 M2
PEKERJAAN PIPA
Pipa vertical flow Ipal Ø 4" AW, Setara Maspion
V = P x N
= 0.65 x 4
inlet
= 2.6 M1
Tee PVC AW Ø 4" x 4"
V = 4 bh
= 1.07 x 4
= 4.28 M1
Tee PVC AW Ø 3" x 3"
V = 8 bh
ABR,AF,ARANG,OUTLET
Talud Pengaman
Vpondasi = P x L x T
= 7.3 x 0.4 x 0.5
= 1.46 M3
Vdinding = P x L x T
= 7.3 x 0.3 x 1.12
= 2.45 M3
Vtot = 3.91 M3
Urugan Pasir
Vpipa Ø6" = P x Apipa Ø6"
= 267.49 x 0.0182
= 4.877 m3
VØ6" = Vgalian - Vpipa Ø6" - Vurugan tnh VØ4" = P x
= 59.591 - 4.877 - 36.112 = 135.00 x
= 18.602 m3 = 4.05
Urugan Pasir tot = 34.615 m3
Bongkaran rabat
V = P x L x T
= 200 x 0.3 x 0.1
= 6 m3
PEKERJAAN PIPA
Pemasangan Pipa 6" 267.49 m
Pemasangan Pipa 4" 135.00 m
Pemasangan Pipa 3" 398.77 m
801.26
PEKERJAAN BAK KONTROL DAN REKONSTRUKSI
Bak Kontrol
Galian tanah Bak Kontrol
V = P x L x N
= 0.8 x 0.8 x 33
= 21.12 m3
Pas. Bata V = P x L x N
= 2.4 x 0.9 x 33
= 71.28 m2
Tutup Bak Kontrol 60 X 60 cm -------------------------------------------> VOL BETON TUTUP+LANTAI= @
Grestrap
V1 = P x L x N
= 1.6 x 0.4 x 45 coba kurangi jumlah SR
= 28.8 m2
Vtotal = 28.8 x 2 (bak kontrol=GT) di BK>: T=2, L=1 harus!!!!!
= 57.6 m2
Rabat
V = P x L x T
= 200 x 0.3 x 0.1
= 6 m3
+ P x L x T + P x L x T
+ 7 x 0.8 x 0.35 + 0 x 0 x 0
+ P x L x T
+ 1 x 3.5 x 0.05
+ P x L x T
+ 1 x 3.5 x 0.05
+ P x L x T + P x L x T
+ 0.75 x 3.3 x 0.15 + 3 x 1.15 x 0.15
+ P x L x T n
+ 0.6 x 0.6 x 0.08 16
T ) + ( P x L x T )
2.545 ) + ( 3 x 0.15 x 2.9 )
+ L x T x N + L x T x N
+ 3.12 x 2.42 x 1 + 3.3 x 2.76 x 1
4" 3"
T = P x L x T
0.5 = 398.77 x 0.3 x 0.3
= 35.889 m3
Urugan Kembali Pipa 3"
L x T Vurugan tnh = P x L x T
0.3 x 0.37 = 398.77 x 0.3 x 0.19
= 22.73 m3
0.016 M3
1.440
dua kali M3
(bak kontrol+grease trap)
yani keseluruhan
DAFTAR HARGA SATUAN BAHAN DAN UPAH
TAHUN 2016
NO. URAIAN SATUAN HARGA POKOK PAJAK 10% HARGA TERMASUK PAJAK
1 2 3 4
UPAH
1 Pekerja Oh 60,000.00 - Rp 60,000
2 Tenaga gali tanah/pondasi Oh 60,000.00 - Rp 60,000
3 Tukang batu Oh 80,000.00 - Rp 80,000
4 Tukang kayu Oh 80,000.00 - Rp 80,000
5 Tukang cat Oh 80,000.00 - Rp 80,000
6 Tukang besi Oh 80,000.00 - Rp 80,000
Tukang Las Konstruksi Oh Rp 57,500
Tukang Las biasa Oh Rp 55,000
9 Tukang Pipa ledeng Oh Rp 55,000
10 Kepala tukang batu Oh 85,000.00 - Rp 85,000
11 Kepala tukang kayu Oh 85,000.00 - Rp 85,000
12 Kepala tukang cat Oh 85,000.00 - Rp 85,000
13 Kepala tukang besi Oh 85,000.00 - Rp 85,000
15 Mandor Oh - - Rp -
BAHAN
1 Air m3 31,500.00 3,500.00 Rp 35,000
2 Batu bata apple 4 bj 495.00 55.00 Rp 550
3 Batu bata apple 5 bj Rp 550
4 Batu belah hitam
batu belah 15/20 m3 150,000.00 16,666.67 Rp 166,667
5 Batu belah putih m3 Rp 103,300
6 Baja dan Besi
Besi beton kg 6,959.62 773.29 Rp 7,733
7 Bambu btg
Bambu apus btg Rp 10,000
Bambu wulung btg Rp 10,000
Bambu petung btg Rp 60,000
8 Buis beton
diameter 30 mm x 1 m bj Rp 32,000
9 Cat
cat tembok exterior (Dulux) kg Rp 100,000
cat tembok exterior (Mowilex) kg Rp 26,000
Dinabolt dia 12 mm ( 10-15 cm) bh Rp 1,250
10 kayu begesteng m3 1,800,000.00 200,000.00 Rp 2,000,000
18 Kayu dolken m3 Rp 1,250,000
Kayu dolken, 4 mtran btg Rp 54,000
19 Kayu jati
papan m3 Rp 28,500,000
balok m3 Rp 27,800,000
reng m' Rp 4,500
20 Kayu kamper
papan m3 Rp 9,500,000
balok m3 Rp 9,000,000
reng m' Rp 2,000
21 Kayu Bangkirei
papan m3 Rp 10,000,000
balok m3 Rp 9,700,000
reng m' Rp 2,500
22 Kayu kruing
papan m3 Rp 7,500,000
balok m3 Rp 5,729,000
reng m' Rp 1,800
23 Kayu meranti
NO. URAIAN SATUAN HARGA POKOK PAJAK 10% HARGA TERMASUK PAJAK
1 2 3 4
papan m3 Rp 6,250,000
balok m3 1,800,000.00 200,000.00 Rp 2,000,000
reng m' Rp 1,500
24 Kayu glugu m3 1,800,000.00 200,000.00 Rp 2,000,000
25 Kapur pasang m3 Rp 115,000
26 Kawat ayakan m2 Rp 17,500
Kawat Las kg Rp 28,000
27 Kawat beton / bendrat kg 13,500.00 1,500.00 Rp 15,000
28 Split beton m3 330,000.00 36,666.67 Rp 366,667
Split beton kg Rp 272
Minyak bekisting ltr Rp 12,000
29 Pasir pasang
pasir pasang m3 135,000.00 15,000.00 Rp 150,000
pasir pasang kg Rp 107
pasir beton m3 135,000.00 15,000.00 Rp 150,000
pasir beton kg Rp 107
30 Pasir urug m3 135,000.00 15,000.00 Rp 150,000
31 Paku besar, sedang kg 13,800.0 1,533.3 Rp 15,333
32 Paku kecil kg Rp 15,333
33 Pipa
PVC 4 m diameter 2" AW btg Rp 111,000
PVC 4 m diameter 3" D btg Rp 77,500
PVC 4 m diameter 3" Orange btg 287,577.0 31,953.0 Rp 319,530
PVC 4 m diameter 4" D btg Rp 118,000
PVC 4 m diameter 4" Orange btg 386,515.8 42,946.2 Rp 429,462
PVC 4 m diameter 6" D btg Rp -
PVC 4 m diameter 6" Orange btg 690,417.0 76,713.0 Rp 767,130
Tee 4" bh 13,500.00 1,500.00 Rp 15,000
Tee 3" bh 9,000.00 1,000.00 Rp 10,000
Tee 2" bh 6,300.00 700.00 Rp 7,000
L 4" bh 13,500.00 1,500.00 Rp 15,000
L 3" bh 6,300.00 700.00 Rp 7,000
L 2" bh 4,500.00 500.00 Rp 5,000
KETERANGAN
5
Kelas I
KETERANGAN
5
KETERANGAN
5
RENCANA ANGGARAN BIAYA
(DANA KONSTRUKSI FISIK)
I. BIAYA FISIK
A. PEKERJAAN PERSIAPAN 6,302,008.73 630,200.87 3,434,002.91 - - -
1 Papan Nama Proyek 1.00 SET Ls 200,000.00 200,000.00 150,000.00 15,000.00 50,000.00 - - -
2 Administrasi dan Operasional 1.00 KEG Ls 5,000,000.00 5,000,000.00 5,000,000.00 500,000.00 - - - -
3 Pengukuran dan Pemasangan Bowplank 31.14 M1 2.2.1 49,326.00 1,536,011.64 1,152,008.73 115,200.87 384,002.91 - - -
4 Pekerjaan Pengukuran Topograf 1.00 KEG Ls 3,000,000.00 3,000,000.00 - - 3,000,000.00 - - -
B. PEKERJAAN BANGUNAN IPAL (BAK INLET, SEATLER, ABR, AF DAN OUTLET) #N/A #N/A #N/A - - 6,000,000.00
B.1 PEKERJAAN TANAH DAN PASIR 326,731.05 32,673.11 4,893,986.18 - - 2,500,000.00
1 Galian Tanah 138.83 M3 2.3.1 45,000.00 6,247,207.35 - - 3,747,207.35 - - 2,500,000.00
2 Urugan Kembali 52.42 M3 2.3.1 19,800.00 1,037,868.48 - - 1,037,868.48 - - -
3 Urugan Pasir Bawah Plat 2.42 M3 2.3.1 180,000.00 435,641.40 326,731.05 32,673.11 108,910.35 - - -
- 10,366,212.51
- 215,000.0
- 5,500,000.0
- 1,651,212.5
- 3,000,000.0
- #N/A
- 7,753,390.34
- 6,247,207.4
- 1,037,868.5
- 468,314.5
- 136,135,646.40
- 1,773,234.3
- 26,209,869.2
- 26,443,707.1
- 2,374,526.8
- 7,211,269.7
- 4,422,385.3
- 1,195,562.4
- 2,026,440.3
- 1,089,301.9
- 2,458,561.7
- 2,778,625.1
- 2,528,083.8
- 55,624,079.0
IBUSI MASYARAKAT
JUMLAH TOTAL HARGA
IN-CAST
15 16
- #N/A
- 1,924,579.5
- 8,208,941.9
- 7,269,795.0
- 1,075,000.0
- 2,377,201.2
- 4,943,054.6
- 5,235,424.5
- #N/A
- 1,912,824.1
- 8,670,000.00
6,020,000.0
- 2,150,000.0
500,000.0
- 5,551,176.28
- 299,959.2
- 64,500.0
- 3,920,018.0
- 602,000.0
- 127,199.2
- 537,500.0
- #N/A
- #N/A
- 5,143,043.7
- 1,107,398.7
- 6,697,994.8
- #N/A
- 106,655,817.88
- 53,435,886.6
- 15,574,802.7
- 35,049,003.6
- 806,250.0
- 483,750.0
- 338,625.0
- 967,500.0
- #N/A
- 950,400.0
- 79,200.0
IBUSI MASYARAKAT
JUMLAH TOTAL HARGA
IN-CAST
15 16
- #N/A
- 5,975,515.4
- #N/A
5,173,606.4
- 4,396,030.8
540,000.00 540,000.00
540,000.00 540,000.00
REKAPITULASI RENCANA ANGGARAN BIAYA (RAB)
(DANA KONSTRUKSI FISIK)
I. BIAYA FISIK
B. PEKERJAAN BANGUNAN IPAL (BAK INLET, SEATLER, ABR, AF DAN OUTLET#N/A #N/A #N/A - 6,000,000.00 - #N/A
TERBILANG :
# #N/A #
RANGKUMAN
ANALISA HARGA SATUAN PEKERJAAN KONSTRUKSI
BANGUNAN GEDUNG DAN PERUMAHAN
TAHUN 2014
HARGA SATUAN
Rp 440,022.00
Rp 132,000.00
Rp 3,300.00
Rp 2,640.00
Rp 21,367.50
Rp 804,100.00
Rp 30,002.50
#REF!
#REF!
Rp 480,104.90
Rp 49,326.00
Rp 6,600.00
Rp 115,534.65
#REF!
Rp 418,836.00
Rp 45,000.00
Rp 59,400.00
Rp 63,000.00
Rp 66,000.00 P L T V HARGA Per meter =
Rp 99,000.00 2.5 ### 1 0.9 Rp66,000.00 Rp26,400.00
Rp 79,200.00
Rp 3,300.00
Rp 21,780.00
Rp 15,000.00
Rp 19,800.00
Rp 21,000.00
Rp 22,000.00
Rp 33,000.00
Rp 26,400.00
Rp 33,000.00
Rp 180,000.00
Rp 15,000.00
Rp 16,500.00
Rp 682,011.00
Rp 742,005.00
Rp 491,287.50
Rp 689,287.50
Rp 454,756.50
Rp 652,756.50
Rp 429,066.00
Rp 627,066.00
Rp 393,871.50
Rp 591,871.50
Rp 335,659.50
Rp 533,659.50
Rp 153,598.50
Rp 351,598.50
Rp 1,881,987.35
Rp 814,836.00
Rp 797,399.82
Rp 830,998.45
Rp 856,590.82
Rp 681,555.16
Rp 887,756.70
Rp 916,106.41
Rp 854,072.98
Rp 952,136.73
Rp 973,928.61
Rp 980,581.95
Rp 1,043,224.33
Rp 1,051,984.78
Rp 1,016,829.00
Rp 6,880.50
Rp 85,496.05
Rp 90,036.15
Rp 12,588.20
Rp 145,475.00
Rp 141,250.00
Rp 224,420.00
Rp 229,820.00
Rp 260,420.00
Rp 244,420.00
Rp 226,017.00
Rp 81,097.50
Rp 3,144,774.31
Rp 3,790,683.59
Rp 5,920,460.13
Rp 4,592,215.57
Rp 4,677,250.59
Rp 4,087,056.31
Rp 4,355,478.59
Rp 78,744.21
Rp 4,245,736.81
Rp 320,000.00
Rp 4,026,747.00
Rp 3,107,171.00
Rp 4,683,568.00
Rp 4,607,743.00
Rp 5,557,461.00
Rp 3,783,244.00
Rp 3,256,393.00
Rp 4,119,078.00
Rp 3,342,123.00
Rp 4,224,136.00
Rp 5,663,749.00
Rp 4,840,923.00
Rp 180,780.00
Rp 170,871.00
Rp 164,229.00
Rp 160,746.00
Rp 159,450.00
Rp 146,373.90
Rp 92,212.50
Rp 82,419.60
Rp 79,725.00
Rp 78,029.40
Rp 77,100.60
Rp 73,110.00
Rp 201,624.29
Rp 201,019.49
Rp 57,082.44
Rp 53,889.96
Rp 185,827.73
Rp 107,319.92
Rp 81,760.73
Rp 8,217.00
1 m3 Membongkar beton bertulang
6.667 OH Pekerja Rp 60,000.00 Rp 400,020.00
TENAGA
0.333 OH Mandor Rp - Rp -
JUMLAH Rp 400,020.00
JASA 10% Rp 40,002.00
HARGA SATUAN Rp 440,022.00
2.2.1 1 m' Pagar sementara dari kawat duri tinggi 1,8 meter
1.000 btg Dolken Rp 9,000.00 Rp 9,000.00
25.000 kg Kawat duri Rp 15,000.00 Rp 375,000.00
2.000 kg PC Rp 1,350.00 Rp 2,700.00
BAHAN
0.005 m3 Pasir beton Rp 135,000.00 Rp 675.00
0.009 m3 Kerikil beton Rp 330,000.00 Rp 2,970.00
0.030 kg Paku biasa Rp 13,800.00 Rp 414.00
0.200 OH Pekerja Rp 60,000.00 Rp 12,000.00
0.400 OH Tukang Kayu Rp 80,000.00 Rp 32,000.00
TENAGA
0.020 OH Kepala Tukang Rp 85,000.00 Rp 1,700.00
0.020 OH Mandor Rp - Rp -
JUMLAH Rp 436,459.00
JASA 10% Rp 43,645.90
HARGA SATUAN Rp 480,104.90
2.2.1 1 m' Pasang pagar beton pracetak (5 x 50 x 213) cm, tinggi 220 cm
0.986 lbr Panel beton pracetak Rp 120,000.00 Rp 118,320.00
0.525 btg Kolom beton pracetak Rp 200,000.00 Rp 105,000.00
BAHAN 0.074 m3 Pasir beton Rp 135,000.00 Rp 9,990.00
0.146 m3 Koral 2/3 Rp 330,000.00 Rp 48,180.00
45.000 kg PC Rp 1,350.00 Rp 60,750.00
0.125 OH Pekerja Rp 60,000.00 Rp 7,500.00
0.375 OH Tukang batu Rp 80,000.00 Rp 30,000.00
TENAGA
0.012 OH Kepala Tukang Rp 85,000.00 Rp 1,020.00
0.019 OH Mandor Rp - Rp -
JUMLAH Rp 380,760.00
JASA 10% Rp 38,076.00
HARGA SATUAN Rp 418,836.00
2.3.1 1 m3 Galian tanah biasa sedalam 1 meter
0.750 OH Pekerja Rp 60,000.00 Rp 45,000.00
TENAGA
0.025 OH Mandor Rp - Rp -
JUMLAH Rp 45,000.00
JASA 10% Rp -
HARGA SATUAN Rp 45,000.00
3.2.1 1 m3 Pondasi siklop, 60% beton camp. 1 PC : 2 PB : 3 KR & 40% batu belah
0.480 m3 Batu belah 15 cm/20 cm (hitam) Rp 150,000.00 Rp 72,000.00
194.000 Kg PC Rp 1,350.00 Rp 261,900.00
0.312 m3 Pasir Beton Rp 135,000.00 Rp 42,120.00
BAHAN
0.468 m3 Kerikil Beton Rp 330,000.00 Rp 154,440.00
126.000 kg Besi Beton Rp 6,959.62 Rp 876,912.59
1.800 Kg Kawat Beton Rp 13,500.00 Rp 24,300.00
3.400 OH Pekerja Rp 60,000.00 Rp 204,000.00
0.850 OH Tukang batu Rp 80,000.00 Rp 68,000.00
TENAGA
0.085 OH Kepala Tukang Rp 85,000.00 Rp 7,225.00
0.170 OH Mandor Rp - Rp -
JUMLAH Rp 1,710,897.59
JASA 10% Rp 171,089.76
HARGA SATUAN Rp 1,881,987.35
4.1.1 1 m3 Beton mutu f'c = 19,3 Mpa (K 225), slump (12 ± 2) cm, w/c = 0,58
371.000 kg PC Rp 1,080.00 Rp 400,680.00
0.499 m3 Pasir beton Rp 135,000.00 Rp 67,307.14
BAHAN
0.776 m3 Kerikil beton Rp 330,000.00 Rp 255,933.33
215.000 liter Air Rp 31.50 Rp 6,772.50
1.650 OH Pekerja Rp 60,000.00 Rp 99,000.00
0.275 OH Tukang batu Rp 80,000.00 Rp 22,000.00
TENAGA
0.028 OH Kepala Tukang Rp 85,000.00 Rp 2,380.00
0.083 OH Mandor Rp - Rp -
JUMLAH Rp 854,072.98
JASA 10% Rp -
HARGA SATUAN Rp 854,072.98
4.1.1 1 m3 Beton mutu f'c = 21,7 Mpa (K 250), slump (12 ± 2) cm, w/c = 0,56
384.000 kg PC Rp 1,080.00 Rp 414,720.00
0.494 m3 Pasir beton Rp 135,000.00 Rp 66,728.57
BAHAN
0.770 m3 Kerikil beton Rp 330,000.00 Rp 253,977.78
215.000 liter Air Rp 31.50 Rp 6,772.50
1.650 OH Pekerja Rp 60,000.00 Rp 99,000.00
0.275 OH Tukang batu Rp 80,000.00 Rp 22,000.00
TENAGA
0.028 OH Kepala Tukang Rp 85,000.00 Rp 2,380.00
0.083 OH Mandor Rp - Rp -
JUMLAH Rp 865,578.85
JASA 10% Rp 86,557.88
HARGA SATUAN Rp 952,136.73
4.1.1 1 m3 Beton mutu f'c = 24 Mpa (K 275), slump (12 ± 2) cm, w/c = 0,53
406.000 kg PC Rp 1,080.00 Rp 438,480.00
0.489 m3 Pasir beton Rp 135,000.00 Rp 65,957.14
BAHAN
0.760 m3 Kerikil beton Rp 330,000.00 Rp 250,800.00
215.000 liter Air Rp 31.50 Rp 6,772.50
1.650 OH Pekerja Rp 60,000.00 Rp 99,000.00
0.275 OH Tukang batu Rp 80,000.00 Rp 22,000.00
TENAGA
0.028 OH Kepala Tukang Rp 85,000.00 Rp 2,380.00
0.083 OH Mandor Rp - Rp -
JUMLAH Rp 885,389.64
JASA 10% Rp 88,538.96
HARGA SATUAN Rp 973,928.61
4.1.1 1 m3 Beton mutu f'c = 26,4 Mpa (K 300), slump (12 ± 2) cm, w/c = 0,52
413.000 kg PC Rp 1,080.00 Rp 446,040.00
0.486 m3 Pasir beton Rp 135,000.00 Rp 65,667.86
BAHAN
0.756 m3 Kerikil beton Rp 330,000.00 Rp 249,577.78
215.000 liter Air Rp 31.50 Rp 6,772.50
1.650 OH Pekerja Rp 60,000.00 Rp 99,000.00
0.275 OH Tukang batu Rp 80,000.00 Rp 22,000.00
TENAGA
0.028 OH Kepala Tukang Rp 85,000.00 Rp 2,380.00
0.083 OH Mandor Rp - Rp -
JUMLAH Rp 891,438.13
JASA 10% Rp 89,143.81
HARGA SATUAN Rp 980,581.95
4.1.1 1 m3 Beton mutu f'c = 28,8 Mpa (K 325), slump (12 ± 2) cm, w/c = 0,49
439.000 kg PC Rp 1,080.00 Rp 474,120.00
0.479 m3 Pasir beton Rp 135,000.00 Rp 64,607.14
BAHAN
0.745 m3 Kerikil beton Rp 330,000.00 Rp 245,911.11
215.000 liter Air Rp 31.50 Rp 6,772.50
2.100 OH Pekerja Rp 60,000.00 Rp 126,000.00
0.350 OH Tukang batu Rp 80,000.00 Rp 28,000.00
TENAGA
0.035 OH Kepala Tukang Rp 85,000.00 Rp 2,975.00
0.105 OH Mandor Rp - Rp -
JUMLAH Rp 948,385.75
JASA 10% Rp 94,838.58
HARGA SATUAN Rp 1,043,224.33
4.1.1 1 m3 Beton mutu f'c = 31,2 Mpa (K 350), slump (12 ± 2) cm, w/c = 0,48
448.000 kg PC Rp 1,080.00 Rp 483,840.00
0.476 m3 Pasir beton Rp 135,000.00 Rp 64,317.86
BAHAN
0.741 m3 Kerikil beton Rp 330,000.00 Rp 244,444.44
215.000 liter Air Rp 31.50 Rp 6,772.50
2.100 OH Pekerja Rp 60,000.00 Rp 126,000.00
0.350 OH Tukang batu Rp 80,000.00 Rp 28,000.00
TENAGA
0.035 OH Kepala Tukang Rp 85,000.00 Rp 2,975.00
0.105 OH Mandor Rp - Rp -
JUMLAH Rp 956,349.80
JASA 10% Rp 95,634.98
HARGA SATUAN Rp 1,051,984.78
4.1.1 1 m3 Beton kedap air dengan storox - 100
400.000 kg PC Rp 1,080.00 Rp 432,000.00
0.480 m3 Pasir beton Rp 135,000.00 Rp 64,800.00
BAHAN
0.800 m3 Kerikil beton Rp 330,000.00 Rp 264,000.00
210.000 liter Air Rp 31.50 Rp 6,615.00
2.100 OH Pekerja Rp 60,000.00 Rp 126,000.00
0.350 OH Tukang batu Rp 80,000.00 Rp 28,000.00
TENAGA
0.035 OH Kepala Tukang Rp 85,000.00 Rp 2,975.00
0.105 OH Mandor Rp - Rp -
JUMLAH Rp 924,390.00
JASA 10% Rp 92,439.00
HARGA SATUAN Rp 1,016,829.00
4.2.1 1 m2 Pintu besi plat baja tebal 2 mm rangkap, rangkap baja siku
15.0000 kg Besi siku L 30.30.3 Rp 15,000.00 Rp 225,000.00
BAHAN 32.8000 kg Besi plat baja Rp 15,000.00 Rp 492,000.00
0.0500 kg Kawat las Rp 30,000.00 Rp 1,500.00
1.050 OH Pekerja Rp 40,000.00 Rp 42,000.00
1.050 OH Tukang las biasa Rp 50,000.00 Rp 52,500.00
TENAGA
0.105 OH Kepala Tukang Rp 55,000.00 Rp 5,775.00
0.0520 OH Mandor Rp - Rp -
JUMLAH Rp 818,775.00
JASA 10% Rp 81,877.50
HARGA SATUAN Rp 900,652.50
1 m2 Pasang Rangka atap baja ringan Main Truss C75 Reng 0,45, penutup atap genteng tanah bentuk
4.2.1
atap pelana
3.5000 m' Main truss C75/75 Rp 15,416.67 Rp 53,958.33
6.1000 m' Roof bottom RT 33-0,45 Rp 7,500.00 Rp 45,750.00
21.9298 bh Self drilling screw dia 6x20 mm Rp 500.00 Rp 10,964.91
13.1579 bh Self drilling screw dia 4x16 mm Rp 250.00 Rp 3,289.47
BAHAN 1.0526 bh Dinabolt dia 12-120 mm Rp 1,250.00 Rp 1,315.79
0.2105 bh Bracket bulat Rp 7,500.00 Rp 1,578.95
0.2105 bh Bracket oval Rp 7,000.00 Rp 1,473.68
0.0789 bh Cornerplat Rp 5,000.00 Rp 394.74
1.0000 Ls Alat (bor dan genset) Rp 5,000.00 Rp 5,000.00
0.247 OH Pekerja Rp 40,000.00 Rp 9,880.00
0.176 OH Tukang Besi profil Rp 50,000.00 Rp 8,800.00
TENAGA
0.117 OH Kepala Tukang Besi profil Rp 55,000.00 Rp 6,435.00
0.002 OH Mandor Rp - Rp -
JUMLAH Rp 148,840.88
JASA 10% Rp 14,884.09
HARGA SATUAN Rp 163,724.96
1 m2 Pasang Rangka atap baja ringan Main Truss C75 Reng 0,45, penutup atap genteng tanah bentuk
4.2.1
atap limasan
3.6500 m' Main truss C75/75 Rp 15,416.67 Rp 56,270.83
6.2500 m' Roof bottom RT 33-0,45 Rp 7,500.00 Rp 46,875.00
23.9298 bh Self drilling screw dia 6x20 mm Rp 500.00 Rp 11,964.91
15.1579 bh Self drilling screw dia 4x16 mm Rp 250.00 Rp 3,789.47
BAHAN 1.5526 bh Dinabolt dia 12-120 mm Rp 1,250.00 Rp 1,940.79
0.2526 bh Bracket bulat Rp 7,500.00 Rp 1,894.74
0.2526 bh Bracket oval Rp 7,000.00 Rp 1,768.42
0.0895 bh Cornerplat Rp 5,000.00 Rp 447.37
1.0000 Ls Alat (bor dan genset) Rp 5,000.00 Rp 5,000.00
0.247 OH Pekerja Rp 40,000.00 Rp 9,880.00
0.176 OH Tukang Besi profil Rp 50,000.00 Rp 8,800.00
TENAGA
0.117 OH Kepala Tukang Besi profil Rp 55,000.00 Rp 6,435.00
0.002 OH Mandor Rp - Rp -
JUMLAH Rp 155,066.54
JASA 10% Rp 15,506.65
HARGA SATUAN Rp 170,573.19
1 m2 Pasang Rangka atap baja ringan Main Truss C75 Reng 0,45, penutup atap genteng metal, bentuk
4.2.1
atap pelana.
3.0000 m' Main truss C75/75 Rp 15,416.67 Rp 46,250.00
3.9650 m' Roof bottom RT 33-0,45 Rp 7,500.00 Rp 29,737.50
BAHAN
21.9298 bh Self drilling screw dia 6x20 mm Rp 500.00 Rp 10,964.91
8.5526 bh Self drilling screw dia 4x16 mm Rp 250.00 Rp 2,138.16
BAHAN 1.0526 bh Dinabolt dia 12-120 mm Rp 1,250.00 Rp 1,315.79
0.2105 bh Bracket bulat Rp 7,500.00 Rp 1,578.95
0.2105 bh Bracket oval Rp 7,000.00 Rp 1,473.68
0.0789 bh Cornerplat Rp 5,000.00 Rp 394.74
1.0000 Ls Alat (bor dan genset) Rp 5,000.00 Rp 5,000.00
0.247 OH Pekerja Rp 40,000.00 Rp 9,880.00
0.176 OH Tukang Besi profil Rp 50,000.00 Rp 8,800.00
TENAGA
0.117 OH Kepala Tukang Besi profil Rp 55,000.00 Rp 6,435.00
0.002 OH Mandor Rp - Rp -
JUMLAH Rp 123,968.73
JASA 10% Rp 12,396.87
HARGA SATUAN Rp 136,365.60
1 m2 Pasang Rangka atap baja ringan Main Truss C75 Reng 0,45, penutup atap genteng metal, bentuk
4.2.1
atap limasan.
3.1000 m' Main truss C75/75 Rp 15,416.67 Rp 47,791.67
4.0625 m' Roof bottom RT 33-0,45 Rp 7,500.00 Rp 30,468.75
23.9298 bh Self drilling screw dia 6x20 mm Rp 500.00 Rp 11,964.91
8.8263 bh Self drilling screw dia 4x16 mm Rp 250.00 Rp 2,206.58
BAHAN 1.5263 bh Dinabolt dia 12-120 mm Rp 1,250.00 Rp 1,907.89
0.2526 bh Bracket bulat Rp 7,500.00 Rp 1,894.74
0.2526 bh Bracket oval Rp 7,000.00 Rp 1,768.42
0.0895 bh Cornerplat Rp 5,000.00 Rp 447.37
1.0000 Ls Alat (bor dan genset) Rp 5,000.00 Rp 5,000.00
0.247 OH Pekerja Rp 40,000.00 Rp 9,880.00
0.176 OH Tukang Besi profil Rp 50,000.00 Rp 8,800.00
TENAGA
0.117 OH Kepala Tukang Besi profil Rp 55,000.00 Rp 6,435.00
0.002 OH Mandor Rp - Rp -
JUMLAH Rp 128,565.33
JASA 10% Rp 12,856.53
HARGA SATUAN Rp 141,421.86
4.4.1 1 m2 Dinding Bata merah tebal 1 bata 1PC : 2PP
140.000 bh Batu bata Rp 495.00 Rp 69,300.00
BAHAN 43.500 kg PC Rp 1,080.00 Rp 46,980.00
0.080 m3 Pasir pasang Rp 135,000.00 Rp 10,800.00
0.600 OH Pekerja Rp 60,000.00 Rp 36,000.00
0.200 OH Tukang batu Rp 80,000.00 Rp 16,000.00
TENAGA
0.020 OH Kepala Tukang Rp 85,000.00 Rp 1,700.00
0.030 OH Mandor Rp - Rp -
JUMLAH Rp 180,780.00
JASA 10%
HARGA SATUAN Rp 180,780.00
4.4.1 1 m2 Dinding bata berongga ekspose uk. (5x11x24) cm, 1PC : 3PP
70.000 bh Bata berongga ekspose Rp 1,000.00 Rp 70,000.00
BAHAN 14.000 kg PC Rp 1,080.00 Rp 15,120.00
0.032 m3 Pasir pasang Rp 135,000.00 Rp 4,320.00
0.300 OH Pekerja Rp 60,000.00 Rp 18,000.00
0.150 OH Tukang batu Rp 80,000.00 Rp 12,000.00
TENAGA
0.015 OH Kepala Tukang Rp 85,000.00 Rp 1,275.00
0.015 OH Mandor Rp - Rp -
JUMLAH Rp 120,715.00
JASA 10% Rp 12,071.50
HARGA SATUAN Rp 132,786.50
4.4.2 1 m2 Plesteran , 1PC : 1PP tebal 15 mm
15.504 kg PC Rp 1,080.00 Rp 16,744.32
BAHAN
0.016 m3 Pasir pasang Rp 135,000.00 Rp 2,160.00
0.300 OH Pekerja Rp 60,000.00 Rp 18,000.00
0.150 OH Tukang batu Rp 80,000.00 Rp 12,000.00
TENAGA
0.015 OH Kepala Tukang Rp 85,000.00 Rp 1,275.00
0.015 OH Mandor Rp - Rp -
JUMLAH Rp 50,179.32
JASA 10% Rp 5,017.93
HARGA SATUAN Rp 55,197.25
TENAGA
0.200 OH Tukang batu Rp 80,000.00 Rp 16,000.00
TENAGA
0.020 OH Kepala Tukang Rp 85,000.00 Rp 1,700.00
0.022 OH Mandor Rp - Rp -
JUMLAH Rp 60,067.56
JASA 10% Rp 6,006.76
HARGA SATUAN Rp 66,074.32
4.6.1 1 m2 Membuat dan memasang daun pintu dan jendela jalusi kayu jati
0.064 m3 Kayu jati, papan Rp 28,500,000.00 Rp 1,824,000.00
BAHAN
0.500 Kg Lem kayu Rp 12,000.00 Rp 6,000.00
1.000 OH Pekerja Rp 60,000.00 Rp 60,000.00
3.000 OH Tukang Kayu Rp 80,000.00 Rp 240,000.00
TENAGA
0.300 OH Kepala Tukang Rp 85,000.00 Rp 25,500.00
0.050 OH Mandor Rp - Rp -
JUMLAH Rp 2,155,500.00
JASA 10% Rp 215,550.00
HARGA SATUAN Rp 2,371,050.00
4.6.1 1 m2 Membuat dan memasang daun pintu dan jendela jalusi kayu kamper
0.040 m3 Kayu kamper, papan Rp 9,500,000.00 Rp 380,000.00
BAHAN
0.500 Kg Lem kayu Rp 12,000.00 Rp 6,000.00
1.000 OH Pekerja Rp 60,000.00 Rp 60,000.00
3.000 OH Tukang Kayu Rp 80,000.00 Rp 240,000.00
TENAGA
0.300 OH Kepala Tukang Rp 85,000.00 Rp 25,500.00
0.050 OH Mandor Rp - Rp -
JUMLAH Rp 711,500.00
JASA 10% Rp 71,150.00
HARGA SATUAN Rp 782,650.00
4.6.1 1 m2 Membuat dan memasang pintu dan jendela jalusi kayu bangkirei
0.040 m3 Kayu bangkirei, papan Rp 10,000,000.00 Rp 400,000.00
BAHAN
0.500 Kg Lem kayu Rp 12,000.00 Rp 6,000.00
1.000 OH Pekerja Rp 60,000.00 Rp 60,000.00
3.000 OH Tukang Kayu Rp 80,000.00 Rp 240,000.00
TENAGA
0.300 OH Kepala Tukang Rp 85,000.00 Rp 25,500.00
0.050 OH Mandor Rp - Rp -
JUMLAH Rp 731,500.00
JASA 10% Rp 73,150.00
HARGA SATUAN Rp 804,650.00
4.6.1 1 m2 Membuat dan memasang daun pintu teakwood rangkap, rangka ekspose, kayu kamper
4.5.2 1 m2 Memasang atap genteng metal uk. 0,77 x 0,8 m, tebal 0,3 mm Ex. Sakuraroof Elang
1.0200 m2 Genteng metal Rp 75,600.00 Rp 77,112.00
BAHAN
0.2000 kg Paku biasa 2"-5" Rp 15,333.33 Rp 3,066.67
0.200 OH Pekerja Rp 60,000.00 Rp 12,000.00
0.100 OH Tukang Kayu Rp 80,000.00 Rp 8,000.00
TENAGA
0.010 OH Kepala Tukang Rp 85,000.00 Rp 850.00
0.010 OH Mandor Rp - Rp -
JUMLAH Rp 101,028.67
JASA 10% Rp 10,102.87
HARGA SATUAN Rp 111,131.53
4.5.2 1 m2 Memasang atap genteng metal berpasir uk. 0,77 x 0,8 m, tebal 0,35 mm Ex. Suryaroof
1.0200 m2 Genteng metal Rp 121,753.25 Rp 124,188.31
BAHAN
0.2000 kg Paku biasa 2"-5" Rp 15,333.33 Rp 3,066.67
0.200 OH Pekerja Rp 60,000.00 Rp 12,000.00
0.100 OH Tukang Kayu Rp 80,000.00 Rp 8,000.00
TENAGA
0.010 OH Kepala Tukang Rp 85,000.00 Rp 850.00
0.010 OH Mandor Rp - Rp -
JUMLAH Rp 148,104.98
JASA 10% Rp 14,810.50
HARGA SATUAN Rp 162,915.48
4.5.2 1 m2 Memasang atap genteng metal color uk. 0,77 x 0,8 m, tebal 0,35 mm Ex. Suryacolor
1.0200 m2 Genteng metal Rp 89,285.71 Rp 91,071.43
BAHAN
0.2000 kg Paku biasa 2"-5" Rp 15,333.33 Rp 3,066.67
0.200 OH Pekerja Rp 60,000.00 Rp 12,000.00
0.100 OH Tukang Kayu Rp 80,000.00 Rp 8,000.00
TENAGA
0.010 OH Kepala Tukang Rp 85,000.00 Rp 850.00
0.010 OH Mandor Rp - Rp -
JUMLAH Rp 114,988.10
JASA 10% Rp 11,498.81
HARGA SATUAN Rp 126,486.90
4.5.2 1 m2 Memasang atap genteng metal color uk. 0,77 x 1 m, tebal 0,4 mm Ex. Multicolor
1.0200 m2 Genteng metal Rp 110,389.61 Rp 112,597.40
BAHAN
0.2000 kg Paku biasa 2"-5" Rp 15,333.33 Rp 3,066.67
0.200 OH Pekerja Rp 60,000.00 Rp 12,000.00
0.100 OH Tukang Kayu Rp 80,000.00 Rp 8,000.00
TENAGA
0.010 OH Kepala Tukang Rp 85,000.00 Rp 850.00
0.010 OH Mandor Rp - Rp -
JUMLAH Rp 136,514.07
JASA 10% Rp 13,651.41
HARGA SATUAN Rp 150,165.48
4.5.2 1 m2 Memasang atap genteng metal berpasir uk. 0,77 x 1 m, tebal 0,4 mm Ex. Multiroof
1.0200 m2 Genteng metal Rp 136,363.64 Rp 139,090.91
BAHAN
0.2000 kg Paku biasa 2"-5" Rp 15,333.33 Rp 3,066.67
0.200 OH Pekerja Rp 60,000.00 Rp 12,000.00
0.100 OH Tukang Kayu Rp 80,000.00 Rp 8,000.00
TENAGA
0.010 OH Kepala Tukang Rp 85,000.00 Rp 850.00
0.010 OH Mandor Rp - Rp -
JUMLAH Rp 163,007.58
JASA 10% Rp 16,300.76
HARGA SATUAN Rp 179,308.33
0.007 OH Mandor Rp - Rp -
JUMLAH #REF!
JASA 10% #REF!
HARGA SATUAN #REF!
4.5.2 1 m' Pasang bubung stel gelombang 0,92 m
2.4000 lbr Bubung stel gelombang #REF! #REF!
BAHAN
6.0000 bh Paku sekrup 3,5" Rp 1,000.00 Rp 6,000.00
0.084 OH Pekerja Rp 60,000.00 Rp 5,040.00
0.125 OH Tukang Kayu Rp 80,000.00 Rp 10,000.00
TENAGA
0.013 OH Kepala Tukang Rp 85,000.00 Rp 1,105.00
0.004 OH Mandor Rp - Rp -
JUMLAH #REF!
JASA 10% #REF!
HARGA SATUAN #REF!
1 m1 Memasang got U - 25 cm
0.0060 m3 Pas. Bata merah 1PC : 4 Ps Rp 79,725.00 Rp 478.35
BAHAN
1.0000 m3 Got -U 25 #REF! #REF!
TENAGA 0.700 OH Pekerja Rp 60,000.00 Rp 42,000.00
JUMLAH #REF!
JASA 10% #REF!
HARGA SATUAN #REF!
1 m1 Memasang got U - 30 cm
0.0060 m3 Pas. Bata merah 1PC : 4 Ps Rp 79,725.00 Rp 478.35
BAHAN
1.0000 m3 Got -U 30 Rp 32,000.00 Rp 32,000.00
TENAGA 0.700 OH Pekerja Rp 60,000.00 Rp 42,000.00
JUMLAH Rp 74,478.35
JASA 10% Rp 7,447.84
HARGA SATUAN Rp 81,926.19
Pekerja OH 3.334
Tenaga Kerja
Mandor OH 0.666
JUMLAH
OVERHEAD 10%
JUMLAH TOTAL
print TERMIN 2print TERMIN 3
Rp 50 Rp 50
Rp 12,500 ###
copy jilid 4 copy jilid 4
82,500 82,500
-
Harga Satuan Jumlah
Bahan/ Upah (Rp.)
(Rp.)
60,000 200,010
#N/A #N/A
JUMLAH #N/A
OVERHEAD 10% #N/A
JUMLAH TOTAL #N/A
DATA VOLUME MANHOLE KEDALAMAN MIN 50 CM
- - -
VOL VOL PAS
NO NAMA BAK KONTROL DIMENSI HARGA
GALIAN BATA HARGA VOL HARGA
P L T BETON
1 BK1 0.6 0.6 0.50 0.32 21,120 1.20 98,904 0.06 245,223
2 BK2 0.6 0.6 0.50 0.32 21,120 1.20 98,904 0.06 245,223
3 BK3 0.6 0.6 0.92 0.59 38,861 2.21 181,982 0.11 451,211
4 BK4 0.3 0.3 1.10 0.70 46,464 1.32 108,794 0.07 269,746
5 BK5 0.6 0.6 1.05 0.67 44,352 2.52 207,697 0.13 514,969
6 BK6 0.3 0.3 0.89 0.57 37,594 1.07 88,024 0.05 218,249
7 BK7 0.3 0.3 1.12 0.72 47,309 1.34 110,772 0.07 274,650
8 BK8 0.3 0.3 1.11 0.71 46,886 1.33 109,783 0.07 272,198
9 BK9 0.6 0.6 1.05 0.67 44,352 2.52 207,697 0.13 514,969
10 BK10 0.3 0.3 1.03 0.66 43,507 1.24 101,871 0.06 252,580
11 BK11 0.3 0.3 1.07 0.68 45,197 1.28 105,827 0.06 262,389
12 BK12 0.6 0.6 0.92 0.59 38,861 2.21 181,982 0.11 451,211
13 BK13 0.3 0.3 0.98 0.63 41,395 1.18 96,925 0.06 240,319
14 BK14 0.6 0.6 1.07 0.68 45,197 2.57 211,654 0.13 524,778
15 BK15 0.6 0.6 1.39 0.89 58,714 3.34 274,952 0.17 681,721
16 BK16 0.6 0.6 0.81 0.52 34,214 1.94 160,224 0.10 397,262
17 BK17 0.6 0.6 1.34 0.86 56,602 3.22 265,061 0.16 657,199
18 BK18 0.6 0.6 1.51 0.97 63,782 3.62 298,689 0.18 740,575
19 BK19 0.6 0.6 1.48 0.95 62,515 3.55 292,754 0.18 725,861
20 BK20 0.6 0.6 1.23 0.79 51,955 2.95 243,303 0.15 603,250
21 BK21 0.6 0.6 0.70 0.45 29,568 1.68 138,465 0.08 343,313
22 BK22 0.6 0.6 0.80 0.51 33,792 1.92 158,246 0.10 392,357
23 BK23 0.6 0.6 1.16 0.74 48,998 2.78 229,456 0.14 568,918
24 BK24 0.6 0.6 0.93 0.60 39,283 2.23 183,961 0.11 456,115
RENCANA #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
AKUMULASI RENCANA #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
REALISASI
BOBOT WAKTU PELAKSANAAN
NO. PEKERJAAN VOLUME SATUAN JUMLAH HARGA
BULAN I BULAN II BULAN III BULAN IV
%
MGG 1 MGG 2 MGG 3 MGG 4 MGG 1 MGG 2 MGG 3 MGG 4 MGG 1 MGG 2 MGG 3 MGG 4 MGG 1 MGG 2 MGG 3 MGG 4
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22
AKUMULASI REALISASI
DEVIASI
#N/A
#N/A #N/A #N/A #N/A #N/A #N/A #N/A
0.00 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
0.00 #N/A #N/A #N/A #N/A #N/A #N/A
0.00 #N/A #N/A #N/A #N/A #N/A #N/A
0.00 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
0.00 #N/A #N/A #N/A #N/A #N/A #N/A
0.00 #N/A #N/A #N/A #N/A #N/A #N/A
0.00 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
0.00 #N/A #N/A #N/A #N/A #N/A #N/A
0.00 #N/A #N/A #N/A #N/A #N/A #N/A
0.00 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
0.00 #N/A #N/A #N/A #N/A #N/A #N/A
0.00 #N/A #N/A #N/A #N/A #N/A #N/A #N/A #N/A
0.00 #N/A #N/A #N/A #N/A #N/A #N/A
#N/A #N/A 10.00 sepuluh
#N/A #N/A 1.00 Satu 11.00 sebelas
#N/A #N/A 2.00 dua 12.00 dua belas
#N/A #N/A 3.00 tiga 13.00 tiga belas
#N/A #N/A 4.00 empat 14.00 empat belas
#N/A #N/A 5.00 lima 15.00 lima belas
#N/A #N/A 6.00 enam 16.00 enam belas
#N/A #N/A 7.00 tujuh 17.00 tujuh belas
#N/A #N/A 8.00 delapan 18.00 delapan belas
#N/A #N/A 9.00 sembilan 19.00 sembilan belas
#N/A #N/A
#N/A #N/A
#N/A #N/A
#N/A #N/A
BEGISTING DARI KAYU
LUAR LUAS = P X L X N
= 0.4 X 0.4 X 4
= 0.64 M2
DALAM LUAS = P X L X N
= 0.32 X 0.4 X 4
= 0.512 M2
LUAR LUAS = P X L X N
= 0.4 X 0.4 X 4
= 0.64 M2
DALAM LUAS = P X L X N
= 0.32 X 0.4 X 4
= 0.512 M2
11,085,081.60
5,761,496.13 SELISIH ###
###