DAVIES TECHNICAL SOLUTIONS INC.

CONSTRUCTION WEEKLY PROJECT UPDATE REPORT

April 7 - 13, 2018

1. Executive Summary as of
1.1 Safety TRIR s
TRIR Derivation (Total Recordable Incident Rate)
= (Number of OSHA Recordable Incidents*200,000) / (Total Number of Hours Work)
= (0 * 200,000) / 9670
=0%

1.2 Project Status Update

DAVIESTECH PROJECT STATUS

As of March 31 – April 6, 2018

Target % Actual % Variance


39.54 % 26.65 % 12.89%

1.2.1 S Curve % of Financial Completion

Target: 39.54 % (P 7,591,680.00)


Actual: 26.65 % (P 5,116,800.00)
Variance: 12.89 %

1.2.2 CPM Schedule


1.2.2.1 Project Full Completion with Beneficial Occupancy Date: August 31, 2018
1.2.2.2 Days Ahead / (Delayed): 31.3 = 32 days /DELAYED

Days Ahead/Delay:

= (Actual – Projected) ÷ (100%/Total Contract Days)

= (26.65 %- 39.54 %) ÷ (100% / 243 days)

= -12.89 % / (.412)

= 31.3
1.2.2.3 Forecast Completion Date: August 31, 2018
1.2.2.4 REASON FOR DELAY OF WORKS
1.2.2.4.1 Availability of Areas (January – February 2018)
1.2.2.4.2 Manpower & Materials
1.2.2.4.3 Areas not yet handover / punchlist but are included on S-Curve
1.2.2.4.4 Proper Scheduling and follow up for Waterproofing works
1.2.3 Critical Milestone Dates

Actual/Forecast Days
Event/Activity Target Date Completion Date Ahead/Days
Delayed

 Application of Krystacem-X (Car Park 1 - 4 Jan 27 – Feb 2, April 30, 2018 88 Days
Flooring Partial Areas) 2018

 Hand over/Punchlist/Rectified ( Level 1 - 3 Jan 27 – Feb 2, April 30, 2018 88 Days


Area) 2018

 Application of Waterproofing (Embedseal)


at Other Area. ( Level 4 - 7 Area) Jan 27 – Feb 2, June 30, 2018 149 Days
2018

 Application of Waterproofing (Swelable


and Waterstop) Jan 27 – Feb 2, June 30, 2018 149 Days
2018

 Application of Krystacem-X (Car Park 1 - 4 Feb 3 – Feb 9, April 30, 2018 81 Days
Flooring Partial Areas) 2018

 Hand over/Punchlist/Rectified ( Level 1 - 3 Feb 3 – Feb 9, April 30, 2018 81 Days


Area) 2018

 Application of Waterproofing (Embedseal)


at Other Area. ( Level 4 - 7 Area) Feb 3 – Feb 9, June 30, 2018 142 Days
2018

 Application of Waterproofing (Swelable


and Waterstop) Feb 3 – Feb 9, June 30, 2018 142 Days
2018

 Application of Krystacem-X (Car Park 1 - 4 Feb. 10 – Feb. April 30, 2018 74 Days
Flooring Partial Areas) 16, 2018

 Hand over/Punchlist/Rectified ( Level 1 - 3 Feb. 10 – Feb. April 30, 2018 74 Days


Area) 16, 2018

 Application of Waterproofing (Embedseal)


at Other Area. ( Level 4 - 7 Area) Feb. 10 – Feb. June 30, 2018 135 Days
16, 2018

 Application of Waterproofing (Swelable


and Waterstop) June 30, 2018 135 Days
Feb. 10 – Feb.
16, 2018

Green – Accomplishment on Schedule


Orange – Accomplishment but Delayed
Red – Delayed
1.1.1 Procurement Status Update (Not Applicable)

Quantity
Packages
Total Awarded On-going/Bid Nego For Bid

Long Lead
Regular
For Detailed Package Procurement Status

1.1.2 Total Man-Days This Period

As of April 7 - 13, 2018

Total Man Days = 24 days

1.3 Unit Turnover Status Update ( Not Applicable )

Total # of Target Turn Over Actual Turn Over Variance


Units Previous This Total Previous This Total %
Period Period

1.4 Bonds/Insurance Updates


(As of November 30, 2017,)

Expiring Within 1 2 3 6
Months Months Months Months
CARI 
Performance Bond 

1.5 Key Updates/ Issue and Action Plan Updated / Issues and Action Plan
1.5.1 Key Updates / Issue and Action Plan

 Hand over area by ARDI at Foundation Grid Line Z’-AA/29-30 Sewage Fit/Grease Tank
date 04 April 2018
 Daviestech will punchlist the area of handover by ARDI.
 Hand over area by ARDI at Foundation Grid Line F-H/29-30, Sewage Fit/Grease Tank
and Grid Line L-N/29-30 Sewage Fit/Grease Tank dated 13 March 2018
 Daviestech will punchlist the remaining area of hand over by ARDI.
 Finished application of waterproofing on Retaining Walls at Lower Ground Grid Line
T-W/28-25a, 1st coat and 2nd coat partial area.
 Hand over area by ARDI at Lower Ground Grid Line 24-30/X-W, Car Park 1 to Car Park
4 Grid Line 29-30/W.
 Daviestech will punchlist the remaining area of hand over by ARDI.

1.5.2 Other Updates / Issues


 Concerns: Hand over Area by ARDI
 Concerns: Additional Area of application.
 Concerns: Additional Area of hand over for application of waterproofing.
 Concerns: Additional Area of hand over for application of waterproofing.

1.6 Permits Status ( Not Applicable )

2. Detailed Project Report


2.1 Safety Report for Year
TRIR Derivation (Total Recordable Incident Rate)
(𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝑂𝑆𝐻𝐴 𝑅𝑒𝑐𝑜𝑟𝑑𝑎𝑏𝑙𝑒 𝐼𝑛𝑐𝑖𝑑𝑒𝑛𝑡𝑠)∗200,000
=
𝑇𝑜𝑡𝑎𝑙 𝑁𝑢𝑚𝑏𝑒𝑟 𝑜𝑓 𝐻𝑜𝑢𝑟𝑠 𝑊𝑜𝑟𝑘
= (0 *200,000)/ 9670
=0%

Number of OSHA Total Number of Hours


Contractor Recordable Incidents Worked to Date TRIR

1.DAVIESTECH 0 9910 0%

2.2 Financial Accomplishment Percentage of Completion Derivation

Target: 39.54 % (P 7,591,680.00)


Actual: 26.65 % (P 5,116,800.00)
Variance: 12.89 %

% Completion per Contract Package

Package # Contractor Target % Actual % Variance


Name
Previous This To Date Previous This To Date %
Period Period

CP-08 DAVIESTECH 50.81 % 5.24 % 56.05 % 17.68 % 3.8% 21.48 % 34.57 %

Total 50.81 % 5.24 % 56.05 % 17.68% 3.8% 21.48 % 34.57 %

2.3 Physical Accomplishment CPM Analysis


2.3.1 CPM Schedule
2.3.1.1 Project Full Completion with Beneficial Occupancy Date: August 31, 2018
2.3.1.2 Days Ahead / (Delayed): 31.3 = 32 days /DELAYED

Days Ahead/Delay:

= (Actual – Projected) ÷ (100%/Total Contract Days)

= (26.65 %- 39.54 %) ÷ (100% / 243 days)

= -12.89 % / (.412)

= 31.3

2.3.1.3

Forecast Completion Date: August 31, 2018

2.3.2 Critical Activities Analysis: (Not Applicable)


Critical Duration Target Actual Target Actual Ahead/
Activity Start Date Start Date Completion Completion (Delayed)
Date Date

2.3.3 Activities Which Will Turn Critical (Not Applicable)


Activities Late Start Date

For 1-Month to +3 months CPM Network, see, Annex 3.3

For 3- Month to Look Ahead Construction Activities, see, Annex 3.

2.4 Mile Stone Dates


2.4.1 Critical Milestone Dates
Actual/Forecast Days
Event/Activity Target Date Completion Date Ahead/Days
Delayed

 Application of Krystacem-X (Car Park 1 - 4 Jan 27 – Feb 2, April 30, 2018 88 Days
Flooring Partial Areas) 2018

 Hand over/Punchlist/Rectified ( Level 1 - 3 Jan 27 – Feb 2, April 30, 2018 88 Days


Area) 2018

 Application of Waterproofing (Embedseal)


at Other Area. ( Level 4 - 7 Area) Jan 27 – Feb 2, June 30, 2018 149 Days
2018
 Application of Waterproofing (Swelable
and Waterstop) Jan 27 – Feb 2, June 30, 2018 149 Days
2018

 Application of Krystacem-X (Car Park 1 - 4 Feb 3 – Feb 9, April 30, 2018 81 Days
Flooring Partial Areas) 2018

 Hand over/Punchlist/Rectified ( Level 1 - 3 Feb 3 – Feb 9, April 30, 2018 81 Days


Area) 2018

 Application of Waterproofing (Embedseal)


at Other Area. ( Level 4 - 7 Area) Feb 3 – Feb 9, June 30, 2018 142 Days
2018

 Application of Waterproofing (Swelable


and Waterstop) Feb 3 – Feb 9, June 30, 2018 142 Days
2018

 Application of Krystacem-X (Car Park 1 - 4 Feb. 10 – Feb. April 30, 2018 74 Days
Flooring Partial Areas) 16, 2018

 Hand over/Punchlist/Rectified ( Level 1 - 3 Feb. 10 – Feb. April 30, 2018 74 Days


Area) 16, 2018

 Application of Waterproofing (Embedseal)


at Other Area. ( Level 4 - 7 Area) Feb. 10 – Feb. June 30, 2018 135 Days
16, 2018

 Application of Waterproofing (Swelable


and Waterstop) Feb. 10 – Feb. June 30, 2018 135 Days
16, 2018

Green – Accomplishment on Schedule


Orange – Accomplishment but Delayed
Red – Delayed
For Contractor Qualitative Accomplishment, see Annex 3.

2.4.2 Milestone Dates Per Package

2.4.3 Man- Days Tabulation Per Package Per Worker Trade


For Manpower Loading, see Annex 2. 5

2.5 Unit Turnover Status (Not Applicable)


2.5.1 Unit Turnover Status Update

Total # of Target Turn Over Actual Turn Over Variance


Units Previous This Total Previous This Total %
Period Period

2.5.2 Turnover Status Per Floor (Not Applicable)

# of Target Turn Over Actual Turn Over Variance


Floor Units Previous This Total Previous This Total %
Period Period

For Detailed Unit Status, see Annex 2.6

2.6 Updated / Issues and Action Plan


2.6.1 Key Updates / Issue and Action Plan

 Hand over area by ARDI at Foundation Grid Line Z’-AA/29-30 Sewage Fit/Grease Tank
date 04 April 2018
 Daviestech will punchlist the area of handover by ARDI.
 Hand over area by ARDI at Foundation Grid Line F-H/29-30, Sewage Fit/Grease Tank
and Grid Line L-N/29-30 Sewage Fit/Grease Tank dated 13 March 2018
 Daviestech will punchlist the remaining area of hand over by ARDI.
 Finished application of waterproofing on Retaining Walls at Lower Ground Grid Line
T-W/28-25a, 1st coat and 2nd coat partial area.
 Hand over area by ARDI at Lower Ground Grid Line 24-30/X-W, Car Park 1 to Car Park
4 Grid Line 29-30/W.
 Daviestech will punchlist the remaining area of hand over by ARDI.

2.6.2 Other Updates / Issues


 Concerns: Hand over Area by ARDI
 Concerns: Additional Area of application.
 Concerns: Additional Area of hand over for application of waterproofing.
 Concerns: Additional Area of hand over for application of waterproofing.
2.7 Minutes of Meetings (Not Applicable)
2.7.1 PTG
2.7.2 Construction
2.7.3 Special Meeting