You are on page 1of 40

HIRA 3 :- HIRA 3 – Road Rcc ---

1.       Concrete Pouring of Diapragm Wall with the help of 10 " Dia Tremie Pipe
2. Lifting of Mechanical Grab Excavator and Placing it at required job location by 75 MT Crane
3.       Water proofing membranes works.
4.       Rain water pipe fixing
5.       Erection of Side cladding with the help of MEN LIFTER.
6.       CALIBRATION OF BATCHING PLANT
7.       Production of concrete with Bin system Batching Plant
8.       Production of concrete with Batching Plant with skip arrangement.
9.       BATCHING PLANT
10.    REINFORCEMENT
11.   Assembly of structural steel
12.   RCC/PCC / SCREED
13.   Loading and Unloading Structural Material
14.   BACK FILLING
15.   EXCAVATION FOR BUND WALL
16.   Lifting of main beam at various height with help of Crane
Note: Contact for any Query about HIRA to.
Mr. Chandrakant Patil
y 75 MT Crane Safety Engineer
Cont no.: 07567118585
SIMPLEX INFRASTRUCTURES LIMITED
COASTAL GUJARAT POWER LIMITED,MUNDRA
Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA)
FORMAT NO:
JOB TITLE : Lifting of Mechanical Grab Excavator and Placing it at required job location by 75 MT Crane

CONTROLLED
Sly ACTIVITY HAZARDS/RISK CONSEQUENCES SEVERITY PROBABILITY RISK PRESENT CONTROL MEASURE SEVERITY PROBABILITY RISK RISK FINAL RESPONSIBILITY
No (JOB STEPS IN SEQUENCE) ASSESSMENT
RATING

1 Slings of grab excavator kept 1.Improper 1.Load should be kept on wooden


on low be trailer will be Stacking/Body injury sleepers in stable possition.use ppe's
placed on the hook of the body injury 3 3 9 2 2 4 Tolerable ACCEPTABLE
crane properly
2.Caught in b/w load and 2.No movement of load should be
sling/body injury allowed while placing the sliing on the
body injury 3 3 9 hook of the crane 2 2 4 Tolerable ACCEPTABLE

2 Grab excavator will be lifted 1.Uneven and loose body injury/ 1.Before using crane the area should
vertically by 1.5 to 2 m from surface/ toppling of Property damage checked and leveled properly.
the static position to clear the crane 5 5 25 2 2 4 Tolerable ACCEPTABLE
bed.

2.Improper body injury/ 2.Periodical maintenance by P&M


maintenance / crane Property damage Dep't. should be done and third party
failure 5 4 20 inspection detail (form 10) should be 2 2 4 Tolerable ACCEPTABLE
attached.

3.Untrained operator body injury/ 3.Medical fit and trained operator


and signal man / Crane Property damage should be deployed for the operation.
collapse 5 5 25 2 2 4 Tolerable ACCEPTABLE Site Engineer /
Project Manager

4.Improper body injury/ 4.Proper assessment of crane safe


assessment/Fall of load Property damage working load at the particular radius
5 4 20 should be done according to load to be 2 2 4 Tolerable ACCEPTABLE
lifted w.r.t. load chart.

5. Improper 5. Barrication should be provided in


barrication/body injury swing area and unauthorized entry
body injury 4 4 16 should be strictly stopped. 2 2 4 Tolerable ACCEPTABLE

3 Move the grab excavator in 1.Free swing of crane/hit body injury/ 1) Proper attention should be paid for
right direction so that any to structure or person Property damage any interaction.
interaction of swinging of the 4 4 16 2 2 4 Tolerable ACCEPTABLE
crane is not occurred.

2. Frequent movement of 2). No movement of persons is


person / body injury body injury 4 4 16 allowed under the load . 2 2 4 Tolerable ACCEPTABLE
4 Take the Grab Excavator up 1.Untrained operator body injury/ 1).Medical fit and trained operator and
to the job location where and signal man / fall of Property damage signal man should be deployed for the
excavation is to be done frame 5 5 25 operation. 2 2 4 Tolerable ACCEPTABLE

2.Improper 2.Barrication should be provided


barrication/body injury around working area and unauthorized
body injury 4 4 16 entry should be strictly stopped. 2 2 4 Tolerable ACCEPTABLE

5 Position the Grab Excavator 1.free swing of grab 1.Double leg sling should be used with
properly to start excavation excavator/hit to body injury/ guide rope at both ends.
process. structure and person 4 4 16 2 2 4 Tolerable ACCEPTABLE
Property damage
Site Engineer /
Project Manager
2.Improper 2.Barrication should be provided
barrication/body injury around working area and unauthorized
body injury 4 4 16 entry should be strictly stopped. 2 2 4 Tolerable ACCEPTABLE

3. Movment of the 3. No unautorised person shall be


unauthorised person allowed at site location and authorised
close to excavated area personal should wear safety belt and
Fall of a person / proper attention should be paid all
body injury 5 5 25 2 2 4 Tolerable ACCEPTABLE
around the area

Prepared By Reviewed By Approved By

Name:

Designation:
SIMPLEX INFRASTRUCTURES LIMITED
COASTAL GUJARAT POWER LIMITED,MUNDRA
Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA)
FORMAT NO:
JOB TITLE : Concrete Pouring of Diaphragm Wall with the help of 10 " Dia Tremie Pipe
Sl No
ACTIVITY (JOB STEPS IN CONTROLLED FINAL
SEQUENCE)
HAZARDS/RISK CONSEQUENCES PROBABILITY SEVERITY RISK PRESENT CONTROL MEASURE PROBABILITY SEVERITY RISK
RISK RATING ASSESSMENT
RESPONSIBILITY

1 Placement of the Tremie 1.Improper Hanlding of


pipe (10 " dia) upto the matarial or fall of material Body Injury / 1. All the segment of the tremie pipe
Property damage 4 3 12 2 2 4 Tolerable Acceptable
bottom of the excavated pit should be properly handled.
in which reinforced cage is
already placed. 2. Improper securing of Body injury / fall of 2. Proper care should be paid while
segments. material / property securing all segments.
damage 3 3 9 2 2 4 Tolerable Acceptable

3. Fall of person in to the pit 3. Ensure all authorised person should


wear safety belt working near excavated Site Engineer /
Body injury / fatal 5 5 25 2 2 4 Tolerable Acceptable
pit while pouring Manager

2 Proper pouring of concrete 1. Improper handling of 1. The trunk of the pumper should be
on to the tremie pipe material / Fall of material properly fixed to avoid splash.
Body injury / fall
of material / 3 3 9 2. The area should be well barricaded and 2 2 4 TOLERABLE ACCEPTABLE
property damage unauthorized entry should be restricted to
avoid injury

Prepared By Reviewed By Approved By

Name:

Designation: DPM
SIMPLEX INFRASTRUCTURES LIMITED
COASTAL GUJARAT POWER LIMITED,MUNDRA

Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA)
JOB TITLE : Water proofing membranes works. FORMAT NO:

ACTIVITY CONTROLLED
Sly FINAL
(JOB STEPS IN HAZARDS/RISK CONSEQUENCES SEVERITY PROBABILITY RISK PRESENT CONTROL MEASURE SEVERITY PROBABILITY RISK RISK RESPONSIBILITY
No ASSESSMENT
SEQUENCE) RATING

1 Surface Preparation / Hand injury / 1)Area shall have adequate TOLERABLE ACCEPTABLE
Pre-cleaning Inhalation of ventilation.
gas/Dust Body injury 3 3 9 2)Use of PPE (Hand 2 1 2
gloves, Goggles)
Site Engineer / Project
2 Liquithane Hand injury / 1)Worker should be well TOLERABLE ACCEPTABLE Manager
preparation mixing of Inhalation of trained .
two components. gas/Dust Body injury / Burn 3 2 6 2 2 4
2)Use of PPE (Hand gloves,
Goggles , etc) .
3 Liquithane applied. Hand injury / 1)Area shall have adequate TOLERABLE ACCEPTABLE
Inhalation of Body injury / Fume ventilation.
gas/Dust mist 4 4 16 2)Use of PPE (Hand 2 2 4
inhalation/Death gloves,Goggles) .
Site Engineer / Project
Manager
4 Post Cleaning Hand injury / Use of PPE (Hand gloves, TOLERABLE ACCEPTABLE
Inhalation of Body injury 3 3 9 Mask ,Goggles) 1 2 2
gas/Dust

Prepared By Reviewed By Approved By

Name
Designation
SIMPLEX INFRASTRUCTURES LIMITED
COASTAL GUJARAT POWER LIMITED,MUNDRA
Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA)

JOB TITLE : Rain water pipe fixing at TG building FORMAT NO:

ACTIVITY (JOB
Sl CONTROLLED FINAL RESPONSIBILI
STEPS IN HAZARDS/RISK CONSEQUENCEPROBABILITY SEVERITY RISK PRESENT CONTROL MEASURE PROBABILITY SEVERITY RISK
No RISK RATING ASSESSMENT TY
SEQUENCE)

1 Reaching to the place 1. Improper route to 5 5 25 1.Proper two no. of lifeline should 2 2 4
reach the top of working be use , fall arrestor should be use
place/fall of person 2. ladder should
be fixed with proper dimension and
Body Injury / ppe rope. TOLERABLE ACCEPTABLE
Fetal 3.Use of PPE (Hand
gloves, Goggles , etc) .

2. Absence of PPE or 5 5 25 1. Ensure availability of full body 2 2 4


not used / fall of person Body Injury / harness and fall arrestor with TOLERABLE ACCEPTABLE
Fetal supervison to ensure use.

2 Use of tools at height 1. Improper arrengment 1) Carry tools in a gunny bag or tie
and Welding machine of lifeline , plateform, the tools with rope.
use for Fixing rain not use of Fallarrestor 2)Rope & pulley used for lifting
water pipe can cause fall of of material should be free from any
person and material defect.
Fatal 5 5 25 3)Worker should be well trained 2 2 4 TOLERABLE ACCEPTABLE
2. Electric and use of proper tool.
shock due to improper
tool use for drill/ welding 4)Use of PPE (Hand gloves,
. Goggles ,etc) , use of Fallarrestor. Site Engineer /
Project Manager

3. Improper material 4 4 16 5. Material should be kept away 2 2 4


handling / Fall of from open edge and tied with stable
material Body Injury position. TOLERABLE ACCEPTABLE

4.Bad environmental 4 4 16 6. Carry out the work in sufficient 2 2 4


condition ./ fall of day light and proper illumination
person should be provided at night.
Body Injury TOLERABLE ACCEPTABLE

7. No work should be done during


stormy or windy weather
5. Untrained worker / 5 5 25 8. Worker should be physically fit 2 2 4
Fall of person and trained for work at height.
Body Injury TOLERABLE ACCEPTABLE

3 Coming down after 1. No use of fall arrestor 5 5 25 1. Ensure supervison to enforce 2 2 4


work completion and Full Body Harness use fall arresto and full body
/ fall of person Body Injury harness.Tool box meeting TOLERABLE ACCEPTABLE

Prepared By Reviewed By Approved By

Name

Designation
SIMPLEX INFRASTRUCTURES LIMITED
COASTAL GUJARAT POWER LIMITED,MUNDRA
Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA)
FORMAT NO:
JOB TITLE : Rain water pipe fixing
Sl No
ACTIVITY (JOB STEPS IN SEVERIT CONTROLLED FINAL
HAZARDS/RISK CONSEQUENCES PROBABILITY SEVERITY RISK PRESENT CONTROL MEASURE PROBABILITY RISK RESPONSIBILITY
SEQUENCE) Y RISK RATING ASSESSMENT

1 Placement of the 1. scaffolding may collapse.


1. Check for any loose and uneven surface
scaffolding.
and make it compact.

2. Provide base plate of standard dimention


below every post/ standard
Serious injury 5 4 20 2 2 4 TOLERABLE ACCEPTABLE
3. Lock the structure with permanent structure
building.

4.Provide sufficient no. of cross bracing to


support the standards.

2 Use of tools at height 1. Improper handling of 1. Carry tools in a gunny bag or tie the tools
Electric drill. material / Fall of material with rope.

Serious injury 3 3 9 2.Rope & pulley used for lifting of material 2 2 4 TOLERABLE ACCEPTABLE
should be free from any defect. Site Engineer /
Manager

3 Fixing rain water pipe 1. Improper arrengment of 1)Worker should be well trained and use of
plateform. / fall of person and proper tool.
material Fatal 5 5 25 2)Use of PPE (Hand 2 2 4 TOLERABLE ACCEPTABLE
2.) Electric gloves, Goggles ,etc)
shock due to improper tool
use for drill.
4 Up & down movement of 1.Improper route 1. Full body harness should be used by all the
persons for work. worker and it will be anchored at suitable
position.
Fatal 4 5 20 2 2 4 TOLERABLE ACCEPTABLE
2. If possible ladder should be used for
moving up and down.
2. Stacking of loose material 1. No loose material should be kept at height
at scaffolding. regular supervison should be done.

2. Unauthorised entry should be stop near the


work and cordond of the area.
Body Injury 3 3 9 2 2 4 TOLERABLE ACCEPTABLE
3. Remove the barricade & allow the persons
up & down for work after checking the
complete installed scaffolding tower like
bracing, locking pins & split pins, etc.

5 Dismantling of scaffold 1.fall of scaffold material 1. The area where dismantling takes place Site Engineer /
while dismantling. should be barricaded and depute one person Manager
for communication to nearby area made.
Serious injury 4 4 16 2 2 4 TOLERABLE ACCEPTABLE

2. No throughing of material should be


allowded.

2. Improper plateformfor 1. Dismantling should be done by competent


working on scaffolding workmen.

Fatal 5 5 25 2. Plateform should be provided for working at 2 2 4 TOLERABLE ACCEPTABLE


height and full body harness should be
anchored at all the times,

Prepared By Reviewed By Approved By

Name
Designation
SIMPLEX INFRASTRUCTURES LIMITED
COASTAL GUJARAT POWER LIMITED,MUNDRA
Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA)
FORMAT NO:
JOB TITLE : Erection of Side cladding with the help of MEN LIFTER.

Sl ACTIVITY (JOB STEPS IN CONTROLLED FINAL


HAZARDS/RISK CONSEQUENCES PROBABILITY SEVERITY RISK PRESENT CONTROL MEASURE PROBABILITY SEVERITY RISK RESPONSIBILITY
No SEQUENCE) RISK RATING ASSESSMENT

1 Rreaching at job/height by Topple of man lifter , Fall of Before use of man lifter operator should
MEN LIFTER. person , Failure of lift . inspect the man lifter properly , proper Full
Fatal / Serious
5 4 20 body harness should be use and properly 2 2 4 TOLERABLE ACCEPTABLE
injury
hanker .

2 Lifting of sheet with the help of 1. Improper handling of 1.Rope & pulley used for lifting of material
PP rope material / Fall of material should be free from any defect.
Serious injury 4 4 16 2 2 4 TOLERABLE ACCEPTABLE
2. Tools like hand drill and screw should be
kept in bags and away from edge.

2. Improper platform / Fall of 1. Platform with sufficient width (900 mm )


person should be provided.

Fatal 5 5 25 2 2 4 TOLERABLE ACCEPTABLE


2. Worker must wear safety belt while
working at all time with anchored to stable
support.

3. Improper Connection / 1. Hand drill (Electrical tool )is double


Electrocution insulated and must be connected to 30 mA
ELCB.

2) Ensure the Earthing. Site Engineer /


Fatal 5 5 25 2 2 4 TOLERABLE ACCEPTABLE Manager

2. Cable used for connection should be free


from any damage and restricte minimum
joint.
3 Fixing of sheet by screwing 1. Improper handling of 1. Sheet should be handled by at least two
material / Fall of material worker and two person should be at ground
level untill fixing to be finished .

Serious injury 4 4 16 2 2 4 TOLERABLE ACCEPTABLE


2. Supervison should be proper while entire
job to restrict unauthorised entry.

4 Removal of lifting arrangment 1.Improper route / Fall of 1. Full body harness should be used by all
person Fatal 5 5 25 the worker and it will be anchored at suitable 2 2 4 TOLERABLE ACCEPTABLE
position.

5 Completion of job 1. Impopre route / Fall of 1. Full body harness should be used by all
person the worker and it will be anchored at suitable
Fatal 5 5 25 position while coming down BY MEN LIFTER 2 2 4 TOLERABLE ACCEPTABLE

Prepared By Reviewed By Approved By

Name
Designation
SIMPLEX INFRASTRUCTURES LIMITED

COASTAL GUJARAT POWER LIMITED,MUNDRA


Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA)

JOB TITLE : CALIBRATION OF BATCHING PLANT FORMAT NO:

Sl ACTIVITY (JOB STEPS CONSEQ CONTROLLED FINAL


HAZARDS/RISK PROBABILITY SEVERITY RISK PRESENT CONTROL MEASURE PROBABILITY SEVERITY RISK RESPONSIBILITY
No IN SEQUENCE) UENCES RISK RATING ASSESSMENT

1 Cleaning all load cells Hand injury / Inhalation 1)Area shall have adequate Tolerable ACCEPTABLE
of gas/Dust Body ventilation. 2)Use
3 3 9 of PPE (Hand gloves, Mask , 2 1 2
injury
Goggles)

2 Keeping weights and Improper placing of 1) Safe distance should be Tolerable ACCEPTABLE
release the loads . load, slip of cell can maintained. Site Engineer / Project
cause body injury Body
4 4 16 2)Operator should be well trained . 2 2 4 Manager
injury 3)Use of PPE (Hand
gloves, Mask , Goggles)
3 Post Cleaning Hand injury / Inhalation 1)Use of PPE (Hand gloves, Mask , Tolerable ACCEPTABLE
of gas/Dust Body Goggles)
2 3 6 1 2 2
injury

Prepared By Reviewed By Approved By

Name

Designation
SIMPLEX INFRASTRUCTURES LIMITED
TATA HOUSING PROJECT, SEC – 72, GURGAON.
Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA)
JOB TITLE : Production of concrete with Bin system Batching Plant
ACTIVITY (JOB CONTROLLE FINAL
S. CONSEQUENC PROBABILI SEVERI PRESENT CONTROL PROBABIL SEVERIT RESPONSIBI
STEPS IN HAZARDS/RISK RISK RISK D RISK ASSESSME
No ES TY TY MEASURE ITY Y LITY
SEQUENCE) RATING NT
1 Aggregates are 1)Manual poring of 1. Proper lifting and placing of
dumped in the plant cement into hopper so cement bag .
area. fall of person, inhalation 2. Proper tool use for cutting
body injury. 4 3 12 cement bag.
3. Use of proper PPE (Safety
goggles ,face mask, hand
gloves)
ACCEPTAB
Body injury/Fetal 2 2 4 TOLERABLE
2) Worker may come in 1. All rotating parts like gears, LE
contact with the rotating chains & rollers should be
parts of the machines. 3 3 9 guarded or barricaded.

3)Inhalation of cement 1.Use of proper PPE (Safety


can cause silicosis . 5 4 20 goggles ,face mask, hand
gloves)
2 Pulls the aggregates 1) Injury due to unsafe 1. All rotating parts like gears,
up to the walls work. chains & rollers should be
2) Worker may come in guarded or barricaded.
contact with the rotating 2. Proper ramp for concrete
parts of the machines. unloading in bucket / pump
should be provide. ACCEPTAB
Body injury 4 4 16 2 2 4 TOLERABLE
LE
3. One signal man should be
deputed for proper signaling. Site
4. Adequate turning area and Engineer /
stoppage for mixer should be Manager
provided.
3 Aggregates,Water & 1) Injury due to unsafe 1. All rotating parts like gears,
Admixture are poured work. 2) chains & rollers should be
in the mixing drum. Worker may come in guarded or barricaded. 2.
contact with the rotating Proper ramp for concrete
parts of the machines. unloading in bucket / pump
should be provide. 3. ACCEPTAB
Body injury 3 3 9 TOLERABLE
One signal man should be LE
deputed for proper signaling. 4.
Adequate turning area and
stoppage for mixer should be
provided.

4 Constituents are 1)Transit mixer may hit 1) Trained person should be


mixed and concrete is the cabin. 2) deployed for concrete poring
poured in the transit Worker may come in activity. 2)
mixer. contact with the rotating Transit mixer driver should be
parts of the machines Body injury/ trained. ACCEPTAB
5 4 20 2 2 4 TOLERABLE
Property damage 2) Proper supervision should be LE
ensured.
3) Technical supervision should
be strictly followed.
Prepared By: Rajiv Singh Approved By: S. K Pal
Name: Rajiv Singh
Designation: Safety Engineer
SIMPLEX INFRASTRUCTURES LIMITED
TATA HOUSING PROJECT, SEC – 72, GURGAON.

Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA)

JOB TITLE : Production of concrete with Batching Plant with skip arrangement. FORMAT NO:

Sl ACTIVITY (JOB STEPS IN CONTROLLED FINAL RESPONSI


HAZARDS/RISK CONSEQUENCES PROBABILITY SEVERITY RISK PRESENT CONTROL MEASURE PROBABILITY SEVERITY RISK
No SEQUENCE) RISK RATING ASSESSMENT BILITY

1 Aggregates are 1)Manual poring of 1. Proper lifting and placing of


dumped in the plant cement into hoper so cement bag .
area fall of person 4 3 12 2. Proper tool use for cutting
,inhalation body cement bag.
injury. 3. Use of proper PPE (Safety
2) Worker may come goggles
2. ,face mask,
All rotating handgears,
parts like gloves )
in contact with the Body injury/Fetal 2 2 4 TOLERABLE ACCEPTABLE
3 3 9 chains & rollers should be guarded
rotating parts of the or barricaded.
machines
3)In halation of 1.Use of proper PPE (Safety
cement can cause 5 4 20 goggles ,face mask, hand gloves )
silicosis .

2 Pulls the aggregates 1) Injury due to unsafe 1. All rotating parts like gears,
up to the walls work. chains & rollers should be guarded
or barricaded.
2) Worker may
come in contact with 2. Proper ramp for concrete
the rotating parts of unloading in bucket / pump should
the machines. be provide.
Body injury 4 4 16 2 2 4 TOLERABLE ACCEPTABLE

3. one signal man should be deputed


for proper signaling.
Site
Engineer /
4. adequate turning area and Manager
stoppage for mixer should be
provided.
3 Aggregates,Water & 1) Injury due to unsafe 1. All rotating parts like gears,
Admixture are poured work. chains & rollers should be guarded
in the mixing drum. or barricaded.
2) Worker may 2. Proper ramp for
come in contact with concrete unloading in bucket / pump
Body injury 3 3 9
the rotating parts of should be provide.
the machines.
3. one signal man
should be deputed for proper
signaling.
4 Constituents are 1)Transit mixer may 1) Trained person should be
mixed and concrete is hit the cabin. 4. adequate
deployed for concrit turning
poring activity.
poured in the transit 2) area
2) and stoppage
Transit for mixer
mixer driver should
should be
mixer. Worker may come in be provided.
trained
contact with the Body injury/ Property
damage 5 4 20 2) proper supervision should be 2 2 4 TOLERABLE ACCEPTABLE
rotating parts of the
machines ensured.
3) Technical supervision should be
strictly followed.

Prepared By Reviewed By Approved By

Name
Designation
SIMPLEX INFRASTRUCTURES LIMITED
TATA HOUSING PROJECT, SEC – 72, GURGAON.
Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA)
JOB TITLE : BATCHING PLANT
CONTROLL FINAL
S. ACTIVITY (JOB STEPS CONSEQUENC PROBABILIT SEVERIT PROBABILI SEVERIT RESPONSIBILI
HAZARDS/RISK RISK PRESENT CONTROL MEASURE RISK ED RISK ASSESSMEN
No IN SEQUENCE) ES Y Y TY Y TY
RATING T
1 Cement are conveyed 1)Manual poring of 1. Proper lifting and placing
by head load from cement into hopper of cement bag.
go-down to cutting so fall of person 2. Proper tool use for cutting
platform ,inhalation body 4 3 12 cement bag.
injury. 3. Use of proper PPE (Safety
goggles ,face mask, hand
gloves )
body
2) Worker may come 2. All rotating parts like gears, 2 2 4 TOLERABLE ACCEPTABLE
injury/Fatal
in contact with the chains & rollers should be
3 3 9
rotating parts of the guarded or barricaded.
machines.
3)Inhalation of 1.Use of proper PPE (Safety
cement can cause 5 4 20 goggles ,face mask, hand
silicosis . gloves )

2 Aggregates,Water & 1) Injury due to 1. All rotating parts like gears,


Admixture are unsafe work. chains & rollers should be
poured in the mixing 2) guarded or barricaded.
drum. Worker may come in
contact with the 2. Proper ramp for concrete Site Engineer /
Manager
rotating parts of the unloading in bucket / pump
machines. body should be provide.
4 4 16 2 2 4 TOLERABLE ACCEPTABLE
injury/Fatal
3. one signal man should be
deputed for proper signaling.

4. adequate turning area and


stoppage for mixer should be
provided.
3 Constituents are 1)Transit mixer may 1) Trained person should be
mixed and concrete hit the cabin. deployed for concrete poring
is poured in the 2) activity. 2)
transit mixer. Worker may come in Transit mixer driver should be
contact with the body trained.
rotating parts of the 5 4 20 2 2 4 TOLERABLE ACCEPTABLE
injury/Fatal 2) proper supervision should
machines be ensured.
3) Technical supervision
should be strictly followed.

Prepared By: Rajiv Singh Approved By: S. K Pal


Name: Rajiv Singh
Designation: Safety Engineer
SIMPLEX INFRASTRUCTURES LIMITED
TATA HOUSING PROJECT, SEC – 72, GURGAON.

Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA)
FORMAT NO:
JOB TITLE : REINFORCEMENT
Sl ACTIVITY (JOB STEPS IN HAZARDS/RISK CONSEQUENCES PROBABILITY SEVERITY RISK PRESENT CONTROL MEASURE PROBABILITY SEVERITY RISK CONTROLLED RISK FINAL RESPONSIBILIT
No SEQUENCE) RATING ASSESSMENT Y

1 Transportation of a)Injury to personnel 1.Provide red flags at the end of protruding


Reinforcement Steel due to hit of rods.
protruding rods body injury/ Property
4 5 20 2.Speed of the trailor /truck should be kept 2 2 4 TOLERABLE ACCEPTABLE
beyond the truck damage minimum.
desk.
3.Load material in stable condition.
b)slippage of rods 1.Side stoppers should be ensured in the trailor
from the trailor bed /truck.
body injury/ Property
4 5 20 2.Wooden planks shall be used between the 2 2 4 TOLERABLE ACCEPTABLE
damage
bed of trailor and the rods.
3.Bars should be tied with trailor body

2 Unloading a)Fall of the load 1.The Crane capacity should be tested before
body injury/ Property lifting the load.
4 5 20 2.The weight being lifted should be less than 2 2 4 TOLERABLE ACCEPTABLE SITE ENGINEER/
damage MANAGER
crane capacity.
b)Hitting of 1.The ends of the load should be tied with rope Name:
personnel due to to control the sway.
way. Contact no:
2.The workman should use proper PPE.
body injury/ Property
4 4 16 2 2 4 TOLERABLE ACCEPTABLE
damage 3.The work should be carried out under proper
supervision.
4.Stack material on sleeper after loading.

3 a) Fall of the steel 1.The weight being lifted should be less than
Placing of Reinforcement Steel
bar men capacity.
4 4 16 2 2 4 TOLERABLE ACCEPTABLE
2.The workman should use proper PPE.
body injury/ Property
b)Hitting of damage 1.The ends of the load should be tied with rope
personnel due to to control the sway.
way. 3 3 9 2 2 4 TOLERABLE ACCEPTABLE
2.The workman should use proper PPE.

Prepared By Reviewed By Approved By

Name

Designation

Page 15 of 40
SIMPLEX INFRASTRUCTURES LIMITED
TATA HOUSING PROJECT, SEC – 72, GURGAON.

Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA)
FORMAT NO:
JOB TITLE :Assembly of structural steel
PROB SEV CONTROLL FINAL
Sl ACTIVITY (JOB STEPS CONSEQ RESPON
HAZARDS/RISK PROBABILITY SEVERITY RISK PRESENT CONTROL MEASURE ABILI ERIT RISK ED RISK ASSESSMEN
No IN SEQUENCE) UENCES SIBILITY
TY Y RATING T
1 Unloading the item 1.Crane failure 1. Ensure the crane and load
parts of length 10- 2.Sling Failure lifting appliances are load tested
12m (variable) from because of loose D and certified by a competent
the Trailer/ Tractor shackles, broken person and available with valid
sling etc documents.
3. Body part caught 2. Ensure proper training
in between. imparted to workers like riggers,
4. Fall of the entire Body signalman, fitters, welders and
load and injury to the injury/ 4 3 12 helpers. 2 2 4 TOLERABLE ACCEPTABLE
Property
persons near by. damage 3. Ensure proper supervision.
4. Use proper SWL rated slings&
‘D’ shackles
5. Ensure that the max safe load
of the crane is more than the
weight of the load to be lifted.
6. Use Proper PPE (viz., Safety
Helmet, Safety Shoe, Hand Gloves
etc.)
2 Assembling of 1.Body parts caught 1. Proper clearance (of both Site
Column parts to in between persons and objects) should be Engineer /
Manager
form a 40m-length 2.Shock Hazard ensured in the vicinity.
part by welding. 3.Radiation 2.Proper Earthing
4.Flash (Eye injury) Body 3. Welding glass should be free
injury/ from damage.
Property
5 4 20 4. The welding machine should be 2 2 4 TOLERABLE ACCEPTABLE

damage connected with proper cable


connector.
5. Ensure no molten slag is falling
down and use proper sheet /
asbestos blanket to prevent fall of
molten slag and other materials.
3 Assembling of two 1.Body parts caught 1.Required number of workers
6.Welding machine should be
parts to form a in between should be deployed
proper earthed
single piece by 2. All the workers should be well
bolting experienced and should be always
5 5 25 2 2 4 TOLERABLE ACCEPTABLE
in vigil.
3. Use Proper PPE (viz., Safety
Body Helmet, Safety Shoe, Hand Gloves
injury/ etc.)
Property
damage
Body
injury/
4 Placing the 1. Sling Failure due Property 1. Ensure proper pep talk
assembled part in a to loose D shackles, damage imparted to workers before
lifting position deteriorated slings, proceeding work.
(horizontal etc. 2. Ensure that the max safe load
5 5 25 2 2 4 TOLERABLE ACCEPTABLE
2. Load may slip on of the crane is more than the
ground if not weight of the load to be lifted.
properly placed on 3. Use Proper PPE (viz., Safety
required number of Helmet, Safety Shoe, Hand Gloves
5 Tying the steel wire wooden
1.Body part/fingers etc.)
1. Use proper PPEs (Leather
rope slings to the sleepers/blockers.
caught in between 4.Use Hand
made propergloves,
D shackles
Hard and
hats,
structure for lifting 3. Load may hit to ensure shoes
Safety its strength
etc.) and capacity
the nearby 2. Deploy experienced Riggers.
persons/objects 3 3 6 3. Persons working must wear 2 2 4 TOLERABLE ACCEPTABLE

causing safety shoes & hand gloves.


injury/property 4. Sling distance shall be
damage. Body maintained based on the CG of
4.Collapse of the injury/
Property crane at site
6 Movement of load
1. Contact/hit with 1.An assistant/signal man should
damage
crawler crane to the any Structure
other be there to convey standard hand
load/ structure mobile/stationary signals to guide the operator or he
location for lifting bodies nearby. must be deployed
2 3 6 1 2 2 TOLERABLE ACCEPTABLE
2.Body parts caught with a Walkie-Talkie
in between For communication. Signal
persons to be trained before the
start of work and walkie to be Site
7 Lifting the 1. Sling Failure due tested
1. Before before theensure
lifting work. the Engineer /
Manager
respective member to loose D shackles 2. Area clearance
availability should belifeline
of a continuous
structure to the deteriorated slings, ensured
made of poly for both persons
propylene and tied
rope,
particular level. etc. objects. to column at both sides
column
4 4 16 2 2 4 TOLERABLE ACCEPTABLE
2. Load may slip along the axis.
from rigging if not 2.Ensure the crane and load
properly attached. lifting appliances are load tested
3. Fall of load and Body and certified by a competent
8 Placement of injury
1. Fall to
of the workers
person from injury/ person and available
1. All workers who are with valid
engaged
assembly to the nearby.
height. Property documents
should wear full body
4. Electrical damage 3. Ensure that the max
positionwith 2. Fall of harness/safety belts andsafe load it
hooked
plumping and hazards/Shock from
materials/tools of the
to the crane
lifelineismade
moreof than
8mm thesteel
alignment hazards
height weight of the load to be lifted
5. 5 4 20 wire ropes. 2 2 4 TOLERABLE ACCEPTABLE
3. Knot
Fall offailure
load. of the 2.Ensure the availability of a
steel
4.Bodywire
partsrope that
Caught continuous lifeline made of poly
is
in tied to columns.
between. propylene rope, tied column to
5.Body strain/Loss of column at both sides along the
Balance axis) and from row to row through
9 Tightening the nut 1. Fall of person
6.Hitting of trussfrom 1. All workers
respective who are engaged
columns.
into the bolt (if height.
structure to must
3. They beshould
qualified
usefor
allheight
other pass
required). 2. Fall of/structures
persons & should PPEs
required wear full body
materials/tools
due to free from harness/safety belts and hooked it
3 3 6 2 1 2 TOLERABLE ACCEPTABLE
height.
movement in air and to the lifeline made of
3. Fallresult
could of load.
in polypropylene ropes or 8mm steel
4. Body parts Caught
injury/property Body wire ropes. 2.Ensure proper
in between.
loss/load falling injury/ tightening of the nut to the anchor
5. Body strain/Loss of Property bolt before releasing the slings.
Balance damage
Body
injury/
10 Releasing the steel 1 to 5 same as above Property 1 to 5 same as above
wire rope sling from 6.Hitting of sling damage 6.Intense care should be
the body wire/D shackles to maintained while releasing.
the body parts of 7.Ensure proper clearance from Site
3 3 6 2 1 2 TOLERABLE ACCEPTABLE Engineer /
workers, while the sling while releasing Manager
releasing

Prepared By Reviewed By Approved By

Name
Designation
SIMPLEX INFRASTRUCTURES LIMITED
TATA HOUSING PROJECT, SEC – 72, GURGAON.

Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA)
FORMAT NO:
JOB TITLE : PCC / SCREED
CONTROLLE
Sl ACTIVITY (JOB STEPS IN PROBABI PROBABI FINAL RESPONSIBI
HAZARDS/RISK CONSEQUENCES SEVERITY RISK PRESENT CONTROL MEASURE SEVERITY RISK D RISK
No SEQUENCE) LITY LITY ASSESSMENT LITY
RATING
1 Placing of concrete Due to tool and tacles Use proper PPE.
by manualy improper handeling body injury/
Property 4 5 20 2 2 4 TOLERABLE ACCEPTABLE

damage

2 Unloading of Hitting the concrete by 1. Stop block are to be placed.


concrete on transit mixer. body injury/ 2. proper
pletform . Property 4 5 20 communication should be 2 2 4 TOLERABLE ACCEPTABLE
damage ensured.

3 Placing concrete Improper Lifting of mateial 1. The hose should not be


bent more that 60'C with the
concrete load.
Site Engineer /
2. Care should be taken to Manager
keep up the continuous flow
of concrete.

body injury/
Property 4 4 16 3. When the floor is in up 2 2 4 TOLERABLE ACCEPTABLE

damage word direction, utmost care is


to be taken.
4. The operation should be
supervised by experienced
supervisor.

Prepared By Reviewed By Approved By

Name

Designation
SIMPLEX INFRASTRUCTURES LIMITED
TATA HOUSING PROJECT, SEC – 72, GURGAON.

Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA)
FORMAT NO:
JOB TITLE : Rainforcemant /Structural Material loading & unloading by crane from trailer,truck .

Sl ACTIVITY (JOB STEPS IN CONSEQUEN CONTROLLED RISK FINAL


HAZARDS/RISK PROBABILITY SEVERITY RISK PRESENT CONTROL MEASURE PROBABILITY SEVERITY RISK RESPONSIBILITY
No SEQUENCE) CES RATING ASSESSMENT

1 Positioning of crane/Hydra a) Accident due to collision 1) Training to signalman should be


near trailer. with personnel . ensured before taking up the work. 2 2 4 TOLERABLE ACCEPTABLE
body injury/
Property 3 4 12
damage 2) Signalman should give proper
signal to crane operator 2 2 4 TOLERABLE ACCEPTABLE

b) Toppeling of crane due 1) Crane operator should have


to uneven ground surface valid licence.
or uneven loading 2 2 4 TOLERABLE ACCEPTABLE

2) Ensure that no persons should


2 2 4 TOLERABLE ACCEPTABLE
body injury/ stand near crane swinging area.
Property 4 5 20
damage 3) Marching route shall be checked
in advance and ensured clear. 2 2 4 TOLERABLE ACCEPTABLE

4) Safe working load (SWL) and


last date of test should displayed 2 2 4 TOLERABLE ACCEPTABLE
on the crane
Site Engineer /
2 Tying sling and D-shackle 1)Improper Selection of 1) Use hand gloves. Manager
sling ,fall of load .
2) Hand injury due to body injury 3 2 6 2 2 4 TOLERABLE ACCEPTABLE
improper handling.

3 Loading and unloading of a) Fall of material due to 1)Load should known and
material with crane damage D-shackle,sling according to it sling should be
and pulley. selected .
2) Inspect all slings, 2 2 4 TOLERABLE ACCEPTABLE
D-shackle for any wear and tear
before its use .

3) check all safety devices for its


body injury/ healthiness 2 2 4 TOLERABLE ACCEPTABLE
Property 4 4 16
b) Improper assessment of damage 1) Never lift the load above the
load rated capacity of material . 2 2 4 TOLERABLE ACCEPTABLE

2) lifting machine and tool should


be third party inspected with valid
form no. 10 2 2 4 TOLERABLE ACCEPTABLE
c) Injury due to fall of body injury/ 1) Tag line should be tied to the
material on person standing Property lifting material. 2 2 4 TOLERABLE ACCEPTABLE
nearby damage
2) No one should be allowed to
4 4 16 stand below the lifted load. 2 2 4 TOLERABLE ACCEPTABLE

3) Area should be clear and


barricaded with a caution board. 2 2 4 TOLERABLE ACCEPTABLE

d) Injury due to caught in body injury 1) No person should be allowed in


between the objects. 3 3 9 the swinging area of crane. 2 2 4 TOLERABLE ACCEPTABLE

e) Collision of lifted material body injury/ 1) before carrying of the lifting Site Engineer /
with other material resulting Property operation check the route that the Manager
in material damage. damage material has to be lifted. 2 2 4 TOLERABLE ACCEPTABLE
3 5 15
2) Signalman should give proper
signal to crane operator 2 2 4 TOLERABLE ACCEPTABLE

4 Removing of sling, D 1) Injury to finger or hand 1) No movement of load should be


shackle allowded while removing sling. 2 2 4 TOLERABLE ACCEPTABLE
body injury 3 2 6
2) Use PPE like hand gloves and
helmet safety shoes etc. 2 2 4 TOLERABLE ACCEPTABLE

Prepared By Reviewed By Approved By


Name
Designation
SIMPLEX INFRASTRUCTURES LIMITED
TATA HOUSING PROJECT, SEC – 72, GURGAON.

Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA)
FORMAT NO:
JOB TITLE : Loading and Unloading Structural Material
Sl ACTIVITY (JOB STEPS CONTROLLED FINAL
HAZARDS/RISK CONSEQUENCES PROBABILITY SEVERITY RISK PRESENT CONTROL MEASURE PROBABILITY SEVERITY RISK RESPONSIBILITY
No IN SEQUENCE) RISK RATING ASSESSMENT
1 Positioning of crane/Hydra a) Accident due to 1) Training to signalman should be
collision with personnel . ensured before taking up the work. 2 2 4 TOLERABLE ACCEPTABLE
body injury/
3 4 12
Property damage 2) Signalman should give proper
signal to crane operator 2 2 4 TOLERABLE ACCEPTABLE

b) Toppeling of crane 1) Crane operator should have


due to uneven ground valid licence.
surface or uneven 2 2 4 TOLERABLE ACCEPTABLE
loading

2) Ensure that no persons should


2 2 4 TOLERABLE ACCEPTABLE
stand near crane swinging area.
body injury/
4 5 20
Property damage
3) Marching route shall be checked
in advance and ensured clear. 2 2 4 TOLERABLE ACCEPTABLE

4) Safe working load (SWL) and Site Engineer /


last date of test should displayed 2 2 4 TOLERABLE ACCEPTABLE Manager
on the crane
2 Tying sling and D-shackle a) Hand injury due to 1) Use hand gloves.
improper handling. body injury 3 2 6 2 2 4 TOLERABLE ACCEPTABLE

3 Loading and unloading of a) Fall of material due to 1) Inspect all slings, D-shackle for
material with crane damage D-shackle,sling any wear and tear before its use .
and pulley. 2 2 4 TOLERABLE ACCEPTABLE

2) check all safety devices for its


body injury/ healthiness 2 2 4 TOLERABLE ACCEPTABLE
4 4 16
Property damage
b) Improper assessment 1) Never lift the load above the
of load rated capacity of material . 2 2 4 TOLERABLE ACCEPTABLE

2) lifting machine and tool should


be third party inspected with valid 2 2 4 TOLERABLE ACCEPTABLE
form no. 10
c) Injury due to fall of body injury/ 1) Tag line should be tied to the
material on person Property damage lifting material. 2 2 4 TOLERABLE ACCEPTABLE
standing nearby
2) No one should be allowed to
4 4 16 stand below the lifted load. 2 2 4 TOLERABLE ACCEPTABLE

3) Area should be clear and


barricaded with a caution board. 2 2 4 TOLERABLE ACCEPTABLE

d) Injury due to caught in body injury 1) No person should be allowed in


between the objects. 3 3 9 the swinging area of crane. 2 2 4 TOLERABLE ACCEPTABLE

e) Collision of lifted body injury/ 1) before carrying of the lifting Site Engineer /
material with other Property damage operation check the route that the Manager
material resulting in material has to be lifted. 2 2 4 TOLERABLE ACCEPTABLE
material damage.
3 5 15
2) Signalman should give proper
signal to crane operator 2 2 4 TOLERABLE ACCEPTABLE

4 Removing of sling, D 1) Injury to finger or 1) No movement of load should be


shackle hand allowded while removing sling. 2 2 4 TOLERABLE ACCEPTABLE
body injury 3 2 6
2) Use PPE like hand gloves and
helmet safety shoes etc. 2 2 4 TOLERABLE ACCEPTABLE

Prepared By Reviewed By Approved By

Name
Designation
SIMPLEX INFRASTRUCTURES LIMITED
TATA HOUSING PROJECT, SEC – 72, GURGAON.

Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA)
JOB TITLE : BACK FILLING FORMAT NO:

Sl ACTIVITY (JOB STEPS IN HAZARDS/RISK CONSEQUEN PROBABI SEVERITY RISK PRESENT CONTROL MEASURE PROBABIL SEVERITY RISK CONTROLLED FINAL RESPONSIBI
No SEQUENCE) CES LITY ITY RISK RATING ASSESSMENT LITY

1 Clearing of site Tripping and cut injury 1. The area should be surveyed for
during housekeeping tripping hazards and workers shall be
Body injury/ briefed for the hazard.
Property 2 2 4 1 2 2 TOLERABLE ACCEPTABLE
damage 2. All persons working shall use PPE's
like helmet, shoes etc.
2 Backfilling by mechanical m/c & 1. Injury due to tools and 1. Experienced persons shall be
manualy tackles. deployed who are aware of handling
Body injury/ backfilling tools.
Property 5 5 25 2 2 4 TOLERABLE ACCEPTABLE Site Engineer /
damage 2. All persons working shall use PPE's Manager
like helmet, shoes etc.

2. Fall of person into the 1. Proper barricading with warning


pit. Body injury 4 4 16 signs to be put. 2 2 4 TOLERABLE ACCEPTABLE

3. Caught in between/ hit 1. Maintaine safe distance from m/c.


by the machine 2.Supervision require in case of
Body injury 4 4 16 working in dense area. 2 2 4 TOLERABLE ACCEPTABLE

Prepared By Reviewed By Approved By

Name

Designation

Page 24 of 40
SIMPLEX INFRASTRUCTURES LIMITED
TATA HOUSING PROJECT, SEC – 72, GURGAON.

Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA)
JOB TITLE : EXCAVATION FOR BUND WALL FORMAT NO:

ACTIVITY (JOB STEPS IN CONSEQUENCE CONTROLLED RISK FINAL


Sl No HAZARDS/RISK PROBABILITY SEVERITY RISK PRESENT CONTROL MEASURE PROBABILITY SEVERITY RISK RESPONSIBILITY
SEQUENCE) S RATING ASSESSMENT

1 Clearing of site Tripping and cut injury 1) The area should be surveyed for tripping
hazards and workers shall be briefed for the
hazard.
Body
injury/Property 2 3 6 2 2 4 TOLERABLE ACCEPTABLE
damage
2)All persons working shall use PPE's like
helmet ,shoes etc.

2 Excavation 1) Injury due to tools and tackles. 1) Experienced persons shall be deployed who
are aware of handling excavation tools.
Body
injury/Property 3 2 6 2 2 4 TOLERABLE ACCEPTABLE
damage 2) Safe distance between crew members to be
maintained to avoid hit injury.
Site Engineer / Manager

2) Fall of person into the pit. 1) Proper access ladder

2) Proper barricading with warning signs to be


Body injury 3 2 6 put. 2 2 4 TOLERABLE ACCEPTABLE

3) Lighting the location during night time

3) Caving in 1) Remove excavated earth immediately.


Body injury 2 2 4 2) Do not keep heavy objects and mud near the 2 2 4 TOLERABLE ACCEPTABLE
edge of pit.
4) Fall of person due to leaving the 1) Impart safety instruction to all worker to
excavated area ovenight guard the area to avaoi fall.

Body injury 3 3 9 2)Proper demarcation around the pit by


2 2 4 TOLERABLE ACCEPTABLE

tape/lighting and cordoning off the area with


sturdy barriers where ever possible.

5) Land slide due to bad 1) Keep 'Danger' sign board and cordon off the
weather/loose nature of soil Body injury 2 2 4 hazardous area. 2 2 4 TOLERABLE ACCEPTABLE

6) Body injury due to fall from 1) Use ladder with guard which is to be secure at
ladder. bottom and top by using mechanized (slips)
means.
Site Engineer / Manager
2)Ladder should be properly stacke at required
Body injury 3 2 6 angle. 2 2 4 TOLERABLE ACCEPTABLE

3) steps of the ladder should be of standard


specification.
3 Removal of excavated materials Fall of stones, earth etc in the 1)Keep the removed earth at least 1.5 m away
excavated pit. from the pit.

Minor injury 2 2 4 2 2 4 TOLERABLE ACCEPTABLE


2) Do not allow structural material at edge of
excavation

Prepared By Reviewed By Approved By

Name

Designation
SIMPLEX INFRASTRUCTURES LIMITED
TATA HOUSING PROJECT, SEC – 72, GURGAON.

Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA)
FORMAT NO:
JOB TITLE : EXCAVATION

ACTIVITY (JOB STEPS IN CONSEQUEN CONTROLLED RISK FINAL


Sl No HAZARDS/RISK PROBABILITY SEVERITY RISK PRESENT CONTROL MEASURE PROBABILITY SEVERITY RISK RESPONSIBILITY
SEQUENCE) CES RATING ASSESSMENT

1 Clearing of site Tripping and cut injury 1) The area should be surveyed for
Body tripping hazards and workers shall be
injury/Pro
4 4 16 briefed for the hazard. 2 2 4 TOLERABLE ACCEPTABLE
perty
damage 2)All persons working shall use PPE's
like helmet ,shoes etc.
2 Excavation 1) injury due to tools and 1) experienced persons shall be
tackles. deployed who are aware of handling
Body excavation tools.
injury/Pro
5 5 25 2 2 4 TOLERABLE ACCEPTABLE
perty 2) Safe distance between crew
damage members to be maintained to avoid hit
injury.

2) fall of person into the 1) proper access ladder


pit.
2) proper barricading with warning
signs to be put.
Body Site Engineer / Manager
5 5 25 3) provide proper slope for stability of 2 2 4 TOLERABLE ACCEPTABLE
injury
excavation.

4) lighting at Night time

3) Caving in 1) provide proper shoring.


2) Remove excavated earth
immediately.
3) Do not keep heavy objects and
muck near the edge of pit.
Minor
injury / 5 5 25 4)Excavation from top to bottom 2 2 4 TOLERABLE ACCEPTABLE

Fatal
5) Provide benching where depth is
more than 3 mtrs. Keep area de-
watered at all time.
6) control wats flow.
d) fall of person due 1) impart safety instruction to all
to leaving the worker to guard against fall.
excavated area
ovenight Minor 2)proper demarcation around the pit
injury / 5 5 25 by tape/lighting and cordoning off the 2 2 4 TOLERABLE ACCEPTABLE

Fatal area with sturdy barriers where ever


possible.

Site Engineer / Manager


e) land slide due to 1) propaer shoring should be done
bad weather. Minor
injury / 5 5 25 2) keep 'Danger' sign board and 2 2 4 TOLERABLE ACCEPTABLE

Fatal cordon off the hazardous area.

f) Body injury due to 1) use ladder with guard which is to be Site Engineer / Manager
fall from ladder. secure at bottom and top by using
mechanized (slips) means.
Minor
injury / 5 5 25 2)ladder should be tied from the top 2 2 4 TOLERABLE ACCEPTABLE

Fatal with a rope to avoid slipping.


3) steps of the ladder should be of
standard specification.

3 Removal of Fall of heavy 1)Keep the removed earth at least 1.5


excavated materials objects/stones,boulde Minor m away from the pit.
rs etc in the injury / 5 5 25 2 2 4 TOLERABLE ACCEPTABLE
excavated pit. Fatal 2) Do not allow structural material at
edge of excavation

Prepared By Reviewed By Approved By

Name
Designation
SIMPLEX INFRASTRUCTURES LIMITED
TATA HOUSING PROJECT, SEC – 72, GURGAON.
Hazard Identification & Risk Assessment and Control Measure Worksheet (HIRA)
JOB TITLE : Dismantling of Overhead gantry crane FORMAT NO:
ACTIVITY CONTROLLED
Sly FINAL
(JOB STEPS IN HAZARDS/RISK CONSEQUENCES SEVERITY PROBABILITY RISK PRESENT CONTROL MEASURE SEVERITY PROBABILITY RISK RISK RESPONSIBILITY
No ASSESSMENT
SEQUENCE) RATING

1 Pre-cleaning of crane and Hand injury / Inhalation of 1)Area shall have adequate clean and Tolerable ACCEPTABLE
near area . gas/Dust proper housekeeping .
Body injury 3 2 6 2)Use of PPE (Hand gloves, 2 1 2
Mask , Goggles)

2 Dismantled of Hook along Improper Selection of 1)Load should known and according to Tolerable ACCEPTABLE
with the wire ropes. sling , ,Material fall or fall it sling should be selected .
of person if not proper 2)Personr should be well
material handleling . trained .
Body injury 3 3 9 2 2 4
3)Proper tool should be used for
dismantled.
3)Use of PPE
(Hand gloves, Goggles , etc) .
3 Dismantling the main IF Proper supervision for 1)Skilled supervisor for the job. Tolerable ACCEPTABLE
trolley. the job is not done can 2)Use guide rope while shifting of
cause fall of material , members with crane Site Engineer / Project
person /body injury Body injury 3 3 9 3)Use of PPE (Hand gloves, Mask , 1 2 2 Manager
Goggles) .

4 Dismantled main beams IF Proper supervision for 1)Skilled supervisor for the job. Tolerable ACCEPTABLE
and Shifting of material. the job is not done can 2)Use guide rope while shifting of
cause fall of material , Body injury /Death 4 4 16 members with crane 2 2 4
person /body injury 3)Use of PPE (Hand gloves, Mask ,
Goggles) .

5 Post Cleaning Hand injury / Inhalation of Use of PPE (Hand gloves, Mask , Tolerable ACCEPTABLE
gas/Dust Goggles)
Body injury / Fume Site Engineer / Project
2 3 6 1 2 2 Manager
mist inhalation

Prepared By Reviewed By Approved By

Name
Designation
Work at Height

Hazard Identifi
JOB TITLE : Work at Height
ACTIVITY (JOB
S.
STEPS IN HAZARDS/RISK
No
SEQUENCE)
1 Lifting of
Shuttering
Material
&Reinforcement
at coloum.

Fall of Person, fall


of material,
Shearing
Page 29
off rope
Work at Height

2 Reinforcement
placing & binding

Fall of Person, fall


of material,
Shearing off rope

Page 30
Work at Height

3 Shuttering

Prepared By: Rajiv Singh


Name: Rajiv Singh
Designation: Safety Engineer

Page 31
Work at Height

SIMPLEX INFRASTRUCTUR
TATA HOUSING PROJECT, SEC –
Hazard Identification & Risk Assessment and Co

CONSEQUEN PROBABILI
SEVERITY RISK
CES TY

Serious
injury or 5 5 25
Fatality Page 32
Work at Height

Serious
injury or 5 5 25
Fatality

Page 33
Work at Height

y: Rajiv Singh

Page 34
Work at Height

X INFRASTRUCTURES LIMITED
NG PROJECT, SEC – 72, GURGAON.
Assessment and Control Measure Worksheet (HIRA)

PROBABILI
PRESENT CONTROL MEASURE SEVERITY
TY

2 2

Page 35
Work at Height

2 2

Page 36
Work at Height

2 2

Approved By: S. K

Page 37
Work at Height

et (HIRA)

FINAL
CONTROLLED RESPONSIBIL
RISK ASSESS
RISK RATING ITY
MENT

ACCEPT
4 TOLERABLE
ABLE

Site
Engineer /
Page 38
Manager
Work at Height

Site
ACCEPT Engineer /
4 TOLERABLE Manager
ABLE

Page 39
Work at Height

ACCEPT
TOLERABLE
ABLE

ACCEPT
4 TOLERABLE
ABLE

roved By: S. K Pal

Page 40