YES / NO 1 Check tag #, kVA size & voltage to drawing & data sheets 2 Check makers nameplate to purchase order & data sheets 3 Location & orientation to design & drawing 4 Enclosure as per area classification 5 Visual inspection for damage or missing parts 6 Check mounting & supports as per design & drawing 7 Oil filled transformer. Check oil level & for oil leaks 8 Air cooled transformer. Check for total vermin proofing 9 Check bushings, marking, terminations & sealing of both primary & secondary compartments 10 Check proper mounting & support of transformer 11 Check both primary & secondary cable sizes, numbers & terminations conform with design & drawing 12 Check tap changer is lockable & selecting positions 13 Megger primary & secondary cables. Record readings on QTR-1 14 Megger test transformer & record readings on QTR-3 15 Check terminations & glanding prior to sealing compartments 16 Check EARTHING, earth rods & wells to design & drawing 17 Megger test earth rods & record readings on QTR-6 18 Any deviations, revisions or changes to be recorded for As Builts