Professional Documents
Culture Documents
CH 07 Cost Estimating Exercises RevA
CH 07 Cost Estimating Exercises RevA
5. A ____________________is used for costs are that are anticipated for uncertain
events. These costs are for “known, unknowns".
10. The budgeting technique in which we monitor and limit large variations in the
expenditure of project funds is called ____________________ (Limiting funds
available for a specific time period, such as by fiscal year or by month).
13. You are told that the SPI on a project is .8. This means the project is: Behind or
Ahead of schedule.
14. You are told the CPI is 1.2 on a project. This means that the project is getting
____________________worth of work for each $1.00 spent.
15. If you are given the net present values of 2 projects then you do not have enough
information to know which project is a better investment. True or False
a. BAC – _____________________________________
b. EV- _____________________________________
c. PV – _____________________________________
d. AC – _____________________________________
e. CV- _____________________________________
f. SV – _____________________________________
g. CPI – _____________________________________
h. SPI – _____________________________________
i. EAC – _____________________________________
j. ETC – _____________________________________
k. VAC – _____________________________________
l. TCPI – _____________________________________
• Sunk costs • Cost control
• funding limit reconciliation • The cost baseline
• Management contingency reserves • Determine budget
• Contingency Reserve • Elaboration
• Parametric estimating • Bottom up estimating
• Analogous estimating • Estimating Costs