Professional Documents
Culture Documents
PROJECT
IMPLEMENTATION PLAN
PROPOSED 10-STOREY
DORMITORY BUILDING
CE168P / A1
Group Members
Cayabyab, Carlo
Lacanienta, Kylah Mari
Luluquisin, Coleen
Naorbe, Evangeline
Racho, Erwin Jed
I. PROJECT INFORMATION
PROJECT BRIEF
PROJECT LOCATION
PROJECT TEAM
PROJECT INFORMATION
Front Elevation
Rear Elevation
Right-Side Elevation
Left-Side Elevation
PROJECT DETAILS
Building Footprint
12.5 m
37.3 m
37.3 m
Building Area
466.25 sq. m
12.5 m
Front Elevation
At the ground floor located is the vehicular entrance, a wrought iron accordion
door provided with complete locking mechanisms. There are also two jalousie
windows and a fixed window beside the entrance. For the second floor up to
the tenth floor, on each level, there are four casement windows and a jalousie
high window at the center. The wall at the ground floor has a concrete groove
finish with a laid hollow blocks pattern. The rest of the front elevation is finished
with a 1-feet concrete groove. There are also pre-cast exterior mouldings
between each floor and concrete railings at the roof deck. A multi-purpose hall
stands on the roof deck.
Rear Elevation
A perimeter wall makes up the ground floor up to the mezzanine floor. For the
second floor up to the tenth floor, on each level, there are four casement
windows and an awning with a fixed window at the center. The whole rear
elevation has a plain cement painted finish.
Formworks Requirements
FOOTINGS
Floor Man-Hours Man Power Hours Days
Foundation 402.77 36 11.19 3
BEAMS
Floor Man-Hours Man Power Hours Days
Foundation 666.30 36 18.51 2
GF 669.90 36 18.61 2
MF 667.92 36 18.55 2
2F 670.20 36 18.62 2
3F 669.81 36 18.61 2
4F 669.32 36 18.59 2
5F 669.46 36 18.60 2
6F 671.28 36 18.65 2
7F 670.86 36 18.63 2
8F 669.22 36 18.59 2
9F 671.18 36 18.64 2
10F 671.51 36 18.65 2
RD 402.91 36 11.19 1
SLABS
Floor Man-Hours Man Power Hours Days
Foundation 0.00 36 0.00 0
GF 434.40 36 12.07 2
MF 433.50 36 12.04 2
2F 433.94 36 12.05 2
3F 433.69 36 12.05 2
4F 433.37 36 12.04 2
5F 433.46 36 12.04 2
6F 434.64 36 12.07 2
7F 434.37 36 12.07 2
8F 433.31 36 12.04 2
9F 434.58 36 12.07 2
10F 434.79 36 12.08 2
RD 434.70 36 12.08 2
COLUMNS
Floor Man-Hours Man Power Hours Days
Foundation 273.75 36 7.60 1
GF 547.50 36 15.21 2
MF 492.75 36 13.69 2
2F 547.88 36 15.22 2
3F 547.56 36 15.21 2
4F 547.16 36 15.20 2
5F 547.27 36 15.20 2
6F 548.76 36 15.24 2
7F 548.42 36 15.23 2
8F 547.08 36 15.20 2
9F 548.68 36 15.24 2
10F 548.95 36 15.25 2
RD 329.37 36 9.15 1
SHEAR WALLS
Floor Man-Hours Man Power Hours Days
Foundation 241.00 36 6.69 1
GF 482.00 36 13.39 2
MF 433.80 36 12.05 2
2F 481.87 36 13.39 2
3F 481.59 36 13.38 2
4F 481.23 36 13.37 2
5F 481.34 36 13.37 2
6F 482.65 36 13.41 2
7F 482.34 36 13.40 2
8F 481.17 36 13.37 2
9F 482.58 36 13.40 2
10F 482.81 36 13.41 2
RD 481.30 36 13.37 2
Reinforcement Requirements
Summary of Duration
FOOTINGS
Floor Man-Hours Man Power Hours Days
Foundation 812.81 36 22.58 3
BEAMS
Floor Man-Hours Man Power Hours Days
Foundation 553.76 36 15.38 2
GF 552.93 36 15.36 2
MF 540.42 36 15.01 2
2F 553.62 36 15.38 2
3F 553.28 36 15.37 2
4F 552.87 36 15.36 2
5F 552.81 36 15.36 2
6F 554.49 36 15.40 2
7F 554.16 36 15.39 2
8F 552.81 36 15.36 2
9F 554.43 36 15.40 2
10F 554.70 36 15.41 2
RD 332.82 36 9.24 1
SLABS
Floor Man-Hours Man Power Hours Days
Foundation 0.00 36 0.00 0
GF 699.64 36 19.43 2
MF 698.03 36 19.39 2
2F 702.58 36 19.52 2
3F 702.15 36 19.50 2
4F 701.63 36 19.49 2
5F 701.55 36 19.49 2
6F 703.69 36 19.55 2
7F 703.26 36 19.54 2
8F 701.55 36 19.49 2
9F 703.60 36 19.54 2
10F 703.95 36 19.55 2
RD 702.14 36 19.50 2
COLUMNS
Floor Man-Hours Man Power Hours Days
Foundation 266.92 36 7.41 1
GF 533.83 36 14.83 2
MF 479.01 36 13.31 2
2F 532.23 36 14.78 2
3F 531.90 36 14.78 2
4F 531.52 36 14.76 2
5F 531.45 36 14.76 2
6F 533.07 36 14.81 2
7F 532.75 36 14.80 2
8F 531.45 36 14.76 2
9F 533.01 36 14.81 2
10F 533.27 36 14.81 2
RD 319.96 36 8.89 1
SHEAR WALLS
Floor Man-Hours Man Power Hours Days
Foundation 243.64 36 6.77 1
GF 487.27 36 13.54 2
MF 438.85 36 12.19 2
2F 487.61 36 13.54 2
3F 487.31 36 13.54 2
4F 486.96 36 13.53 2
5F 486.90 36 13.52 2
6F 488.38 36 13.57 2
7F 488.09 36 13.56 2
8F 486.90 36 13.52 2
9F 488.32 36 13.56 2
10F 488.56 36 13.57 2
RD 488.63 36 13.57 2
Concrete Requirements
Concrete per Floor (cu. m)
Shear
Floor Footings Beams Slabs Columns Total
Walls
Foundation 154.88 77.65 0.00 34.19 30.07 296.79
GF 77.43 50.25 38.25 33.21 199.14
MF 77.22 50.31 34.24 30.11 191.87
2F 77.55 50.21 38.04 33.45 199.25
3F 77.50 50.18 38.01 33.43 199.13
4F 77.44 50.14 37.99 33.41 198.98
5F 77.44 50.14 37.98 33.41 198.96
6F 77.67 50.29 38.10 33.51 199.56
7F 77.63 50.26 38.08 33.49 199.45
8F 77.44 50.14 37.98 33.41 198.96
9F 77.66 50.29 38.09 33.50 199.55
10F 77.70 50.31 38.11 33.52 199.65
RD 46.62 50.19 22.87 33.43 153.11
Sum Total 2634.40
Summary of Duration
FOOTINGS
Floor Man-Hours Man Power Hours Days
Foundation 774.40 36 21.51 3
BEAMS
Floor Man-Hours Man Power Hours Days
Foundation 465.92 36 12.94 2
GF 464.60 36 12.91 2
MF 463.34 36 12.87 2
2F 465.32 36 12.93 2
3F 465.02 36 12.92 2
4F 464.66 36 12.91 2
5F 464.66 36 12.91 2
6F 466.04 36 12.95 2
7F 465.80 36 12.94 2
8F 464.66 36 12.91 2
9F 465.98 36 12.94 2
10F 466.22 36 12.95 2
RD 279.73 36 7.77 1
SLABS
Floor Man-Hours Man Power Hours Days
Foundation 0.00 36 0.00 0
GF 526.18 36 14.62 2
MF 526.81 36 14.63 2
2F 525.76 36 14.60 2
3F 525.45 36 14.60 2
4F 525.03 36 14.58 2
5F 525.03 36 14.58 2
6F 526.60 36 14.63 2
7F 526.28 36 14.62 2
8F 525.03 36 14.58 2
9F 526.60 36 14.63 2
10F 526.81 36 14.63 2
RD 525.55 36 14.60 2
COLUMNS
Floor Man-Hours Man Power Hours Days
Foundation 237.44 36 6.60 1
GF 478.13 36 13.28 2
MF 427.95 36 11.89 1
2F 475.50 36 13.21 2
3F 475.13 36 13.20 2
4F 474.88 36 13.19 2
5F 474.75 36 13.19 2
6F 476.25 36 13.23 2
7F 476.00 36 13.22 2
8F 474.75 36 13.19 2
9F 476.13 36 13.23 2
10F 476.38 36 13.23 2
RD 285.83 36 7.94 1
SHEAR WALLS
Floor Man-Hours Man Power Hours Days
Foundation 238.64 36 6.63 1
GF 474.43 36 13.18 2
MF 430.07 36 11.95 1
2F 477.86 36 13.27 2
3F 477.57 36 13.27 2
4F 477.29 36 13.26 2
5F 477.29 36 13.26 2
6F 478.71 36 13.30 2
7F 478.43 36 13.29 2
8F 477.29 36 13.26 2
9F 478.57 36 13.29 2
10F 478.86 36 13.30 2
RD 477.57 36 13.27 2
Project Stakeholders
SCHEDULE SUMMARY
S-CURVE
10,000,000.00 70,000,000.00
60,000,000.00
50,000,000.00
6,000,000.00 40,000,000.00
4,000,000.00 30,000,000.00
20,000,000.00
2,000,000.00
10,000,000.00
0.00 0.00
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Series1 Series2
REBAR DEMAND
FORMWORKS DEMAND
CONCRETE DEMAND
MANPOWER DEMAND
EQUIPMENT LOADING
Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Bulldozer 3
Compactor 3
Feller
3
Bunchers
Excavator 7
Submersible
2
Pump
Dump Truck 1
Backhoe 3
Vibro Hammer 3
Air
3
Compressor
Tower Crane 18 30 31 30 31 31 30 31 29
IV. CONSTRUCTION METHODS AND SITE LOGISTICS
Pile Foundation
Day 12-14: Formworks of Beam and Slab
Pile Foundation
Pile Foundation Work Process
1. Excavation
2. Dewatering
3. Pile Driving
4. Pile Hacking
5. Gravel Bedding
6. Formworks of Pile Caps for Pile Cap Placing
7. Reinforcement of Pile Caps
8. Concrete Pouring for Pile Caps
Beams and Columns
Column Formworks
1. Rebar installation
2. Rebar Inspection
3. Column formworks
4. Application of oil preceding to closure
5. Inspection of formworks
6. Application of turnbuckles for lateral support
7. Concrete pouring
8. Removal of turnbuckles
9. Removal of formworks
10. Curing
Shear Wall Formworks
1. Install formworks
2. Inspection of rebars, formworks and supports
3. Application of oil preceding to closure
4. Concrete pouring
5. Removal of formworks
Beam and Slab Formworks
1. Rebar Installation
2. Formworks
3. Inspection preceding to closure and pouring
4. Concrete Pouring
5. Removal of formworks
Stair Formworks
1. Rebar Installation
2. Formworks
3. Inspection preceding to closure and pouring
4. Concrete Pouring
5. Removal of formworks
V. WORK SIMULATION
Land Acquired
Date as of: February 1, 2019
Excavation
Date as of: March 6, 2019
Pile Driving
Date as of: March 15, 2019
Pile Hacking
Date as of: March 19, 2019
Pile Backfilling
Date as of: March 20, 2019
Date as of:
9th Floor Wet Works Start: November 15, 2019
3rd Floor Dry Works Start: November 15, 2019
Date as of:
10th Floor Wet Works Start: November 19, 2019
4th Floor Dry Works Start: November 19, 2019
Date as of:
Roof Deck Wet Works Start: November 22, 2019
5th Floor Dry Works Start: November 22, 2019
Date as of:
6th Floor Dry Works Start: November 26, 2019
Date as of:
7th Floor Dry Works Start: November 29, 2019
Date as of:
8th Floor Dry Works Start: December 4, 2019
Date as of:
9th Floor Dry Works Start: December 7, 2019
Date as of:
10th Floor Dry Works Start: December 11, 2019
Date as of:
Roof Deck Dry Works Start: December 14, 2019
Finish Project
Date as of: December 21, 2019
TEMPORARY WORKS AND SITE LOGISTICS
1. Workers’ Lounge
2. Rebar Stockyard and Fabrication
3. Genset
4. Crane
5. Stockyard and Warehouse
6. Convan Office
7. Guard House