Safety Interlock 1 Lube Oil header pressure > 3.0 kg/cm2 2 Lube oil pump differential pressure < 5000 mmwc 3 Lube oil tank temperature < 50 degC Initial Start up: 1 Ensure the Oil level in tank > 60%. 2 Open the suction & Discharge valve of lube oil pump. 3 Open the valves before & after the filter and lube oil cooler. 4 Ensure electric source supplied for motor. 5 Ensure Cooling water supply and return line valves open and system properly vented. 6 Ensure Minimum Recirculation & balancing line discharge valve to be kept open. Operation: 1 Switch on the System. 2 Ensure NO oil leakage. 3 Ensure the oil flow through the line from rota meter. 4 Start water flow into the heat exchanger (Oil Cooler) 5 Now the system is ready for use BFP SAFTEY INTERLOCK. 1 Motor winding temp < 130 deg C. 2 Motor bearing DE and NDE temp < 110 deg C. 3 Pump bearing DE and NDE temp < 90 deg C. 4 Pump DE and NDE side vibration < 7 mm/s 5 Motor DE and NDE side Vibration < 7 mm/s BFP PROCESS INTERLOCK. 1 Feed water line to pump suction DP < 3000 mmwc. 2 Deaerator level > 20 %. 3 BFP Suction valve open feed back. 4 BFP Cooling water Pressure > 2 kg/cm2. 5 BFP suction pressure > Corresponding the Saturation temp. (Value shown on DCS) BFP START permission. 1 BFP oil skid pressure > 0.6 kg/cm2 2 BFP oil temp <50 deg C. 3 BFP SAFTEY INTERLOCK OK. 4 BFP PROCESS INTERLOCK OK. BFP TRIP INTERLOCK. 1 BFP oil skid pressure < 0.6 kg/cm2 2 BFP oil temp >50 deg C. 3 BFP Oil skid filter DP > 5000 mmwc. 4 BFP SAFTEY INTERLOCK NOT OK. 5 BFP PROCESS INTERLOCK NOT OK.
NOTE: OIL SKID PUMP AUTO CHANGE OVER WHEN OIL PRESSURE < 0.8 kg/cm2. IF PUPM IN AUTO MODE.