Professional Documents
Culture Documents
Earned Schedule Leads To Improved Forecasting
Earned Schedule Leads To Improved Forecasting
to Improved Forecasting
Walt Lipke
waltlipke@cox.net
(405) 364-1594
ES
SPI(t) = SV(t) = ES − AT
AT
Projection of EV
onto PMB
EV
ES = All of May + Portion of June
EV($) - PV(May)
ES = 5 +
PV(June) - PV(May)
AT = 7
J F M A M J J A S O N
PROMAC 2006 Time 7
Sep 27-29 Copyright 2006 Lipke
Earned Schedule Formulae
• EScum is the:
Number of completed PV time increments EV exceeds + the
fraction of the incomplete PV increment
• EScum = C + I
C = number of time increments for EV ≥ PV
I = (EV – PVC) / (PVC+1 – PVC)
• ESperiod(n) = EScum(n) – EScum(n-1)
= ∆EScum
Schedule Performance
Indicators Index
SPI(t) SPI(t) = ES / AT
20 2
0 0
-20 Stop wk 19 -2
Dollars (,000)
-40 -4
Sched wk 20 Re-start wk 26
Weeks
-60 -6
-80 -8
-100 -10
-120 -12
-140 -14
-160 -16
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 32 33 34
Elapsed Weeks
BAC
$$
PV
EV
SV(t)
ES AT PD
PROMAC 2006 Time
Sep 27-29 Copyright 2006 Lipke 17
How Can This Be Used?
• Tasks behind – possibility of impediments or constraints can
be identified
• Tasks ahead – a likelihood of future rework can be identified
• The identification is independent from schedule efficiency
• The identification can be automated
Percent Difference
1.06 -0.02
1.04
CPIcum
-0.04
1.02
1.00 -0.06
0.98
-0.08
0.96
0.2 0.4 0.6 0.8 1.0 -0.10
BAC
$$
PV
EV
SV(t)
ES AT PD
PROMAC 2006 Time
Sep 27-29 Copyright 2006 Lipke 25
Schedule Performance
• EV isn’t connected to task sequence
– Hypothesis: Completion sequence of tasks
affects performance efficiency
• Incorrect task sequencing occurs when there is …
– Impediment or constraint
– Poor process discipline
• Improper performance sequence may cause …
– Overloading of constraint
– Performance of tasks w/o complete inputs
ΣEVj ⇐ PV @ ES
Total EV
EV(r)
EV(r) is performed at risk of creating rework
Portion colored is usable
Portion colored is unusable
PROMAC 2006 Copyright 2006 Lipke 31
Sep 27-29
Effective Earned Value
• Effective earned value is a function of EV, P, and
Rework
EV(e) = f (EV, P, Rework)
• EV(e) = [ (1 + P ∗ R%) / (1 + R%) ] ∗ EV
R% = Rework Percent
R% = fraction of EV(r) unusable ÷ by fraction of EV(r) usable
{ EV(r) = Σ PVj - Σ EVj }
• EV(e) = [ (P + 2) / 3 ] ∗ EV
when R% = 50%
CPI
1.1
CPI(e)
Index Value
1.0
0.9
P – Factor
0.8
0.7
0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
Percent Complete
PROMAC 2006 Copyright 2006 Lipke 34
Sep 27-29
Graphs of CPI, CPI(e)
& P - Factor (real data)
1.2
1.1
CPI
Index Value
1.0 CPI(e)
SPI(t)
0.9 SPI(te)
P- Factor
0.8
0.7
0.1 0.2 0.3 0.4 0.5 0.6 0.7 0.8 0.9 1.0
Percent Complete
$1,250 45
IEAC(e) IEAC(te)
43
$1,150
(x 1000)
Months
IEAC
41
IEAC(t)
39
$1,050
37
BAC = $1,000,000 PD = 36 months
$950 35
0.2 0.4 0.6 0.8 1.0 0.2 0.4 0.6 0.8 1.0
Percent Complete Percent Complete