You are on page 1of 2

Municipality of Laur

Province of Nueva Ecija


Region III

SCHEDULE OF INFRASTRUCTURE ASSETS


For the year 2018

Year Account Name Particulars Location Amount Remarks

Cost of submersible motor pump and


2018 Water Supply System installation Poblacion 298,771.85
Electricfication of potable water system Level
2018 Water Supply System III-New San Josep 252,473.79
2018 Water Supply System Water system-New San Vicente 3,607,282.02
2018 Water Supply System Pipelaying LWS-New San Vicente 872,249.55
2018 Water Supply System Water system-New San Josep 1,211,500.00
2018 Sewer Systems Drainage Canal General Tinio Brgy. I 4,339,835.98
2018 Sewer Systems Drainage Canal Barangay III 411,072.90
2018 Road Networks Concreting of brgy roads Brgy. Canantong 1,278,664.05
2018 Road Networks Concreting of brgy roads Brgy. Betania 1,111,264.77
2017 Sewer Systems Drainage Canal Brgy. San Fernando 196,446.00
2017 Sewer Systems Construction of drainage canal Poblacion 1,074,281.48
2017 Sewer Systems Construction of Canal drainage General Tinio Brgy. I and II 1,471,706.88
2017 Sewer Systems Construction of Canal Brgy. Pinagbayanan 198,839.00
2017 Sewer Systems Construction of drainage canal Brgy. I,II,III and IV 4,426,860.23
Bonifacio St./Rizal St. Brgy
2017 Road Networks Concreting of road II and IV 1,395,040.85
2017 Road Networks Concreting of Road Brgy Brgy. I 1,462,171.58
2017 Road Networks Concreting of Brgy road Brgy. San Juan 186,895.00
2017 Road Networks Concreting of Brgy Road Brgy. San Joseph 186,828.00
2017 Road Networks Concreting of Brgy Road Brgy. Sagana 6,280,922.20
2017 Road Networks Concreting of Brgy Road Brgy. San Joseph 7,630,268.38
2017 Water Supply System Submersible pump and motor Poblacion 335,000.00
2016 Road Networks Concreting of Brgy Roads Brgy I, Poblacion 2,043,394.05
2016 Flood Control System Slope Protection Brgy IV, Poblacion 2,989,295.68
2016 Water Supply System Energization of Laur Water System-New Brgy. San Vicente 211,806.26
2016 Water Supply System Submersible motor of Laur Water System Brgy II, Poblacion 335,000.00
2016 Power Supply System Cost of Transformer -PNP Building Brgy. Canantong 208,749.82
2016 Power Supply System Electrification-BFP Brgy. Canantong 33,825.43
2016 Flood Control System Additional Cost of slope protection Brgy IV, Poblacion 298,929.57 2015 DRRMF
2016 Flood Control System Concrete slope protection dike Brgy IV, Poblacion 1,211,715.56 2015 DRRMF
2016 Flood Control System Concrete slope protection dike Brgy. San Juan 2,326,108.21 2014 DRRMF
2016 Flood Control System Concrete slope protection dike with gabion wire Brgy IV, Poblacion 1,199,214.50 2014 DRRMF
2015 Road Networks Asphalt Overlay Bonifacio St./Rizal St. Brgy I 2,941,469.24
2015 Road Networks Asphalt Overlay Burgos St., Brgy III and Brgy 2,991,998.18
2015 Water Supply System Submersible pump and motor Brgy II, Poblacion 300,000.00 Infra previously
transferred to
2015 Water Supply System Submersible pump and motor Brgy II, Poblacion 300,000.00 Registry
2015 Water Supply System Cost of motor control (ABB) Brgy. San Vicente 308,500.00
2014 Road Networks Concreting of Brgy Roads Brgy I, Poblacion 455,689.00
2014 Power Supply System Electrification-LWS Brgy. San Vicente 334,844.13
2010 Power Supply System Electrification-Municipal Hall Brgy II, Poblacion 1,042,335.30

Total 57,761,249.44
-
Prepared by:

RONALYN G. BAYRO
Municipal Acountant