You are on page 1of 2

EHS RISK ASSESSMENT

Ref : HMRP - 08 B Rev 00


Project : Hyderabad Metro Rail
Client : Hyderabad Metro Rail limited
Independent Engineer : Louis Berger Consulting Pvt. ltd
Concessionaire : L&T Metro Rail Hyderabad Limited
Contractor : L&T Construction PT&D IC (POWER SUPPLY & SCADA PROJECT)

Activity considered : Shuttering & De-shuttering Date: 09.02.12

Severity rating
Hazard / Environment Aspect

Probability
Risk / Residual

rating
Sl.no Activity Existing control measures Imapct Additional Control measures Risk / Action by
Source / Situation /
Possible outcome People at risk level Impact
Act

1) Head & Leg injury


1) Making path way clear without
due to material fall workmen
undulaitons & obstructions. If need to reach to the heights,
Shuttering 1) Material fall 2) MSDS due to engaged for Site Engineer
1 2)Material shifting in an 4 4 High shall be lifted using rope pulley Low
material shifting 2) Un clear pathway repetitive lifts of the material / Supervisor
ergonomous way (not lifting arrangement.
heavy shuttering shifting
above the shoulders & shifting)
material

Shuttering 1) Injury to workmen


workmen in the 1) Ensure safety shoe for the 1) Ensure lowering of formwork Site Engineer
2 material dropping 1) Material fall 2) Damage of 4 3 Medium Low
pit workmen using rope arrangement / Supervisor
into the pit material

1) Heavy material
Steel Wallers 1) Muscle strains / workmen
handling
3 handling & pains engaged & 2) Ensure safety shoe for the 3 4 Medium 1) Ensure lowering of waller Low Supervisor
2) Repetitive works /
dropping into pit 2) Foot injuries workmen in the workmen supports using rope arrangement
motions
pit 2) Establish good communication
1) Ensuer Removal & collection of
1) Eye Injury nails
1) Nail prick 2) Foot injury workmen 2) Lengthier nails inserting
1) Foot protection with safety
2) Fly of the wooden 3) Cuts, bruises engaged for (hammering) by giving packing
Shuttering works shoe
edges 4) Electrocution shuttering 3) NO joints in the cable shall be Site Engineer
4 into place(as per 2) Portable cutting m/c shall be 3 4 Medium Low
3) Usage of portable 5) Eye, nose placing allowed / Supervisor
dimensions) provided casing for the rotary part
cutting machine irritation (cartpenter, 4) Cable shall be layed away from
3) Using protection against dust
4) Dust expel 6) Respiratory helpers) the work posture
etc
problems etc 5) Machine - supply shall be put
OFF in idle condition.
workmen 1) Providing lifeline rope for the
engaged for 1) Material / men fall shall be height workmen to harness the
1) Failure of supports 1) Injury to workmen
Shuttering works shuttering protected using fall protection lanyards. Site Engineer
5 2) Fall of material 2) Damage of 3 5 High Low
for slab works placing nets. 2) NO ledger pipes etc shall be / Supervisor
3) fall of person material
(cartpenter, 2) Provision of edge barricades allowed at the top (chance of trip
helpers) & fall)
1) Cuts, brusies &
1) Handling of eye injury to workmen
1) Placing rigid platform for
Reinforcement lengthier rods & workmen engaged for 1) Sufficient workforce to handle
placing links/stirrups inbetween
6 placing & rod placing vertically 2) Fall of workmen reinforcement lengthier materials 3 4 Medium Low Supervisor
2) Usage of eye protection while
binding 2) Placing of links / 3) Penetration of placing (Fitter, 2) Usage of all PPE's
binding of the column(vertical)
stirrups reinforcement into helpers)
reinforcement
body due to fall
3)Good communication

1) ) Removing of steelwallers shall


be done by releasing the tie rod &
making it let down. 2) Shutter
boards shall be removed by tying
both the ends of the board &
1) Handling of heavy workmen release down. 3) De-
1) Foot / leg injuries
De-shuttering materilas engaged for de- shuttered materials shall be lifted No men shall be allowed
7 2) Finger crush 3 4 Medium Low Supervisor
works 2) Fall of material shuttering / lowered carefully with rope beaneath the de-shuttering area.
3) Head injury etc
3) Work at height works arrangement 4)
Ensure head/foot protection
5) Placing the de-shuttered
materials one over other at tools
yard (away from the pit edge &
away from the pathway)

FOR LTC FOR LTMRHL

You might also like