Professional Documents
Culture Documents
MPD was used in the entire reservoir section from the casing underbalanced kick situation. Likewise, the surface separation
shoe to total depth (TD). Wells with uncertainty in reservoir equipment was well suited for managing kicks safely during
pressure were drilled at an equivalent circulating density the return to a low overbalanced condition.
(ECD) of 8.34 ppg until fractures were encountered, and A recyclable high-quality foam system with continuous
significant fluid losses were induced. Reservoir pressure and foaming and defoaming chemical injection was used with
required ECD were determined from a static fluid-level wells that required an ECD of less than 4.5 ppg. The foam
measurement. The fluid system and parameters for MPD were system contained all the components of the two-phase fluid
selected and applied from this point forward to TD. system but with the addition of a continuously injected
Successful results had been achieved by the operator’s use foaming agent and a defoaming agent. Fig. 5 shows the
of MPD techniques on offset wells. However, the fact that rheology changes with foam quality.
some of the current reservoir pressures were now much lower The two systems were readily interchangeable because the
compared to when the offset wells were drilled caused same polymers (at different concentrations) were used to mix
considerable concern. This prompted a thorough review to be the base fluid, and the foaming and defoaming chemical
conducted on the reservoir pressure trends along with the injection could be controlled easily.
MPD techniques used on offset wells. Both MPD fluid systems were adjusted to an ECD control
Offset drilling data from these fields indicated a downward point with careful selection of pump rates, nitrogen rates, fluid
trend in the ECDs used to drill the production zone. MPD properties, and chemical injection control. Monitoring of the
techniques with foam-surfactant-stabilized two-phase fluids level of overbalance or underbalance was performed by
had been very effective for drilling these wells; however, as precise measurement of the net losses or gains of drilling fluid
the reservoir pressure had declined over time, 2-phase fluid and nitrogen. Real-time comparison of the injected rates vs.
systems with a quality range of 10 to 50% (ECDs greater than the returned rates were used to make fine adjustments to the
approximately 4 ppg) would no longer be effective in the more ECD using annular wellhead pressure to provide the exact
depleted and highly fractured areas of the fields. level of overbalance required.
Downhole equipment specific to the MPD section of the pushing the known limits of foam-drilling fluid technology.
well included wireline-retrievable non-return valves (NRVs) Foam-system products that were believed to retain the
in the drillstring and dual-flapper NRVs in the bottomhole required properties at the depths and temperatures that would
assembly. Additionally, a bottomhole annular pressure be found in the field (bottomhole circulating temperature up to
recorder was used to verify the accuracy of calculations made 275°F) were selected. Deeper depths also increased the round-
with flow-modeling software. Corrosion rings were installed trip time that the foam fluid system needs to retain its stability
in the BHA and the top of the drillstring to monitor and and hole-cleaning properties.
confirm effectiveness of the corrosion control program. Real- Preliminary testing at a fluids lab with the foam system
time bottomhole annular pressure readings from MWD would products was performed at atmospheric pressure and
have been useful but were not an option. Mud-pulse telemetry temperatures up to 190°F. These tests were performed to
systems would not function with the high gas fractions present initiate the product selection process, and later, were followed
in the drillstring, and electromagnetic MWD (EM-MWD) up with testing at downhole conditions in a more elaborate test
telemetry equipment was not readily available for the project. apparatus. Various combinations and concentrations of
Monitoring and safety equipment for H2S and polymers, foaming agents, and defoaming agents were tested
hydrocarbons were installed at various locations at the wellsite to advance the selection. The following test criteria were
to allow for the appropriate measures to be taken if either was tested:
detected at surface.
Drilling parameters specific to the MPD operation were Half-life (time that foam maintains its volume at surface
measured, recorded, and displayed at critical wellsite locations conditions) was an important test and design parameter both
by a dedicated data-acquisition system. (Fig. 8 shows the for the preliminary lab testing and in final wellsite
screen capture of the DAS data display). Additionally, all optimization. In drilling conditions the foam is required to
wellsite rig and MPD specific data were transmitted real-time maintain its characteristic structure and properties for the
to an operations control center. This provided experts in the round trip time to circulate and not be excessively stable so
control center with the capability to provide support to several that it could still be chemically broken.
different wellsite MPD operations being run simultaneously.
Yield (an experimental measure of the total volume of foam)
Foam Fluid System that is generated from a fixed volume of liquid and surfactant.
a) High-temperature recyclable foamed drilling fluid This is a numerical indication of the efficiency of the polymer
In several locations throughout the world, “once-through” and surfactant combination.
foam systems are used to drill, and then, are discarded when
they are produced to surface. In this project, this would not Base Fluid Rheology is an important characteristic that has a
have been a viable option since national environmental significant effect on the foam rheology that is generated and
regulations prohibit the use of open reserve pits. Additionally, on the halflife/stability that the foam will have. Rheology of
fluid disposal costs are high and a “once-through” foam fluid the base fluid generated with the various viscosifying
system would not be logistically or economically feasible. polymers was carefully controlled and recorded.
The foam fluid system used in this project needed to be
contained in a closed system comprised of the separator, Foaming and defoaming cycling was simulated to confirm
closed storage tanks and rig mud tanks. Additionally, the which combination of products and concentrations would
foam was required to be recycled through as many foaming maximize the number of foaming/defoaming cycles of the
and defoaming cycles as possible. polymer base fluid.
There are two main types of recyclable foam systems: pH Once preliminary testing identified the most promising
controlled and chemically controlled (surfactant/alcohol). The candidates for a recyclable foam system at surface conditions,
industry trend is moving towards the chemically controlled the system was further tested at a research facility at simulated
surfactant/alcohol system, and this was the type the project downhole temperatures, pressures, pump rates and
used. contaminants in a high pressure, high-temperature
The recyclable foam is generated by adding foaming agent recirculating foam-flow loop apparatus.
to a polymer base fluid with nitrogen and shearing it to Foam rheology is greatly increased compared to the
generate foam. The foam mixture is then circulated down hole rheology of the components that make it up. Models that
as drilling fluid. Upon the foam’s return to surface carrying consider the properties of the base fluid, the downhole foam
drill cuttings, a defoaming chemical is injected in order to quality or gas fraction, and calculate a foam rheology at
break the foam. This “defoamed” mixture passes into a downhole conditions have been developed.
pressurized separator where the nitrogen, fluid, and cuttings The accuracy of this foam rheology calculation at down
are separated. The fluid and cuttings streams are transferred to hole conditions was a critical factor to validate. This was
the rigs solids control system to remove the drill solids, and imperative for ensuring
then, the recycled fluid is ready to be foamed again. The • Good hole cleaning characteristics
nitrogen is vented to a flare pit. • Precise bottom hole pressure control.
The polymer liquid or base fluid, the foaming agent, and Figs. 5 and 9 illustrate foam rheology calculations.
the defoaming agent were all carefully selected to ensure they Once laboratory testing was completed, the foam system
would be compatible. MPD was applied from depths of 9,656 was commissioned and optimized in the first four wells. The
to 19,834 ft TVD. These depths and temperatures were
4 SPE 104030
foam performed well, and only minor changes were made to hole cleaning without causing washouts in the open hole,
the chemical concentrations in the field. minimized RCD element consumables, and minimized
The original foam system design was for an ECD range of cryogenic nitrogen.
2.0 ppg to 5.5 ppg. The foam was actually used on wells with
an ECD range of 2.9 ppg to 5.0 ppg. This system was used c) Foam bullheading to initialize circulation
from the shallowest payzone casing shoe depth of 9225 ft Wells in the project that were drilled at the lowest range of
TVD and up to the deepest well in the project up to 19,334 ft ECD had problems initializing circulation after a trip or a rig
TVD. In the laboratory, the maximum stable circulating service. Numerous techniques were used in order to establish
temperature was tested to 285°F, which exceeded the highest circulation including staging in (establishing circulation from
bottomhole circulating temperature to be encountered in the above the casing point and circulation down), slugs of
field (275°F). nitrogen, jet subs and the novel technique of foam
bullheading. After some field optimization, the foam
b) Hybrid foam/2-phase fluid systems with tapered tubular bullheading technique was found to be the most effective
geometries technique.
Some of the deeper wells in the project required ECDs that The problem occurs when establishing circulation from a
were normally in the range of 2-phase fluid systems, but they condition where the annulus has reached a static fluid level
used a casing program and drillstring configuration that with open fractures that are highly permeable. When
benefited from the use of foam. On the wells where a liner circulation is initiated the light foam fluid in the drillstring is
was used along with a tapered drillstring (Refer to Figure 4), displacing the higher density fluid in the annulus creating an
an area of low annular velocity is created between the 3.5-in. overbalanced condition. Fluid is lost to the fractures as soon
drillpipe and the 9-5/8-in. casing. For good hole cleaning, a 2- as the overbalance condition is created. Depending on the
phase system relies on fluid velocity greater than the velocity drillstring position, the lighter fluid being pumped down the
required by foam (approximately 2:1). drillstring can be completely lost to the open fractures. With
On two of the wells in the project, Jujo 543 and Jujo 506, sufficient time some of the lighter foam may eventually
an unusual situation had to be resolved. Both wells are over displace the liquid in the annulus and circulation may be
19,000 ft TVD and drilled through the payzone section with a resumed. In some of the wells normal injection of foam via
5 7/8-in. hole with 9 5/8-in. casing and a 7-in. liner (Fig 4). the drill string in excess of 6 hours failed to resume
Options that were considered to drill these wells with circulation.
ECDs of 4 ppg and 5 ppg respectively were foam and 2-phase
fluid systems. Both systems had advantages and Methods to Re-establish Circulation
disadvantages in this application. Jet subs did not have a significant effect and lost flow rate and
The 2-phase fluid system required higher rates of nitrogen hole cleaning below the jet sub.
and fluid in order to sufficiently clean the 3-1/2-in. x 9-5/8-in. Pumping batches of nitrogen can be effective, but there
annulus. At this point in the project, cryogenic nitrogen was were risks inducing hydrocarbons to surface, since some areas
still being used, and cryogenic nitrogen cost and supply was a of the field contains H2S. Tripping back above the casing shoe
negative factor for this option. The velocities required to every time a slow drill string connection was made was not a
clean the 3.5-in. x 9-5/8-in. cased-hole annulus could be a viable option either.
concern for washing out the openhole section with a more Staging in the well was found to be time consuming and
constricted annulus. not always effective, since staging in generally worked more
A foam system was also considered for drilling these effectively in wells with ECDs greater than 4.0 ppg.
sections but would have required continuous back pressure on The foam bullhead technique was developed in order to
the annulus while drilling. This system was considered but in regain circulation where other methods had failed. In this
order to reduce the rate of wear on the rotating control device method, the dedicated choke to the separator is closed, foam is
(RCD) sealing elements, a hybrid system was used that had pumped down the drillstring and the annulus simultaneously
the benefits of a lower continuous operating wellhead pressure through the kill line. This pressurizes the drillstring with a
of 2-phase along with the better hole cleaning characteristics light fluid and also pushes the fluid level down in the annulus.
of foam. Once the fluid level in the annulus is pushed down to the
At deeper depths, the hybrid fluid system uses a 2-phase formation fractures, the flow in the annulus is reversed: foam
system at deeper depths, which converts to a foam system injection to the annulus via the kill line is stopped, and the
before the low velocity section is reached. The foam surfactant choke to the separator is opened while injection to the
chemical is present at all depths, but the quality of the foam is standpipe continues. Normal circulation is established, the
in the correct range to form high-foam rheology in the range pressures are allowed to stabilize, and drilling operations are
of 0.50 to 0.85 only. As the pressure decreases when the foam resumed.
is traveling up the annulus, the nitrogen gas expands, and the Status as to what is occurring downhole is determined by a
foam quality increases. At a depth 600 ft below the top of the wellsite engineer using a combination of real-time surface data
liner hanger, the foam has reached the quality of 0.50, and the acquisition and flow model calculations. The sequence of
foam structure and rheology has developed. The hybrid events for a foam bullhead is outlined below, and a pressure
system relies on 2-phase flow and higher velocities to clean schedule is illustrated in Fig. 10.
the open hole and the higher foam rheology to clean the larger Time 1: Commence pumping foam down the drillstring
annulus in cased hole. Overall, this system provided good and annulus. Pressure rises with both standpipe pressure and
SPE 104030 5
wellhead pressure tracking each other closely. The surface guidelines were based on a minimal range of fluid loss (5
injection pressures are rising to compensate the hydrostatic bbls/hr) to avoid oil contamination of the fluid system.
pressure, which is decreasing as the liquid is being displaced Specific procedures during tripping and startup minimized
by a lighter foam mixture. and segregated any produced hydrocarbons. During events
Time 2: Injection pressure is stabilized indicating the such as initializing circulation, eliminating influx of oil was
annular condition is not changing. The fluid level has been not always possible. Therefore, the first returns of fluid were
completely displaced back to the formation fracture with diverted to a separate storage tank until oil-free returns were
foam. At this point, the annular flow is reversed. received at surface. The returns then were diverted to the rig’s
Time 3: Injection and wellhead pressure have stabilized, fluid system from the closed tanks. Any mixtures of oil and
and drilling resumes. water-based fluid in the closed tanks were separated, and the
After demonstrating that this technique was a reliable recovered water-based fluid was returned to the active fluid
method to remedy a lost-circulation situation, it was optimized system.
in order to reduce the time and fluid lost during the procedure. Careful management of the foam base fluid was required
Advances were made by reduction in the percentage of final to maintain the correct rheology and ensure the system
stable injection pressure where the annular flow is reversed, compatibility. On one well the base fluid was mixed with an
and the technique was still effective. This would depend on incorrect polymer, this resulted in problems breaking the foam
how low the reservoir pressure was and the fracture at surface and a foam system that could no longer be recycled.
permeability.
The foam bullhead has become the standard method for Training
establishing and regaining circulation where ECDs are less A training program was developed specifically for the project.
than 4.0 ppg. Initially, drilling supervisors and project personnel received
MPD-specific classroom training that covered equipment,
d) Hole cleaning challenges in geo-mechanically unstable benefits and limitations, operational and emergency
formations. procedures, hazards, and well control.
It was found that certain areas of the field were prone to hole Prior to each MPD well section, training was given to the
instability due to the extensive fracturing that occurred when wellsite crews. This included a general overview of MPD and
close to a salt dome. Cuttings analysis revealed that the equipment, roles and responsibilities, operational and
instability was not due to any water sensitivity of the emergency procedures, communication, and procedures to
formations and that the friable formation instability was ensure safety to personnel and the environment.
mechanical in nature.
Hole cleaning calculations based on near gauge-hole Hole sections with multiple pressures.
assumptions had to be revised. Two wells were drilled On two wells, it was found that zones with different reservoir
simultaneously in close proximity, Iride 1156 and 1163 at pressures were encountered in the same producing section. On
ECDs of approximately 6.0 ppg. Upon first examination, the the Cunduacan-39 and Iride-2126st wells, it was not possible
more suitable fluid system appeared to be 2-phase. However, to maintain a fluid loss of 5 bbls/hr and avoid hydrocarbon
due to unstable hole conditions, washouts with this system production to surface. A compromise was made to allow fluid
drilled with an 8.5-in. bit were up to 20-in. (See Fig. 11 log. losses up to 30 bbls/hr. This maintained an overbalanced
After experiencing stuck pipe incidents, the fluid system was condition to separate produced oil of 5 bbls /hr from the rig
changed to foam with additional back pressure, providing a tank system using a separate closed-tank system.
similar ECD. The higher rheology of foam at a lower annular
velocity and lower turbulence was believed to be capable of Conclusions
cleaning the hole efficiently with fewer wash outs. Innovative MPD techniques were built upon previous work
The fluid system was switched on Iride-1156, and the fluid done by the operator in the Bermudez Complex and Jujo-Teco
rheology was raised to the highest level at which the foam was fields. These new techniques were capable of overcoming the
still manageable and could be broken and recycled on surface. significant drilling problems associated with reservoir pressure
Additionally, prior to each drill pipe connection, a surfactant declines and the significant changes are summarized below:
sweep which provided additional hole cleaning was pumped. a) The high-temperature recyclable foam system developed
Drilling of these wells was cautiously completed, and this in the test labs was successfully applied in the field at ECDs as
revision in technique became the norm for subsequent wells low as 2.9 ppg and at depths up to 19,334 ft TVD. This system
with hole instability problems drilled in this area of the field. combined with the 2-phase system provided a seamless fluid
system combination that can be used from 2.0 ppg up to 8.34
Challenges ppg.
Contamination issues. It is critical to maintain a precise level b) The hybrid foam / 2-phase system was developed from
of overbalance when drilling an oil-bearing formation with a the high-temperature recyclable foam system and succeeded in
water-based fluid system. Underbalanced situations result in providing good hole cleaning without causing washouts in the
oil inflow and contamination of the fluid system, while too openhole sections of deep wells with complex geometry. The
much overbalance results in excessive fluid loss. Even though hybrid system minimized RCD element consumables and
the oil could be separated from the water-based fluid and was cryogenic nitrogen usage in a fixed cost environment.
designed to maximize the tolerance for oil influx, the level of c) Foam bullheading has been used to establish circulation
contamination was planned to be minimized. Fluid loss on low-pressure wells where they may have previously been
6 SPE 104030
South Mexico
State of Tabasco
Q2 2004 – Q2 2006
Bermudez 27 wells
5 rigs
Jujo 6 wells
2 rigs
COSACO
MANEA PALAPA
PTO. CEIBA PIJIJE
DOS BOCAS
ARRASTRADERO
MAYACASTE PARAISO MELOCOTON
CASTARRICAL ESCARBADO
MECOACAN CARDO CAPARROSO
TUPILCO RICINO
EL GOLPE PARAISO
SANTUARIO MENTA SEN
ESCUINTLE
CARACOLILLO COMALCALCO
MUSGO
Bermudez NACAJUCA
CHIPILIN CUNDUACAN
BELLOTA OXIACAQUE
MORA
CUNDUACAN
EDEN
CARDENAS SAMARIA
JOLOTE IRIDE
Jujo-Teco
JUJO
CARDENAS
VILLAHERMOSA
TECOMINOACAN
JUJO
PAREDON
JACINTO
CACTUS NISPERO
N-80 72 # BCN
30” @ 50 m 30” @ 50 m
K-55 94 # BCN
Polimérico Inhibido
1.14
Programa Paraje Solo 1.14
1.15
K-55, 94 #/ft, BCN
Real
K-55, 94 #/ft, BCN
WBM: Polimérico
1530 m 1530 m
N-80, 68 #/ft, BCN
1500
1000 1.38
1822 m
1500
1.37
OBM: Invermul 1.39
1304 m 1291 m
1.32 – 1.42 g/cc
P-110 72 # BCN
9 5/8” TAC-110 53.5 # HDSLX
1344 m 1.32 – 1.42 g/cc 2000
2000
Fil 1.38
1500 1.40
1666 m 1627 m
P-110 53.5 #/VFJL
Deposito
P-110 53.5 #/ft VFJL
2500
CS 2500 1.42
TC 2700 1.41
Emulsión Inversa
1876 m 1884 m
1.46
2000 CI
TR 13 3/8” 3000 13.3/8” @ 2900 m TR 13 3/8”
1.42
TR 13 3/8” 2904 m 3000 1.80 1.80
1976 m 2040 m 2210 m 1972 m 3054 m
3260 m 3260 m BL 7’r 3200 m BS 7”
3205 m 1.83
Enc 2333 m Plan
3500 Oligoceno 3500 Real 1.85
2500 2608 m 2580 m 1.87
1.85
7” TAC-140 35# HDSLX
1.88
9 7/8” TAC-140 62.8 # HDSLX
OBM: Invermul
TAC-110 53.5 #/ft VFJL
3890 m
TAC-110 53.5 #/ft VFJL
3860 m
1.55 – 1.63 g/cc
1.55 – 1.63 g/cc 4000 4000
Eoceno
Eoc
3000 1.87
1.90
4500 4523 m 4355 m 4500
Paleoceno
4725 m 4725 m 9.5/8” @ BL 7”
3301 m 3413 m BL 7” 4952 mV,
BL 7” KSM 4972 m 1.90
7” TAC-140 35# HDSLX
TR 9 5/8”
P-110, 35 #/ft VFJL
4500
Viscosity (cP@1000/s)
Rheology Changes with Foam Quality
180
160 1.5g/L Polymer Model
140 1.5mL/L Foam Agent
120 pH 9.6
100 75°F, 1000psi N2
80
60 Actual Data
40
20
0
0 10 20 30 40 50 60 70 80 90 100
% N2 Quality
RFD
MPD Process Flow
RCH Flare
3 Phase
Vertical
MPD
Choke Separator
Defoamer
Injection
Closed Tanks
Diverter
Storage/Treatment
Manifold
Disposal/Reclaim
N2
Foamer
Injection
40
Viscosity (cP@170/s)
35
30
15
Modeled Data
10
5
60% Quality, 1500psi, 1.5g/L Polymer, 1.5mL/L Foaming Agent, pH 9.6
0
50 100 150 200 250 300 350
Temperature °F)
(
80 800
Pressure (psig)
60 600
40 400
20 200
0 0
1 2 3
Time