Enter the text below for checking the available project no. Here for e.g we are using” bd” for bagasse
dryer. For other projects use relevant nomenclature. Our Format is det-(two alphabets)-(five
numerical)
Available Project
No.
Hit Enter button and then select this from dropdown menu and Hit Enter. (For Capex select DETS
Capex project profile and for customer projects select dets customer project profile.
Insert the Plant Code: Here we are putting 2001 for Ghaziabad. For Pune its 2002
Enter the Profit Centre. Here we are putting 20010 for Ghaziabad .For Pune its 20020. Hit Save and
project definition will be created
Profit centre
can be
searched here
Opening the Project:
1. Right Click on the project name and select create a WBS Element.
Put the Description of the network and put the MRP Controller as 999
Creating Internal Network
1. Right click on the activity and select create and click on Activity (internal)
Enter the description of the activity also enter the duration for the purpose of the
scheduling
Similarly Make all the internal Activities (refer screenshot)
Right Click on the WBS Element where you want to copy a network, go to create and then copy
network
Enter the id of the source network from when you want to copy and press enter.
1. Click on any activity header and then click on the button network graphics which appears on
tool bar.
Now click on the connect button to create the relation among the activities.
Cost Planning
The Cost Planning is created by code: cj40 and we use cj41 to display the Cost Planning
WBS Element description is by WBS Element No. It will be easier if the description is by text so click
on settings and select display option. Following Screen will Pop Up.
Click on this
and press
enter
.
We can use M for the materials which is present in the materials master. Just select the material
code, if the cost of the materials is present, the system will automatically take up the value of the
materials. Otherwise we have use V (variable) and insert the details manually as show below:
Insert Qty
Insert unit
price
Insert material
description
Click This or
press Enter
Similarly Insert all the materials and then Press Save icon to save and return to the previous screen.
Click on Check Icon to check for any errors and then press Save Icon. The Cost Planning will be
completed.
Budget Planning:
Important Codes:
Select the line item whose budeting is to be done or All the line items can be selected by clicking on
this icon
Then Click on Edit tab as shown on the below screen shot and click on the copy view
Budgeting is completed.
Releasing the Project:
Complete Project or any of its WBS can be released, once its budgeting is done.
Goto Edit tab, select Satus and click on Release. The Project will be released.
Activity Confirmation:
To Confim any activity, open the bar chart
Select the activity which you want to confirm and then click on the confirm icon
Step 2: Click
on the
confirm icon
Following tab will be opened, enter the details like, actual start, actual finish and actual n of days etc.
hit the back button.
2. Step – 2 Click on the edit button, Click on status – Select Close and then select Set.
Please note that to close the project, all the activites to be confirmed, there should be no stock,
commitment (open PR/PO) in the project and all the sales is to be completed. Only then a project
can be closed.
Canceling confirmation – cn29
and then put the reason for cancellation and press back button
REPORTS
For creating reports, go to the SAP Menu and then click on Information systems tab and the Click on
the Porject Systems tab. From there you can make the desired reports . (Refer below screen shot)