You are on page 1of 4

Project :

Location :

ASPHALTING CHECKLIST
NO INSPECTION ITEM
ITEM

1
Stone Crusher : Confirm to produce properly four (4) times fractions in confirmity with JMF

2 Asphalt Mixing Plant : Properly Calibrate in weighing wirh aggregats required for mixing hot-
mix equal to the JMF. To confirm final product temeperature of 145° - 155° C

3 Site Preparation

3.1 Shop Drawing


3.2 Survey, Verification of coordinate and elevations

3.3 Equipment mobilzation, verification & installation


3.4 Cleaning surafce status to be covered

3.5 Delivering time properly set up


4 Execution of work
4.1 Prime Coat, tack coat spraying quantity

- Prime : 0.4 - 1.3 Liter / m²


- Tack : 0.51 Liter / m² (3 times test per 200 m)

4.2 Spreading of asphalt mixture


- After 6-8 hours spraying of prime coat & tack coat
- Proper spreading temperature : 125° - 145° C

- May not allow surface crack ; tearing or other damages


4.3 Compaction

- Initial compacting by tandem = 4km/hour (maintained temperature : 125° - 145° C)


- Secondary compaction bt pnematic tire roller : 10 km/hour (maintained temperature :
100° - 125° C)

-
Finishing Rolling : Temperature over 90° C (it may be omitted provided compaction after
secondary rolling is adequate)
Finishing Rolling : Temperature over 90° C (it may be omitted provided compaction after
secondary rolling is adequate)

5 Test

5.1 Material test comply with specification and the contractor methode of statement
5.2 Field Density Test

Inspected by :

CONSULTAN
Date :

INSPECTION RESULT
REMARK
OK NOT OK
Prepared by :

CONTRACTOR