Professional Documents
Culture Documents
0 CONTENTS
2. General requirements............................................................ 5
4. Handling................................................................................ 12
5. Cutting .................................................................................. 16
6. Welding ................................................................................. 22
8. Backfill .................................................................................. 33
1. INTRODUCTION
2
KPS System Manual – Version 6.0 1. INTRODUCTION
Polyethylene Pipe
Polyethylene has excellent life expectancy – far above any other polymer
used for underground pipework. KPS demonstrates this by offering a 30-
year guarantee on all items manufactured by KPS and a 15 year
guarantee on complete systems. Polyethylene pipes are easy to install
and are more resistant to puncture from sharp objects than any other
polymer pipes. The KPS Petrol Pipe System™ is designed from 10 bar
primary line classed pipe which means that the pipe is subjected to a
momentary pressure test at 30 bar before being put into service.
To achieve even greater safety the multi-layer lined pipe may be placed
inside an additional high strength pipe to protect the primary pipe from
damage thus preventing possible leaks. This is known as a coaxial pipe
or ‘a pipe in a pipe’.
3
KPS System Manual – Version 6.0 1. INTRODUCTION
IMPORTANT NOTICE
The KPS Petrol Pipe System™ has been developed to offer users a cost
effective system which will provide reliable performance over many
years. Careful attention has been paid to minimising the environmental
impact during manufacture and during operation.
To ensure that these high standards are maintained and to protect the
environment it is essential that all handling, storage and installation work
be performed strictly in accordance with the requirements specified in
this manual. It is a condition of all guarantees that the installation be
undertaken by a KPS certified installer.
4
KPS System Manual – Version 6.0 2. GENERAL REQUIREMENTS
2. GENERAL REQUIREMENTS
Application ...................................................................................................... 5
Registration ..................................................................................................... 8
Backfill............................................................................................................. 8
Application
All installations are to be in accordance with the arrangements shown in
the typical examples – see section 10, Installation Examples.
Arrangement of pipes
Pipes must be installed on a bed of at least 150 mm of pea gravel
(0-22 mm). Stones or sharp objects must not come into contact with the
pipe.
300 m m
150 m m Pea gravel φ 0-22mm
200 m m 100 m m
5
KPS System Manual – Version 6.0 2. GENERAL REQUIREMENTS
Pipes and fittings may only be cut within the limits given in Section 5,
Cutting.
Cutting
All pipes and fittings should be cut using KPS approved cutting tools.
Contact the KPS office for product details. For other requirements see
Section 5, Cutting.
Welding
All welding should be undertaken using a KPS approved welding
machine and welding fixtures. For other requirements see Section 6,
Welding.
6
KPS System Manual – Version 6.0 2. GENERAL REQUIREMENTS
The use of KPS flexible hoses under the dispenser is recommended and
steel pipe risers shall not be used. Rigid risers in a flexible system may
damage the shear valve.
For proper design of pressure systems always consult KPS for specific
advice.
KP 110EC 80 kohm/m
KP 90EC 100 kohm/m
KP 63EC 140 kohm/m
KP 54EC 170 kohm/m
Certification
After completing the above tests a final inspection is made prior to
backfilling. The KPS certified installer should make a formal inspection
and complete the KPS Installation Checklist – see page 8.
7
KPS System Manual – Version 6.0 2. GENERAL REQUIREMENTS
Registration
The KPS Installation Checklist is the basis of the guarantee. The
customer shall retain these for a period of 30 years from the date of
installation and shall make them available at all times on reasonable
notice for inspection by authorised agents of Kungsörs Plast AB who
shall be entitled to a copy of thereof on request.
Backfill
Backfilling may be undertaken only after satisfactory completion of
pressure testing and after approval by the KPS certified installer. Backfill
is to be performed in accordance with Section 8, Backfill.
IMPORTANT NOTICE
Improper backfill may damage the pipe!
8
KPS System Manual – Version 6.0 2. GENERAL REQUIREMENTS
All KPS products were checked upon arrival at the site and free from freight and handling
damages.
All KPS products were handled with care during unloading and installation.
All pipe trenches were excavated to provide a minimum of 10-cm free space on either side of
every pipe.
All pipes have been installed on a smooth, more than 10-cm, thick, bed of pea gravel (0-22mm).
All KPS pipes were cut squarely with KPS recommended pipe cutters, not a hacksaw.
All pipes were installed in accordance with the KPS installation manual in order to allow for
expansion and contraction.
All pipe-ends were dry and thoroughly cleaned with emery cloth and acetone before welding.
All welding sockets have been signed and welded in accordance with the KPS installation
manual.
Pressure Test has been performed in accordance with the KPS Installation manual and no leaks
were detected.
All parts in the pipe work system are KPS products or products distributed by KPS and were
installed in accordance with the KPS installation manual.
All refilling material consists of fine gravel (less than 22 mm) and the refilling has been
performed according to KPS installation manual.
Installing Contractor acknowledges that the warranty will be void unless a Certified Installer, i.e.
trained by a KPS approved instructor, has carried out the installation.
Conductivity test on all pipes is performed according to the KPS manual (applies only when KPS
conductive pipes are used).
____________________________________ ___________________________________
Certified Installer (signature and company name) Installing Contractor (signature and
company name)
3. PRODUCT DESCRIPTIONS
Tools............................................................................................................... 11
In general pipes are joined together and fittings are joined to pipes by
electrofusion welding. Fittings are supplied with moulded-in heating
elements. Mechanical joints and fittings and fittings for polymer to metal
transition are included in the range.
KPS also supplies the cutting and welding equipment required to ensure
that installation work can be carried out correctly and efficiently.
10
KPS System Manual – Version 6.0 3. PRODUCT DESCRIPTIONS
This pipe is used to contain the flow of liquid fuels and to prevent the
accumulation of static electricity thereby avoiding the risk of sparking.
The range of sizes and the relevant fittings are listed on the following
pages under Product specification references.
Tools
KPS supplies special tools for cutting and welding all of the above pipe
systems. The tools are listed with further details in the KPS Product
Reference Manual issued electronically and available upon request.
11
KPS System Manual – Version 6.0 4. HANDLING
4. HANDLING
Introduction .................................................................................................. 12
Transportation .............................................................................................. 12
Loading/Unloading ....................................................................................... 13
Introduction
All components in the KPS Petrol Pipe System™ are of the highest
quality, resilient and are easy to handle. However care must always be
taken to avoid damage to the pipe surfaces during transport, handling and
storage.
Transportation
• Pipes and ancillary fittings for the KPS Systems are delivered in
protective packaging to avoid any damage during transportation.
Deliveries should be made on a flat bed vehicle, free from any sharp
objects.
• When loading pipes/racks and coils onto the truck, make sure
that the racks and coils are stacked in a proper way.
12
KPS System Manual – Version 6.0 4. HANDLING
Loading/Unloading
• A rack or coil is best lifted with a fork truck. Where forklifts are
used to off load coils, the forks should be protected to avoid damage
to the coil outer surfaces.
• When lifting pipe bundles by crane, wide slings must be used.
Do not use chains or hooks.
• Racks and bundles may be handled using a forklift and coils
manhandled by a minimum of two people.
• When pipes/racks and coils are loaded/unloaded with a forklift-
truck or cranes, make sure to pick up the load at their centre-points.
• Make sure that the load doesn’t scrape along the edge of the
truck bed or against any other sharp object.
• Pipe/Coils should be set down gently and horizontally onto the
ground.
• Make sure to take any necessary step to prevent pipe damage
during loading/unloading.
Releasing Coils
IMPORTANT NOTICE
Releasing coils is hazardous. When pipes are coiled energy is stored in
the coil and incorrect release can cause injury. To avoid this, use two
people to secure the pipe end and coil. Remove the restraining bands
carefully and with a rope slipknot.
13
KPS System Manual – Version 6.0 4. HANDLING
• Never store KPS Pipes without end caps and in direct exposure
to sunlight.
IMPORTANT NOTICE
Exposure to UV rays from the sun may damage the lining.
Trucks or heavy plant equipment running over pipes can cause internal
damage. Deep scratches, more than 10% of the wall thickness, or marks
on the outside will weaken the pipe and are grounds for invalidating the
guarantee.
Small ancillary fittings and sockets are delivered in plastic bags, within
boxes. Upon arrival at site, all boxes and materials should be checked for
signs of damage. All fittings and sockets should be kept in the plastic
bags until ready for use. The plastic bag protects the fittings and sockets
from contamination and oxidation.
Coiled pipe should be unrolled and straightened the day before use for
relaxation and easier handling.
14
KPS System Manual – Version 6.0 4. HANDLING
ALWAYS
NEVER
15
KPS System Manual – Version 6.0 5. CUTTING
5. CUTTING
Introduction .................................................................................................. 16
Introduction
To ensure that the KPS Petrol Pipe System™ can be assembled correctly
it is important that the cutting of the pipes and fittings are to the required
length and that preparation is carried out in accordance with KPS
procedures. To ensure a high quality joint, it is important that the pipes
are cut square. Only then can the cut end be properly joined to other
parts in the KPS Petrol Pipe System™.
Cutting is best achieved by the use of a KPS pipe cutters. These tools
give a clean and square cut without burrs.
IMPORTANT NOTICE
Do not cut the pipe with a saw-edged blade.
The following cutting instructions explain the type of cutting tools that
can be used, how to use them, restrictions and important measurements
when cutting KPS components.
It is important to note that formed products in the KPS System must not
be cut too close to the curved section, as this will prevent them from
fitting correctly into the welding fitting.
16
KPS System Manual – Version 6.0 5. CUTTING
Cutting tools
Cutting Scissors
The KPS cutting scissors can cut KP pipes up to 63 mm diameter. They
are fast and reliable and ensure a clean and square cut.
(Spare blades are available from your KPS Petrol Pipe System™
distributor.)
Scissors:
When cutting, position the scissors with one blade on top of the pipe and
move them forward until they make contact with the pipe. Check that the
handles are square to the pipe and that the blades line up square. Then
proceed with the cutting.
17
KPS System Manual – Version 6.0 5. CUTTING
45º bends, KP 4
These bends must not be shortened.
B min
18
KPS System Manual – Version 6.0 5. CUTTING
The black inner pipe shall be longer than the green outer pipe in
accordance with the illustrations to the right. 65mm
KP 75/63 SC
40mm
Minimum length:
75/63SC L=130 mm
IMPORTANT NOTICE
Joining two primary pipes using a KP T75/63SC is not allowed!
19
KPS System Manual – Version 6.0 5. CUTTING
Cutting Secondary Containment pipes for use with KP T125/110SC-L transition fitting
When the KP T125/110SC-L integrated transition fitting is used it is
possible to make a joint inside the fitting. See drawing below.
20
KPS System Manual – Version 6.0 5. CUTTING
On either side of the bent section, the length from the elongation of one
straight leg to the cut on the other straight leg must be of minimum
dimensions shown below:
B-min
21
KPS System Manual – Version 6.0 6. WELDING
6. WELDING
Introduction...................................................................................................22
The Process....................................................................................................23
Introduction
This is a general instruction for welding KPS pipe designs and welding
fittings. Due to the hazardous area where the welding procedure takes
place, please note:
WARNING
Do not weld where there is risk of flammable liquids or vapours. Always
ensure that petrol or petrol vapours have been completely removed
before welding.
IMPORTANT NOTICE
Do not use sandpaper as a substitute for emery cloth.
KPS System Manual – Version 6.0 6. WELDING
The welding fitting should be removed from its packing and checked that
it is clean. It should not be touched, abraded or come into contact with
contaminated material such as silicones, lanoline from human skin or
other greasy substances. Use a cloth moistened with acetone to wipe
clean the prepared pipe, fitting and the bore of the welding fitting.
The Process
Polyethylene pipes and fittings in the KPS system are joined by
electrofusion welding. The method is suitable for use on an installation
site, because it is not sensitive to weather conditions. However, all joints
must be kept dry and clean during the welding process.
The ambient temperature when welding can be between -15ºC and +45ºC
(-5ºF and +110ºF). The lower temperatures are applicable only under
calm, protected conditions.
The power, energy and welding times are automatically calculated and
applied when KPS welding machines are used. Other welding machines
must not be used.
23
KPS System Manual – Version 6.0 6. WELDING
Arrange the pipes so that they are approximately in line and push them
until they meet. Place the welding fitting alongside where the two pipes
meet. Mark each pipe where the fitting ends and renew the mark if it
fades or is erased during the subsequent stages.
Thoroughly clean the outer surface of each pipe by roughing from the
mark back to the pipe end. Use emery cloth, about 120-180 grit. Do not
use sandpaper.
IMPORTANT NOTICE
Make sure the surfaces are kept clean and dry. Protect with plastic
sheeting whenever necessary.
24
KPS System Manual – Version 6.0 6. WELDING
Clean the outside of the pipe and the inside of the fitting with a clean
cloth moistened with acetone.
Connect the fitting onto the pipe and push it firmly to the bottom of the
socket.
IMPORTANT NOTICE
Always ensure that the pipe/pipes are pushed to the bottom of the fitting.
Push the pipe ends into the bottom of the welding socket. Mark on both
pipes the outer ends of the fitting. After welding both of these marks
must still be close to the socket ends.
Clamp both pipes into the welding fixture, so that they cannot move
during the welding process.
Connect the welding machine to the welding fitting with the appropriate
welding cable.
25
KPS System Manual – Version 6.0 6. WELDING
IMPORTANT NOTICE
Only cables supplied by KPS can be used with KPS welding machines.
Ensure that the dimensions of the cable connector and the pin size of the
welding socket conform.
After welding, remove the cables with care to avoid damage on the
connectors.
Start the welding process and follow the procedures for the welding
machines as appropriate.
When the welding has been completed, check that the welding machine
indicates a correct weld.
Sign or mark the fitting to indicate that it has been welded and checked.
Wait at least 20 minutes or until the socket has cooled off to body
temperature before removing the clamping fixture. Normally after 2
hours the weld has reached its full strength.
Testing of the welded joints should take place after the whole installation
has been completed.
26
KPS System Manual – Version 6.0 6. WELDING
With the KPT integrated transition fitting the inner and outer pipes are
fixed relative to each other.
After cutting back the outer pipe to fit the entry boot, roughen the fusion
area surfaces on both the inner and outer pipes with emery cloth (the
entire area must be abraded) over the following lengths:
Cleaning length:
125/110SC outer pipe 60 mm
inner pipe 70 mm
Clean the roughened area and the inside of the fitting using a clean cloth
moistened with acetone.
Weld the KP T- SC fitting to the pipes. (Note that the illustration to the
right shows the installation of a KP T75/63SC.)
27
KPS System Manual – Version 6.0 6. WELDING
When the welding has been completed, check that the welding machine
indicates a correct weld.
Sign or mark the fitting to indicate that it has been welded and checked.
Pay careful attention not to apply any force to the fitting or pipe during
the welding process. After 2 hours the weld has reached its full strength.
Testing of the welded joints should take place after the whole installation
has been completed.
IMPORTANT NOTICE
Under hot conditions, there may be a need to adjust to longer cooling
times before removing the fixture in order to obtain a proper weld.
28
KPS System Manual – Version 6.0 6. WELDING
Cutting lengths:
125/110SC 65 mm
75/63SC 40 mm
Connect the welding fitting onto the fixed pipe and ensure that the outer
pipe is pushed to the bottom of the fitting. Because the inner and outer
pipes are now integrated, the inner pipe will also be pushed to the bottom
of the fitting.
29
KPS System Manual – Version 6.0 6. WELDING
Fit the opposite pipe into the fitting. Start with the inner pipe and push it
fully into the bottom of the socket so that the marking matches the edge
of the fitting (illustration).
Continue with the outer pipe and push it fully into the bottom of the
socket so that the marking matches the edge of the fitting
(see illustration).
IMPORTANT NOTICE
When certain that the pipes are fully inserted, clamp the pipes into the
clamping fixture to ensure that the pipes will not move out of the
welding fitting. Attach the welding cables and weld in accordance with
the instructions in ‘Welding’ above.
30
KPS System Manual – Version 6.0 7. PRESSURE TESTING
7. PRESSURE TESTING
Introduction .................................................................................................. 31
Introduction
Pressure testing of the system is vital to ensure the system performance.
The purpose of the pressure test is twofold: To test the strength of the
piping system and to detect potential leakage.
WARNING
When using air to pressure test the system make sure to take all
necessary actions to avoid air blowouts. All personnel must keep a
secure distance from the system when pressure is applied. High-pressure
air contained in a pipe creates a substantial force that could cause an air
blow-out in case of failure.
31
KPS System Manual – Version 6.0 7. PRESSURE TESTING
IMPORTANT NOTICE
The pressure may vary slightly during a leakage test. This may be due to
some movement of the piping system. The pressure may vary by up to 4
kPa (0.04 bar, 0.6 psi) during a leakage test without indicating leaks.
32
KPS System Manual – Version 6.0 8. BACKFILL
8. BACKFILL
Backfill........................................................................................................... 33
Backfill
Backfilling may be undertaken only after satisfactory completion of
pressure testing and after approval by the KPS certified installer.
Proper backfill supports the pipe system and protects it from mechanical
damage and handles the effects of heavy traffic or other loading imposed
on the pipe system.
The depth of the top depends on the top paving. With pavement of
reinforced concrete it is possible to reduce the top layer to 150 mm but
with other pavement such as asphalt, the top layer must be at least 300
mm.
The space within 150 mm of the pipe shall be filled with pea gravel 0-22
mm. Do not compact material immediately on top of the pipe,
compacting should be done in 150-200 mm layers on both sides.
On top of the gravel, it is usually possible to fill with the previously dug
up material, but with heavy stones removed. See drawings below.
IMPORTANT NOTICE
Improper backfill may damage the pipe!
300 mm
150 mm Pea gravel φ0-22mm 100 mm Pea gravel φ0-22mm 150 mm
200 mm 100 mm
33
KPS System Manual – Version 6.0 9. PIPE WELDING MACHINE
General information
KPS welding sockets are welded using a constant current. The energy
input is controlled by the voltage applied to the socket and the welding
time. Before welding is started, the resistance in the socket wire is
measured and, using the measured value, the welding machine
automatically calculates and applies the required energy for proper
welding.
The machine also takes into account the ambient temperature and
automatically adjusts the amount of energy required. Therefore the
machine should always be placed close to the welding socket to attain
the same temperature. If the machine is moved from one place to another
with a large difference in temperature, the machine should be given at
least 30 minutes to adjust to the correct working conditions. The
temperature sensor is attached to the rear (bottom left) of the machine, in
contact with the steel frame.
For further information and details regarding the KPS welding machines
refer to the product manuals delivered with the product.
34
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
Introduction .................................................................................................. 35
General Layouts............................................................................................ 52
Introduction
KPS has considerable experience in the application of its pipes and
fittings. The drawings included in this section show the KPS
recommended solution for all applications at filling stations.
35
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
1 2 3 4
36
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
1: KP7 (Gasket)
2: KP5 (Stub flange)
3: KP6 (Steel flange)
4: KP2 (Welding socket)
5: KPM (Entry boot)
6: KP-E (Lined Pipe)
1 2 3 4 5 6
37
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
1 2 3 4 5
38
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
1: KP7 (Gasket)
2: KP5 (Stub flange)
3: KP6 (Steel flange)
4: KP2 (Welding socket)
5: KPT-SC (Transition fitting)
6: KPM (Entry boot)
7: KP-SC (Secondary contained Pipe)
1 2 3 4 5 6 7
39
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
5 4 3 2 1
40
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
Delivery Systems
KPS-INST-11 Alt 1: At the tank top. Connection to a
Secondary Contained polyethylene pipe, from the tanks threaded steel
delivery pipe. Then exiting the tank chamber liner. Components type:
1 2 3 4 5
41
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
1 2 3 4 5
42
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
1 2 3 4
43
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
1 2 3 4
44
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
1: KP7 (Gasket)
2: KP5 (Stub flange)
3: KP6 (Steel flange)
4: KP2 (Welding socket)
5: KPM (Entry boot)
6: KP-E (Single Wall Lined Pipe)
1 2 3 4 5 6
45
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
1: KP7 (Gasket)
2: KP5 (Stub flange)
3: KP6 (Steel flange)
4: KP2 (Welding socket)
5: KPT-SC (Transition fitting)
6: KPM (Entry boot)
7: KP-SC (Secondary Contained Pipe)
1 2 3 4 5 6 7
46
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
47
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
5 4 3 2 1
48
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
49
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
1 2 3 4 5 6
50
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
1 2 3 4
51
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
General Layouts
KP-INST-30
Example of layout for a suction system (split lines) with 4 tanks, 4 fuel
types, 4 dispensers, venting system with stacks and both stage 1b and
stage 2 vapour recovery system.
52
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
KP-INST-35
Example layout for a pressure system with 4 tanks, 4 fuel types, 4
dispensers, venting system with stacks and both stage 1 and stage 2
vapour recovery system.
53
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
KP-INST-37
Secondary Contained off-set fill line, from the sump at the road tanker
delivery point, to the fuel tank top chamber liner. 90º and 45º bends used
to permit expansion and contraction.
54
KPS System Manual – Version 6.0 10. INSTALLATION EXAMPLES
KP-INST-38
Secondary Contained off-set fill line, from the sump at the road tanker
delivery point, to the fuel tank top chamber liner. 90º bends used to
permit expansion and contraction.
55