Problem Statement:: Construction Quality & Safety Management Term Project
Problem Statement:: Construction Quality & Safety Management Term Project
TERM PROJECT
1. Problem statement:
Identify a construction operation for which you will develop a quality plan using the Life Cycle
of Acceptance Control Application framework given in the class. You need to develop a case
study to demonstrate each of the steps. The data may be generated but must be relevant to and
reflect the application under consideration.
2. Group details: Group - 3
1 KARUNAKARRAO D CE12M178
2 KALIMUTHU S CE12M185
3. Construction Activity:
The site chosen is “2×600 MW Shree Singaji Thermal Power Plant, Khandwa, Madhya
Pradesh”. Scope of work includes erection and commissioning of Coal Handling Plant.
The activity considered is ring diameter inspection for assembling in Ring Granulator (a
crusher)
4. Deliverables:
Detailed Report on inspection
Mean Chart
Range Chart
Control Chart
Statistical control check
OC curves