Daily Working Record

Name : PHAL Pisey

Month : Mar 2018


Date Contents Achievement Remark
26 Mon -Join Ground Breaking Ceremony -Back to PNH
-Comparing drawing with the new
drawing of CP2 and CP3.
27 Tue -Completed.
-Combine documents for Paper drain
(General DW and Specification)
-Quantity for Bearing and Expansion
joint for Bridge Prek Chhloung, Peam
Te Bridge and combine quantity for 7
28 Wed Bridges. -Completed.
-Combine documents of Bearing
expansion joint for CP2
(DW, Quantity and Specification)
-Make drawing of Cofferdam for Bridge
29 Thu -Completed.
58 and 59 for Side view.
-Make drawing of Cofferdam for Bridge
58 and 59 for Plan View.
30 Fri -Completed.
-Comparing drawing of Abutment for
Bridge Project (Peam Te Br.).
-Comparing drawing of Abutment for
Bridge Project (Prek Chhloung Br.).
31 Sat
-Extract the quantity of reinforcement
for Prek Chhloung Bridge.