Project: C1145 Edificios Metor

CIVIL WORK

Period from Jan-29-2007 to Feb-04-2007

Work accomplished during this week: Cumulative Progress


Issue of:
1145-01-100-C73-DWG-001 (1) Hydraulic & Sanitary Installations - Details 80 %
1145-01-100-C73-DWG-002 (1) Control Room – hydraulic Installations 80%
1145-01-100-C71-CAL-007 Hydraulic & Sanitary Calculations for Maint. Office & Shop Bldg. 60%
1145-01-100-C71-CAL-008 Hydraulic & Sanitary Calculations for Control Room Bldg. 40%

Goals and Plans for next week (Feb-05-2007 to Feb-11-2007):


Continue with the development of:
1145-01-100-C73-DWG-003 (1) Electrical Main SS – Hydraulic & Sanitary Installations
1145-01-100-C73-DWG-004 (2) Maint. Office & Maint. Shop– Sanitary Installations
1145-01-100-C71-CAL-009 Hydraulic & Sanitary Calculations for Main Elect. SS Bldg.

Pending information:
Final Architectural drawings.
Final Soil Report.
Final Design Basis

Notes:
During December of last year INECOL produced a list of Load Combination Factors, using AISC-LRFD that could be included in “Design Basis” document;
these load combination factors are under study by CCS and will be commented as soon as possible in order to be used in the calculations final issue.
INECOL is waiting load information related with the new hoist inside the Electrical Main SS over the auxiliary generator, in order to define the pre-cast roofing
elements. INECOL sent to INEVEN a sketch of the SS roof showing Dead and Live loads; in order to consult a technical department of one of the producers of
this type of pre-cast elements.