SLAB CALCULATION

Structural Model :

Type Slab = S1 ly 5 1.0 < 2.5 ( two way slab )


= =
Thickness = 100 mm lx 5
Material :
fc' = 186.75 kg/cm2 from SKSNI T-15-1991-03 table, we find :

lx
2
fy = 2400 kg/cm2
2
2 Mlx = Mtx 0.001 q lx2 * 51
2
Mly = Mty 0.001 q lx2 * 51

ly
Loading : a. Dead Load - Selfweight of Slab = 240 kg/m2
- Tile , t 3 cm = 72 kg/m2
- Mortar, t 2 cm = 42 kg/m2 2
- Ceiling, ( Asbes Cement + hanger ) = 18 kg/m2 2
- M&E = 0 kg/m2 2+
2
q dl = 372 kg/m2
2
b. Live Load q ll = 250 kg/m2
2
c. Ultimate Load qu = 1.2 q dl + 1.6 q ll = 846.4 kg/m2
2 2
Moment : 2
2 2
Mlx = - Mtx = 1079.16 kg m
Mly = - Mty = 1079.16 kg m

a. Rebar Required :
a.1 ( x - dirrection )

m = fy = 15.1193 ; Rn = Mu = 70 kg/cm22 d= 44 mm ; ø = 0.8


0.85 fc' ø b d2 2 b= 1000 mm
2
r req = 1 1 - 1 - 2 m Rn = 0.0430 > r min
m fy

r min = 1.4 = 0.0058 rmin = 0.005833


fy As = r o * b * d = 18.93 cm2
r r = 1.33 * r req ro = 0.043028
= 0.0572
a.2 ( y - dirrection )
m = fy = 15.1193 ; Rn = Mu = 43 kg/ cm2 ; d= 56 mm ; ø = 0.8
0.85 fc' ø b d2 b= 1000 mm

r req = 1 1 - 1 - 2 m Rn = 0.0214 > r min


m fy

r min = 1.4 = 0.0058 rmin = 0.005833


fy As = r o * b * d = 9.41 cm2
r r = 1.33 * r req ro = 0.021378
= 0.0284
b. Shrinkage and Temperature
r min = 0.0018
As min = 0.0018 * b * d = 0.8 cm2
A so = 18.93 cm2 x - dirrection
A so = 9.41 cm2 y - dirrection

c. Re-bar Selection
D = 12 mm ; Ab = 1.13 cm2

Longitudinal Re-bar ( for Shorter span ) S max = 3*h = 300 mm


Transversal Re-bar ( for Longer span ) S max = 5*h = 500 mm

No. of Re-bar per meter, n = A so / Ab


nx = 17
ny = 8
Spacing of Re-bar, s =1000/(n-1)
sx = 50 mm use D 12 @ 50 mm
sy = 125 mm use D 12 @ 125 mm

SKETCH :
50

100
50

12 @ 50 mm
d. Crack Control
Chose "1" or "2" : 2 INTERIOR EXPOSURE
1 EXTERIOR EXPOSURE
2 INTERIOR EXPOSURE
s = 50 mm ; b = 1.35 for Slab
bw = 1000 mm
dc = 44 mm
A = 2 * s* dc = 4400 mm2
fs = 0.6 * fy = 144 MPa
z = fs * ( dc * A)1/3 = 8330 N/mm
= 8.33 MN/m < 30 MN/m OK !!
w = 11*b *fs* (dc*A)1/3 = 0.124 mm < 0.4 mm OK !!
100000
Ly/Lx 1.0 1.1 1.2 1.3 1.4 1.5 1.6 1.7 1.8 1.9 2.0 2.1 2.2 2.3 2.4 2.5
Mlx = Mtx 51 57 63 68 72 75 78 80 81 82 82 82 83 83 83 83
Mly = Mty 51 53 54 55 55 55 54 54 54 54 53 53 53 52 52 51
SLAB CALCULATION W/ BONDEX :
Structural Model :

Type Slab = S1 ly 6 1.4


= =
Thickness = 100 mm lx 4.5
Material :
fc' = 332 kg/cm2 from SKSNI T-15-1991-03 table, we fin

x
l
fy = 2 2
5000 kg/cm
2
2 Mlx = Mtx 0.001 q lx2 *
2
Mly = Mty 0.001 q lx2 *

ly
Loading : a. Dead Load - Selfweight of Slab = 240 kg/m2
- Tile , t 0 cm = 0 kg/m2
- Mortar, t 3 cm = 63 kg/m2 2
- Ceiling, ( Asbes Cement + hanger = 18 kg/m2 2
- M&E = 0 kg/m2 2+
2
q dl = 321 kg/m2
2 2
b. Live Load q ll = 100 kg/m
c. Ultimate Load qu = 1.2 q dl + 1.6 q ll = 545.2 kg/m2 2
2
Moment : 2
2
Mlx = - Mtx = 794.902 kg m
Mly = - Mty = 607.217 kg m

a. Rebar Required :
a.1 ( x - dirrection )

m = fy = 17.7179 ; Rn = Mu = 47 kg/cm22 d= 46
0.85 fc' ø b d2 2 b= 1000
2
r req = 1 1 - 1 - 2 m Rn = 0.0103 > r min
m fy

r min = 1.4 = 0.0028 rmin = 0.0028


fy As = r o * b * d = 4.76
r r = 1.33 * r req ro = 0.010338
= 0.0138
a.2 ( y - dirrection )
m = fy = 17.7179 ; Rn = Mu =
26 kg/cm22 d= 54
0.85 fc' øb d 2
2 b= 1000
2
r req = 1 1 - 1 - 2 m Rn = 0.0055 > r min
m fy

r min = 1.4 = 0.0028 rmin = 0.0028


fy As = r o * b * d = 2.52
r r = 1.33 * r req ro = 0.005471
= 0.0073
b. Shrinkage and Temperature
r min = 0.0018
As min = 0.0018 * b * d = 0.8 cm2
A so = 4.76 cm2 x - dirrection
A so = 2.52 cm2 y - dirrection

c. Re-bar Selection
D = 8 mm ; Ab = 0.50 cm2

Longitudinal Re-bar ( for Shorter span ) S max = 3*h = 300 mm


Transversal Re-bar ( for Longer span ) S max = 5*h = 500 mm

No. of Re-bar per meter, n = A so / Ab


nx = 9.5
ny = 5.0
Spacing of Re-bar, s =1000/(n-1)
sx = 100 mm use D 8 @ 100 mm
sy = 225 mm use D 8 @ 225 mm

SKETCH :

50

100
50
8 @ 100 mm
d. Crack Control
Chose "1" or "2" : 2 INTERIOR EXPOSURE
1 EXTERIOR EXPOSURE
2 INTERIOR EXPOSURE
s = 150 mm ; b = 1.35 for Slab
bw = 1000 mm
dc = 29 mm
A = 2 * s* dc = 8700 mm2
fs = 0.6 * fy = 300 MPa
z = fs * ( dc * A)1/3 = 18957 N/mm
= 18.96 MN/m < 30 MN/m OK !!
w = 11*b *fs* (dc*A) 1/3
= 0.282 mm < 0.4 mm OK !!
100000
< 2.5 ( two way slab )

T-15-1991-03 table, we find :

0.001 q lx2 * 72 Ly/Lx 1.0 1.1 1.2 1.3


0.001 q lx2 * 55 Mlx = Mtx 51 57 63 68
Mly = Mty 51 53 54 55

2
2

mm ; ø = 0.8
mm

cm2

mm ; ø = 0.8
mm

cm2
1.4 1.5 1.6 1.7 1.8 1.9 2.0 2.1 2.2 2.3 2.4 2.5
72 75 78 80 81 82 82 82 83 83 83 83
55 55 54 54 54 54 53 53 53 52 52 51
SLAB CALCULATION
Structural Model :

Type Slab = S1 ly 6 1.5 < 2.5 ( two way slab )


= =
Thickness = 150 mm lx 4
Material :
fc' = 332 kg/cm2 from SKSNI T-15-1991-03 table, we find :

lx
fy = 2 2
4600 kg/cm
2
2 Mlx = Mtx 0.001 q lx2 * 75
2
Mly = Mty 0.001 q lx2 * 55

ly
Loading : a. Dead Load - Selfweight of Slab = 360 kg/m2
- Tile , t- 2 cm = 48 kg/m2
- Mortar, t - 3 cm = 63 kg/m2 2
- Ceiling, ( Asbes Cement + hanger ) = 18 kg/m2 2
- M&E = 0 kg/m2 2+ +
2
q dl = 489 kg/m2
b. Live Load q ll = 800 kg/m2 2
c. Ultimate Load qu = 1.2 q dl + 1.6 q ll = 1866.8 kg/m2 2
2 2
Moment : 2 2
Mlx = - Mtx = 2240.16 kg m
Mly = - Mty = 1642.78 kg m

a. Rebar Required :
a.1 ( x - dirrection )

m = fy = 16.3005 ; Rn = Mu = 23.1 kg/cm


22 d= 110 mm ; ø = 0.8
0.85 fc' ø b d2 2 b= 1000 mm
2
r req = 1 1 - 1 - 2 m Rn = 0.0053 > r min
m fy

r min = 1.4 = 0.0030 rmin = 0.00304


fy As = r o * b * d = 5.78 cm2
r r = 1.33 * r req ro = 0.00526
= 0.0070
a.2 ( y - dirrection )
m = fy = 16.3005 ; Rn = Mu = 14.3 kg/cm2
2
d= 120 mm ; ø = 0.8
0.85 fc' ø b d2 2 b= 1000 mm
2
r req = 1 1 - 1 - 2 m Rn = 0.0032 > r min
m fy

r min = 1.4 = 0.0030 rmin = 0.00304


fy As = r o * b * d = 3.50 cm2
r r = 1.33 * r req ro = 0.00318
= 0.0042
b. Shrinkage and Temperature
r min = 0.0018
As min = 0.0018 * b * d = 2 cm2
A so = 5.78 cm2 x - dirrection
A so = 3.50 cm2 y - dirrection

c. Re-bar Selection
D = 10 mm ; Ab = 0.79 cm2

Longitudinal Re-bar ( for Shorter span ) S max = 3*h = 450 mm


Transversal Re-bar ( for Longer span ) S max = 5*h = 750 mm

No. of Re-bar per meter, n = A so / Ab


nx = 7.4
ny = 4.5
Spacing of Re-bar, s =1000/(n-1)
sx = 150 mm use D 10 @ 150 mm
sy = 275 mm use D 10 @ 275 mm

SKETCH :
150

10 @ 150 mm
d. Crack Control
Chose "1" or "2" : 2 INTERIOR EXPOSURE
1 EXTERIOR EXPOSURE
2 INTERIOR EXPOSURE
s = 150 mm ; b = 1.35 for Slab
bw = 1000 mm
dc = 30 mm
A = 2 * s* dc = 9000 mm2
fs = 0.6 * fy = 276 MPa
z = fs * ( dc * A)1/3 = 17839 N/mm
= 17.839 MN/m < 30 MN/m OK !!
w = 11*b *fs* (dc*A)1/3 = 0.2649 mm < 0.4 mm OK !!
100000
SPREAD FOUNDATION
1. Loading Data
P Loading : a. Permanent Load b. Temporary Load
Mx P = Axial Load
(Mz) ( w/o foundation weight )
Vx = 21.43 ton P = 23.62 ton
(Vz Vx = Shear ( x - direction )
) = 2.1 ton Vx = 2.95 ton
Vz = Shear ( z - direction )
= 3.10 ton Vz = 2.58 ton
Df H Mx = Moment ( x - direction )
= 0.00 ton. m Mx = 0.00 ton.m
Mz = Moment ( z - direction )
= 0.00 ton.m Mz = 0.00 ton.m

Note : Leter inside bracket means Forces which have direction perpendicular
to this plane.
B (L)
2. Assumed Dimension
b

h
Foundation Size Data :
H= 110 cm
Df = 80 cm
B= 440 cm
L= 300 cm
hf = 40 cm
d= 32.5 cm
H Df b= 45 cm
h= 45 cm

d hf

c1
Punching Shear Line :
b1
b1 = b + d = 77.5 cm
b2 = h + d = 77.5 cm
c1 = b/2 + d = 55 cm
L b2 c2 = h/2 + d = 55 cm

z c2

B
3. Check of Soil Reaction "fe"
Design Loads :
a) Vertical Loads (P)

Perm. : P tot = P + Wf = 43800.4 kg


Temp. : P tot = P + Wf = 45990.4 kg

Where,Wf = Wp + Wb + Ws = 22370.4 Kg
Wp = Pedestal weight = 340.2 Kg
Wb = Footing weight = 12672 Kg
Ws = Soil weight on Footing = 9358.2 Kg

b) Moment due to Horizontal Force (M)

Permanent : Temporary :
Mx1 = Vx . H Mx1 = Vx . H
= 2310 kg m = 3245 kg m

Mz1 = Vz . H Mz1 = Vz . H
ex
(ez) = 3404.5 kg m = 2835.8 kg m

c) Eccentricity (e)
P tot
- Perm. : Mx.tot = Mx1 + Mx = 2310 kg m ex = 5.2739 cm
Mz.tot = Mz1 + Mz = 3404.5 kg m ez = 7.7728 cm
- Temp. : Mx.tot = Mx1 + Mx = 3245 kg m ex = 7.0558 cm
Mz.tot = Mz1 + Mz = 2835.8 kg m ez = 6.1661 cm
Xn > B
(L)
d) Compute "fe" : P tot
fe = a2 B.L
Take " a " depend on " e " condition below :

a = 1 + factor x + factor z
Where : ex(ez) < B(L)/6, factor x (z) = 6 ex(ez)/ B (L)
Xn < B ex(ez) > B(L)/6, factor x (z) = 2/ [3{0.5-ex(ez)/ B (L)}]
(L)
for this case :
- Perm. : ex < B/6 Factor x = 0.07
ez < L/6 Factor z = 0.16
Xn = Neutral Axis
- Temp. : ex < B/6 Factor x = 0.10
ez < L/6 Factor z = 0.12
e) Allowable soil stress "Fe" :
- Permanent - Temporary
Fe = 0.40 kg/cm2 Fe = 0.52 kg/cm2
f) Soil stress "fe" :

- Permanent - Temporary
P tot = 0.41 kg/cm2 P tot = 0.42 kg/cm2
fe = a fe =a
B*L B*L
> Fe Change < Fe OK !
a = 1.227 a = 1.220

4. Check of Stability
Permanent : Temporary :
Overturning Moment ( OM ) : Mx tot = 2310 kg m Mx tot = 3245 kg m
Mz tot = 3404.5 kg m Mz tot = 2835.8 kg m
9
Resistant Moment ( RM ) : Ptot.B/2 = 96361 kg m Ptot . B/2 = 101179 kg m
Ptot.L/2 = 65701 kg m Ptot . L/2 = 68986 kg m
Permanent Load : RM / OM = Ptot . B = 41.7 > 2.0
2 . Mx tot
Ptot . L 19.3 > 2.0
2 . Mz tot
Temporary Load : RM / OM = Ptot . B = 31.2 > 1.5
2 . Mx tot
Ptot . L 24.3 > 1.5
2 . Mz tot

5. Footing Design
5.1 Design Soil Reaction "qus"
fe max = 0.425 kg/cm2
qus = 1.6 * ( fe max - Wf ) 0.409 kg/cm2 ; Note : 1.6 is used an average load factor,
B.L because the proportion of dead and
live load are not known.
5.2 Required Re-bar due to Bending Moment
a. Design Moment :
Mux = qus . L . ( B - b )2 /8 = 23912.0 kg m
Muz = qus . B . ( L - h )2 /8 = 14616.1 kg m
b. Steel Ratio, r :
fy = 4000 kg/cm2
fc' = 122.5 kg/cm2
m= fy 38.4 ; Ø = 0.9
0.85 fc'

- About x - dirrection :

Rn = Mux 8.4 kg/ cm2


ø L d2

r req = 1 1 - 1 - 2 m Rn 0.0022 < r min


m fy

r min = 1.4 0.0035


fy r min = 0.0029
r r = 1.33 * r req = 0.0029
ro = 0.0029

As = ro*L*d = 28.4 cm 2

D= 16 mm ; Ab = 2.01 cm2
n = A s / Ab 15
Spacing, s = 191 mm ; whichever is smaller.
Spacing Limit : S max = 2d = 650 mm Spacing s = 190 mm
take : D 16 @ 190

- About z - dirrection :

Rn = Muz 3.5 kg/ cm2


ø B d2
r req = 1 1 - 1 - 2 m Rn 0.0009 < r min
m fy

r min = 1.4 0.0035


fy r min = 0.0012
r r = 1.33 * r req = 0.0012
ro = 0.0012

As = ro*B*d = 16.9 cm2


D= 16 mm ; Ab = 2.01 cm2
n = A s / Ab 9
spacing, s = 522 mm Whichever is smaller.
Spacing Limit : S max = 2d = 650 mm spacing s = 500 mm

take : D 16 @ 500
5.3 Check of Shear Stress

Vux = qus * ( B/2 - c1) / d = 2.07 kg/cm2 <


ø (0.53 vfc') = 4.986 kg/cm2
Vuz = qus * ( L/2 - c2) / d = 1.19 kg/cm 2
<
Ok !!
5.4 Check of Punching Shear

Vup = qus * ( B*L - b1*b2) = 5.11 kg/cm2 < ø (1.06 vfc') = 9.972 kg/cm2
2 * ( b1 + b2 ) * d
Ok !!
6. Sketch :

D 16 @ 190 D 16 @ 500

7. Pedestal :
Check requirement :
Ratio = Pedestal Length 70
= 1.56 < 2.5 Short Column
Width of pedestal 45
=
Rebar requirement :

ro = 0.01 As = r o Ag = 20.25 cm2

Used 8 D-13 As = 10.62 cm2 No Ok!


Pile Foundation
1. Dimensions : 2. Loading Data :
Loading : a. Permanent Load ; b. Temporary Load
X
P = Axial Load ( w/o foundation weight )
P Mx
Z P = 15.00 ton ; P=
Vx Mz Vx = Shear ( x - direction )
Vx = 5.00 ton ; Vx =
Vz Vz = Shear ( z - direction )
Vz = 1.50 ton Vz =

ht hs
;

hp
Mx = Moment ( x - direction )
Mx = 0.50 ton. m ; Mx =
Mz = Moment ( z - direction )
hc

Mz = 0.60 ton.m ; Mz =

1 2
3. Reaction :
Footing weight, Wf = Wp + Wc + Ws + Wt =
Wp = Pedestal weight =
C

Wc = Pile Cap weight =


wp

wc

Ws = Soil weight on Footing =


C

lp
Ws = Slab weight on Footing =

A B A
Total Loading : a. Permanent L ; b. Temporary Load
E
lc Pt = Total Axial Load = P + Wf
Pt = 20.284 ton Pt =
Pedestal / Column : Vx = 5.00 ton ; Vx =
length, lp = 40.0 cm Vz = 1.50 ton ; Vz =
width, wp = 40.0 cm Mtx = 6.02 ton. m ; Mtx =
depth, hp = 120.0 cm Mtz = 2.40 ton. m ; Mtz =

Foundation : Eccentricity, ( = e) : a. Permanent ; b. Temporary Load


length, lc = 230.0 cm (min = ### cm) epx = (A+E) - lc/2
width, wc = 100.0 cm (min = 96.0 cm) epx = 0.100 m
depth, hc = 55.0 cm (min = 55.0 cm) ex = 0.297 m ; ex =
A = 50.0 cm (min = 48.0 cm) ez = 0.118 m ; ez =
B = 130.0 cm (min = ### cm) so, ex1 = 0.9468 m ; ex1 =
C = 50.0 cm (min = 48.0 cm) ex2 = 0.353 m ; ex2 =
E = 75.0 cm ez1 = ez2 = ez = 0.118 m ; z1 = ez2 = ez =

Others : 4. Pile Reaction :


Slab thk., hs = 15.0 cm if any ) Pile-1 : P1 = 24.84 ton ; P1 =
Soil thk., ht = 25.0 cm if any ) P2 = 36.01 ton ; P2 =

Pile Data : PC40 5. Check Pile Reactions vs Allowable :


Length L = 12.0 m (from Soil Invest.)
Dia/Rec = 40.0
Allow.Comp. Call = 70.0 ton (from Soil Invest.)
Allow.Tension Tall = 35.0 ton (from Soil Invest.)
Lall = 6.0 ton (from Soil Invest.)
b. Temporary Load Dia. / Pall Tall Lall
( w/o foundation weight )
f Rect. ton ton ton
16.00 ton RC20 20 35 25 3
PC35 35 60 30 5
6.00 ton PC40 40 70 35 6
PC45 45 90 40 7
2.50 ton RC25 25 50 30 4
RC30 30 60 35 5
1.50 ton.m

0.90 ton.m

5.284 ton
0.461 ton
3.036 ton
1.017 ton
0.770 ton

b. Temporary Load

21.284 ton
6.00 ton
2.50 ton
7.23 ton.m
3.90 ton.m

b. Temporary Load

0.340 m
0.183 m
0.9898 m
0.310 m
0.183 m

25.27 ton
38.58 ton
SECONDARY BEAM DESIGN
1. Loading Data

Loading : a. Dead Load


- Selfweight of Beam = 730.8 kg/m2
- Slab = 360 kg/m2 (Thk. = 150 )
- Tile = 0 kg/m2 (Thk. = 0 )
- Mortar = 0 kg/m2 (Thk. = 0 )
- Ceiling, ( Asbes Cement + hanger ) = 0 kg/m2
q dl = 1090.8 kg/m2
b. Live Load q ll = 525 kg/m2

c. Ultimate Load qu = 1.4 q dl + 1.7 q ll 2419.6 kg/m2


2
Material : 2
fc' = 332 kg/cm2
fy = 4100 kg/cm22
2
2. Structural Model

+ Mu - DIAGRAM

Vu - DIAGRAM

span, B = 4 m
L= 7 m
d b= 30 cm
h= 70 cm
d= 62.8 cm

Mu = 1/12 qu * B * L^2 39.52 ton.m


b
Vu = 1/2 qu * B * L = 33.87 ton

3. Re-bar due to Bending Moment

m = fy = 14.529 ; ø = 0.9
0.85 fc'

Rn = Mu = 37.114 kg/ cm2


ø b d^2

r req = 1 1 - 1 - 2 m Rn = 0.010 > r min


m fy

r min = 1.4 = 0.0034


fy r min = 0.0034

r r = 1.33 * r req = 0.0130


ro = 0.0097

As = ro * b* d= 18.35 cm2
D = 20 mm ; Ab = 3.14 cm2
n = A s / Ab = 6 Aprov. = 18.85 cm2
Spacing = 2.12 cm

4. Stirrup due to Shear

4.a Necessity of Stirrups :

i) When Vu < 1/2 øVc , Shear re-bar is not necessary.


ii) When øVc > Vu > 1/2 øVc , Min. shear re-bar is required.
iii) When Vu > ø Vc , Shear re-bar is required

4.b Compute Shear Reinforcement

Vu < ø Vn = ø (Vc + Vs) ; ø = 0.85


Vu = 33874.68 kg
Vc = 0.53efc' b d = 18194 kg Shear re-bar is required
ø Vc = 15465 kg

Vs = 21659 kg < 2.12efc'bd oke !!!


2.12efc'bd = 72776 kg

D = 12 mm ; Ab = 1.13 cm2
As = Vs*100/(fy*d) = 8.4118 cm2
n = 4
spacing,s = 1000 / (n - 1) = 333 mm

4.c Stirrups Spacing Limits

1.06efc'bd = 36388 kg > Vs

Smax = d/2 or 60 cm ; whichever is smaller

SKETCH :

SIZE : 300 X 700

BOTH END MIDDLE


TOP : 2 D20 2 D20
BOT : 2 D20 4 D20
STIRRUP D10 - 150 D10 - 250
CONCRETE-GIRDER DESIGN
Material =
fc' = 332 kg/cm2
fy = 4100 kg/cm2
m = 14.5287 i) When Vu < 1/2 øVc , Not Necessary
r min = 0.003 ii) When øVc > Vu > 1/2 øVMin. is Required
iii) When Vu > ø Vc , To be Required
IV) Vs > 2.12√fc'bd Change Size !!!

Longitudinal Reinforcement due to Bending Moment Stirrup due to Shear


BEAM SIZE
Req'd Re-bar Min Re-bar Actual Re-bar Re-bar Min. Shear Actual
MARK Design Moment Design Shear
b h d r As Asm r Aso Arrangement 1/2øVc øVc Reinf. Spacing Stirrup
(cm) (cm) (cm) ( ton.m ) (cm2) (cm2) (cm2) n n ( ton ) ( ton ) ( ton ) s ( mm ) (mm )
TOP 19.76 0.0024 11.35 16.39 0.0034 16.39 5.2 6 -D 20 33.870
END BOTH Mu Vu 19.700 39.401 D 10 @ 240 D 10 @ 225
BOT 11.86 0.0014 6.76 16.39 0.0034 16.39 5.2 6 -D 20
1 1GY1 100 55 48
TOP 15.81 0.0019 9.05 16.39 0.0034 16.39 5.2 6 -D 20 20.322
MIDDLE Mu Vu 19.700 39.401 D 10 @ 240 D 10 @ 225
BOT 39.52 0.0048 23.12 16.39 0.0048 23.12 7.4 8 -D 20
TOP 6.95 0.0024 3.03 4.32 0.0034 4.32 2.1 3 -D 16 8.223
END BOTH Mu Vu 5.188 10.376 D 10 @ 316 D 10 @ 300
BOT 2.09 0.0007 0.90 4.32 0.0034 4.32 2.1 3 -D 16
2 1GY2 20 70 63.2
TOP 1.43 0.0005 0.61 4.32 0.0034 4.32 2.1 3 -D 16 4.112
MIDDLE Mu Vu 5.188 10.376 D 10 @ 316 D 10 @ 300
BOT 4.76 0.0016 2.07 4.32 0.0034 4.32 2.1 3 -D 16
TOP 3.59 0.0062 3.07 1.70 0.0062 3.07 1.5 2 -D 16 4.486
END BOTH Mu Vu 2.044 4.088 D 10 @ 166 D 10 @ 150
BOT 1.08 0.0018 0.89 1.70 0.0034 1.70 0.8 2 -D 16
3 1GX1 15 40 33.2
TOP 0.89 0.0015 0.74 1.70 0.0034 1.70 0.8 2 -D 16 2.243
MIDDLE Mu Vu 2.044 4.088 D 10 @ 166 D 10 @ 150
BOT 2.98 0.0051 2.52 1.70 0.0051 2.52 1.3 2 -D 16
TOP 8.69 0.0161 8.03 1.70 0.0161 8.03 4.0 4 -D 16 8.456
END BOTH Mu Vu 2.044 4.088 D 10 @ 166 D 10 @ 150
BOT 2.61 0.0044 2.20 1.70 0.0044 2.20 1.1 2 -D 16
4 1GX2 15 40 33.2
TOP 1.46 0.0024 1.21 1.70 0.0034 1.70 0.8 2 -D 16 4.228
MIDDLE Mu Vu 2.044 4.088 D 10 @ 166 D 10 @ 150
BOT 4.87 0.0085 4.23 1.70 0.0085 4.23 2.1 3 -D 16
TOP 4.65 0.0023 2.97 4.43 0.0034 4.43 2.2 3 -D 16 8.328
END BOTH Mu Vu 5.319 10.638 D 10 @ 216 D 10 @ 200
BOT 1.40 0.0007 0.88 4.43 0.0034 4.43 2.2 3 -D 16
5 1GX3 30 50 43.2
TOP 3.88 0.0019 2.47 4.43 0.0034 4.43 2.2 3 -D 16 4.164
MIDDLE Mu Vu 5.319 10.638 D 10 @ 216 D 10 @ 200
BOT 12.95 0.0066 8.53 4.43 0.0066 8.53 4.2 5 -D 16
TOP 24.29 0.0050 11.74 7.95 0.0050 11.74 5.8 6 -D 16 19.846
END BOTH Mu Vu 9.555 19.109 D 10 @ 291 D 10 @ 275
BOT 7.29 0.0015 3.43 7.95 0.0034 7.95 4.0 4 -D 16
6 1GX4 40 65 58.2
TOP 8.75 0.0018 4.13 7.95 0.0034 7.95 4.0 4 -D 16 9.923
MIDDLE Mu Vu 9.555 19.109 D 10 @ 291 D 10 @ 275
BOT 29.18 0.0061 14.22 7.95 0.0061 14.22 7.1 8 -D 16
TOP 19.51 0.0040 9.36 7.95 0.0040 9.36 4.7 5 -D 16 19.551
END BOTH Mu Vu 9.555 19.109 D 10 @ 291 D 10 @ 275
BOT 5.85 0.0012 2.75 7.95 0.0034 7.95 4.0 4 -D 16
7 1GX5 40 65 58.2
TOP 3.14 0.0006 1.47 7.95 0.0034 7.95 4.0 4 -D 16 9.776
MIDDLE Mu Vu 9.555 19.109 D 10 @ 291 D 10 @ 275
BOT 10.47 0.0021 4.95 7.95 0.0034 7.95 4.0 4 -D 16
TOP 2.83 0.0103 3.58 1.19 0.0103 3.58 1.8 2 -D 16 3.765
END BOTH Mu Vu 1.428 2.857 D 10 @ 116 D 10 @ 100
BOT 0.85 0.0029 1.01 1.19 0.0034 1.19 0.6 2 -D 16
8 2GY1 15 30 23.2
TOP 0.78 0.0027 0.93 1.19 0.0034 1.19 0.6 2 -D 16 1.883
MIDDLE Mu Vu 1.428 2.857 D 10 @ 116 D 10 @ 100
BOT 2.61 0.0094 3.27 1.19 0.0094 3.27 1.6 2 -D 16
TOP 5.87 0.0027 2.57 3.24 0.0034 3.24 1.6 2 -D 16 6.782
END BOTH Mu Vu 3.891 7.782 D 10 @ 316 D 10 @ 300
BOT 1.76 0.0008 0.76 3.24 0.0034 3.24 1.6 2 -D 16
9 2GY2 15 70 63.2
TOP 1.11 0.0005 0.48 3.24 0.0034 3.24 1.6 2 -D 16 3.391
MIDDLE Mu Vu 3.891 7.782 D 10 @ 316 D 10 @ 300
BOT 3.71 0.0017 1.61 3.24 0.0034 3.24 1.6 2 -D 16
TOP 1.22 0.0020 1.01 1.70 0.0034 1.70 0.8 2 -D 16 3.182
END BOTH Mu Vu 2.044 4.088 D 10 @ 166 D 10 @ 150
BOT 0.37 0.0006 0.30 1.70 0.0034 1.70 0.8 2 -D 16
10 2GX1 15 40 33.2
TOP 0.97 0.0016 0.80 1.70 0.0034 1.70 0.8 2 -D 16 1.591
MIDDLE Mu Vu 2.044 4.088 D 10 @ 166 D 10 @ 150
BOT 3.24 0.0055 2.76 1.70 0.0055 2.76 1.4 2 -D 16
TOP 2.77 0.0035 2.32 2.27 0.0035 2.32 1.2 2 -D 16 5.462
END BOTH Mu Vu 2.725 5.450 D 10 @ 166 D 10 @ 150
BOT 0.83 0.0010 0.68 2.27 0.0034 2.27 1.1 2 -D 16
11 2GX2 20 40 33.2
TOP 1.62 0.0020 1.34 2.27 0.0034 2.27 1.1 2 -D 16 2.731
MIDDLE Mu Vu 2.725 5.450 D 10 @ 166 D 10 @ 150
BOT 5.40 0.0070 4.65 2.27 0.0070 4.65 2.3 3 -D 16
TOP 2.72 0.0009 1.39 5.45 0.0034 5.45 2.7 3 -D 16 6.842
END BOTH Mu Vu 6.550 13.101 D 10 @ 266 D 10 @ 250
BOT 0.81 0.0003 0.42 5.45 0.0034 5.45 2.7 3 -D 16
12 2GX3 30 60 53.2
TOP 3.46 0.0011 1.78 5.45 0.0034 5.45 2.7 3 -D 16 3.421
MIDDLE Mu Vu 6.550 13.101 D 10 @ 266 D 10 @ 250
BOT 11.54 0.0038 6.05 5.45 0.0038 6.05 3.0 4 -D 16
TOP 17.14 0.0042 9.01 7.27 0.0042 9.01 4.5 5 -D 16 12.299
END BOTH Mu Vu 8.734 17.468 D 10 @ 266 D 10 @ 250
BOT 5.14 0.0012 2.64 7.27 0.0034 7.27 3.6 4 -D 16
13 2GX4 40 60 53.2
TOP 5.99 0.0014 3.08 7.27 0.0034 7.27 3.6 4 -D 16 6.149
MIDDLE Mu Vu 8.734 17.468 D 10 @ 266 D 10 @ 250
BOT 19.96 0.0050 10.55 7.27 0.0050 10.55 5.2 6 -D 16
TOP 11.41 0.0028 5.93 7.27 0.0034 7.27 3.6 4 -D 16 13.872
END BOTH Mu Vu 8.734 17.468 D 10 @ 266 D 10 @ 250
BOT 3.42 0.0008 1.75 7.27 0.0034 7.27 3.6 4 -D 16
14 2GX5 40 60 53.2
TOP 4.32 0.0010 2.22 7.27 0.0034 7.27 3.6 4 -D 16 6.936
MIDDLE Mu Vu 8.734 17.468 D 10 @ 266 D 10 @ 250
BOT 14.41 0.0035 7.54 7.27 0.0035 7.54 3.7 4 -D 16
TOP 3.37 0.0043 2.84 2.27 0.0043 2.84 1.4 2 -D 16 7.081
END BOTH Mu Vu 2.725 5.450 D 10 @ 166 D 10 @ 150
1BY1 BOT 1.01 0.0013 0.83 2.27 0.0034 2.27 1.1 2 -D 16
15 20 40 33.2
2BY1 TOP 2.32 0.0029 1.93 2.27 0.0034 2.27 1.1 2 -D 16 3.540
MIDDLE Mu Vu 2.725 5.450 D 10 @ 166 D 10 @ 150
BOT 7.72 0.0103 6.81 2.27 0.0103 6.81 3.4 4 -D 16
TOP 1.25 0.0016 1.03 2.27 0.0034 2.27 1.1 2 -D 16 5.069
END BOTH Mu Vu 2.725 5.450 D 10 @ 166 D 10 @ 150
1BY2 BOT 0.37 0.0005 0.31 2.27 0.0034 2.27 1.1 2 -D 16
16 20 40 33.2
2BY2 TOP 1.50 0.0019 1.24 2.27 0.0034 2.27 1.1 2 -D 16 2.534
MIDDLE Mu Vu 2.725 5.450 D 10 @ 166 D 10 @ 150
BOT 5.00 0.0064 4.28 2.27 0.0064 4.28 2.1 3 -D 16
Stirrup due to Shear
Shear
Reinforcement

Min. is
Required
Min. is
Required
Min. is
Required

Not Necessary

To be Required

Min. is
Required

To be Required

To be Required

Min. is
Required

Not Necessary

To be Required

Min. is
Required

To be Required

Min. is
Required

To be Required

Min. is
Required
Min. is
Required

Not Necessary

Min. is
Required

Not Necessary

To be Required

Min. is
Required
Min. is
Required

Not Necessary

Min. is
Required

Not Necessary

Min. is
Required

Not Necessary

To be Required

Min. is
Required
Min. is
Required

Not Necessary
COLUMN-TBL

COLUMN TABLE ( FOR UNBRACED FRAME ONLY )


SIZE Check of Slenderness Effects Moment magnification fa
MARK b h Dir Lu yA yB r øPc
k kLu/r Check Cm bd d
( cm ) ( cm ) ( cm ) TOP BOT ( cm ) ( ton )
X 2.17 10 2.00 8.66 80.83 To be considered 1 0.5 55.53 2.045
C1 30 30 350
Z 1.81 10 1.22 8.66 49.31 To be considered 1 0.5 149.25 1.235

NOTE :
y = S EIk / lk ; y = 0 ( fixed end ) ø= 0.7
S EIb / lb y = 10 ( column end supported on footing ) Pc = p2 EIk
EIk = ( Ec Igk / 2.5 ) ; EIb = ( Ec Igb / 5 ) (kLu)^2
1 + ßd 1 + ßd
fc' = 210 kg/cm2
Ec = 15100* fc'^.5 = 218.82 ton/cm2
x - dir : z - dir :
Igk = 1/12 bh3 = 67500 cm4 Igk = 1/12 hb3 = 67500 cm4
Ec Igk = 1477.0 ton m2 Ec Igk = 1477.0 ton m2
EIk = 393.9 ton m2 EIk = 393.9 ton m2
Igb = 106667 cm4 Igb = 106667 cm4
Ec Igb = 2334.1 ton m2 Ec Igb = 2334.1 ton m2
EIb = 311.2 ton m2 EIb = 311.2 ton m2
lb = 6.0 m lb = 5.0 m

yA = 2.17 yA = 1.81
yB = 10 yB = 10
k= 2 ( from monogram ) k= 1.22 ( from monogram )
Check Eccentricity :
et = dMu / Pu = 0 mm
et min = ( 15 + 0.03 h ) = 24 mm
If et < et min , Mu should be taken from Pu . et min

COLUMN TABLE ( FOR UNBRACED FRAME ONLY )


SIZE Check of Slenderness Effects Moment magnification fa
MARK b h Dir Lu yA yB r øPc
k kLu/r Check Cm bd d
( cm ) ( cm ) ( cm ) TOP BOT ( cm ) ( ton )
X 2.17 2.17 1.60 8.66 64.66 To be considered 1 0.5 86.77 1.257
C2 30 30 350
Z 1.81 1.81 1.60 8.66 64.66 To be considered 1 0.5 86.77 1.257

NOTE :
y = S EIk / lk ; y = 0 ( fixed end ) ø= 0.7
S EIb / lb y = 10 ( column end supported on footing ) Pc = p2 EIk
EIk = ( Ec Igk / 2.5 ) ; EIb = ( Ec Igb / 5 ) (kLu)^2
1 + ßd 1 + ßd
fc' = 210 kg/cm2
Ec = 15100* fc'^.5 = 218.82 ton/cm2
x - dir : z - dir :
Igk = 1/12 bh3 = 67500 cm4 Igk = 1/12 hb3 = 67500 cm4
Ec Igk = 1477.0 ton m2 Ec Igk = 1477.0 ton m2
EIk = 393.9 ton m2 EIk = 393.9 ton m2

Igb = 106667 cm4 Igb = 106667 cm4


Ec Igb = 2334.1 ton m2 Ec Igb = 2334.1 ton m2
EIb = 311.2 ton m2 EIb = 311.2 ton m2
lb = 6.0 m lb = 5.0 m

yA = 2.17 yA = 1.81
yB = 2.17 yB = 1.81
k= 1.6 ( from monogram ) k= 1.6 ( from monogram )
Check Eccentricity :
et = dMu / Pu = 444 mm
et min = ( 15 + 0.03 h ) = 24 mm

If et < et min , Mu should be taken from Pu . et min


COLUMN-TBL

COLUMN TABLE ( FOR UNBRACED FRAME ONLY )


SIZE Check of Slenderness Effects Moment magnification fa
MARK b h Dir Lu yA yB r øPc
k kLu/r Check Cm bd d
( cm ) ( cm ) ( cm ) TOP BOT ( cm ) ( ton )
X 2.17 10 2.00 8.66 80.83 To be considered 1 0.5 55.53 2.045
C3 30 30 350
Z 1.81 10 1.22 8.66 49.31 To be considered 1 0.5 149.25 1.235

NOTE :
y = S EIk / lk ; y = 0 ( fixed end ) ø= 0.7
S EIb / lb y= 10 ( column end supported on footing ) Pc = p2 EIk
EIk = ( Ec Igk / 2.5 ) ; EIb = ( Ec Igb / 5 ) (kLu)^2
1 + ßd 1 + ßd
fc' = 210 kg/cm2
Ec = 15100* fc'^.5 = 218.82 ton/cm2

x - dir : z - dir :
Igk = 1/12 bh3 = 67500 cm4 Igk = 1/12 hb3 = 67500 cm4
Ec Igk = 1477.0 ton m2 Ec Igk = 1477.0 ton m2
EIk = 393.9 ton m2 EIk = 393.9 ton m2
Igb = 106667 cm4 Igb = 106667 cm4
Ec Igb = 2334.1 ton m2 Ec Igb = 2334.1 ton m2
EIb = 311.2 ton m2 EIb = 311.2 ton m2
lb = 6.0 m lb = 5.0 m

yA = 2.17 yA = 1.81
yB = 10 yB = 10
k= 2 ( from monogram ) k= 1.22 ( from monogram )
Check Eccentricity :

et = dMu / Pu = 0 mm
et min = ( 15 + 0.03 h ) = 24 mm

If et < et min , Mu should be taken from Pu . et min

COLUMN TABLE ( FOR UNBRACED FRAME ONLY )


SIZE Check of Slenderness Effects Moment magnification fa
MARK b h Dir Lu yA yB r øPc
k kLu/r Check Cm bd d
( cm ) ( cm ) ( cm ) TOP BOT ( cm ) ( ton )
X 2.17 2.17 1.60 8.66 64.66 To be considered 1 0.5 86.77 1.257
C4 30 30 350
Z 1.81 1.81 1.60 8.66 64.66 To be considered 1 0.5 86.77 1.257

NOTE :
y = S EIk / lk ; y = 0 ( fixed end ) ø= 0.7
S EIb / lb y= 10 ( column end supported on footing ) Pc = p2 EIk
EIk = ( Ec Igk / 2.5 ) ; EIb = ( Ec Igb / 5 ) (kLu)^2
1 + ßd 1 + ßd
fc' = 210 kg/cm2
Ec = 15100* fc'^.5 = 218.82 ton/cm2

x - dir : z - dir :
Igk = 1/12 bh3 = 67500 cm4 Igk = 1/12 hb3 = 67500 cm4
Ec Igk = 1477.0 ton m2 Ec Igk = 1477.0 ton m2
EIk = 393.9 ton m2 EIk = 393.9 ton m2
Igb = 106667 cm4 Igb = 106667 cm4
Ec Igb = 2334.1 ton m2 Ec Igb = 2334.1 ton m2
EIb = 311.2 ton m2 EIb = 311.2 ton m2
lb = 6.0 m lb = 5.0 m

yA = 2.17 yA = 1.81
yB = 2.17 yB = 1.81
k= 1.6 ( from monogram ) k= 1.6 ( from monogram )
Check Eccentricity :

et = dMu / Pu = 444 mm
et min = ( 15 + 0.03 h ) = 24 mm

If et < et min , Mu should be taken from Pu . et min


COLUMN-TBL

COLUMN TABLE ( FOR UNBRACED FRAME ONLY )


SIZE Check of Slenderness Effects Moment magnification fa
MARK b h Dir Lu yA yB r øPc
k kLu/r Check Cm bd d
( cm ) ( cm ) ( cm ) TOP BOT ( cm ) ( ton )
X 16.00 10 2.20 17.32 44.46 To be considered 1 0.5 45.90 -0.777
C5 60 60 350
Z 14.81 10 2.15 17.32 43.45 To be considered 1 0.5 48.06 -0.844

NOTE :
y = S EIk / lk ; y = 0 ( fixed end ) ø= 0.7
S EIb / lb y= 10 ( column end supported on footing ) Pc = p2 EIk
EIk = ( Ec Igk / 2.5 ) ; EIb = ( Ec Igb / 5 ) (kLu)^2
1 + ßd 1 + ßd

fc' = 210 kg/cm2


Ec = 15100* fc'^.5 = 218.82 ton/cm2
x - dir : z - dir :
Igk = 1/12 bh3 = 1080000 cm4 Igk = 1/12 hb3 = 1080000 cm4
Ec Igk = 23632.5 ton m2 Ec Igk = 23632.5 ton m2
EIk = 6302.0 ton m2 EIk = 6302.0 ton m2
Igb = 208333 cm4 Igb = 208333 cm4
Ec Igb = 4558.7 ton m2 Ec Igb = 4558.7 ton m2
EIb = 607.8 ton m2 EIb = 607.8 ton m2
lb = 5.4 m lb = 5.0 m

yA = 16.00 yA = 14.81
yB = 10 yB = 10
k= 2.2 ( from monogram ) k= 2.15 ( from monogram )

Check Eccentricity :

et = dMu / Pu = -30 mm
et min = ( 15 + 0.03 h ) = 33 mm

If et < et min , Mu should be taken from Pu . et min


COLUMN-TBL

oment magnification factor


Pu Mu dMu
( ton ) (ton.m) (ton.m)
0.00 0.00
28.38
0.00 0.00

oment magnification factor


Pu Mu dMu
( ton ) (ton.m) (ton.m)
6.26 7.87
17.725
4.48 5.62
COLUMN-TBL

oment magnification factor


Pu Mu dMu
( ton ) (ton.m) (ton.m)
0.00 0.00
28.38
0.00 0.00

oment magnification factor


Pu Mu dMu
( ton ) (ton.m) (ton.m)
6.26 7.87
17.725
4.48 5.62
COLUMN-TBL

oment magnification factor


Pu Mu dMu
( ton ) (ton.m) (ton.m)
4.00 -3.11
105
10.80 -9.11
CONCRETE-COLUMN DESIGN
Material :
fc' = 210 kg/cm2
fy = 4000 kg/cm2

Longitudinal Reinforcement due to Bending Moment Tie due to Shear

Pu Pu et r Re-bar Min. Shear Actual Shear


MARK Ag Ast Ast.min Asto Design Shear 1/2øVc øVc Vc1 Vc2
Dir ø Agr.0.85fc' ø Agr.0.85fc' h (see table) r Arr. Reinf.spacing Stirrup Reinforcement
( cm2 ) ( cm2 ) ( cm2 ) ( cm2 ) n ( ton ) ( ton ) ( ton ) (ton) (ton) s ( mm ) (mm )

X
C1 900 0.27 0.00 0.022 0.0176 15.8 9.0 15.8 8 - D 16 Vu 1.300 3.666 7.332 7.332 14.545 D 10 @ 130 D 10 @ 125 Not Necessary
Z

NOTE :
d'/h = 0.17
d = 26
r = rb ; b= 0.8 :ø= 0.65
Ast = r Ag Actual Re-bar,
Ast min = 0.01 Ag Asto is Ast or Ast min whichever is larger

i) When Vu < 1/2 øVc , Not Necessary


ii) When øVc > Vu > 1/2 øVc , Min. is Required
iii) When Vu > ø Vc , To be Required
IV) Vs > 2.12√fc'bd Change Size !!!
Compute Shear Reinforcement
Vu < ø Vn = ø (Vc + Vs) ; ø = 0.85
Vc = 0.53 (1 + 0.0071 Pu/Ag) √fc' b d (kg)
whichever is smaller
or Vc = 0.93 √fc' b d √(1 + 0.029 Pu/Ag) (kg)

Vs = (Vu-Vc)/0.85 < 2.12√fc' bd

CONCRETE-COLUMN DESIGN
Material :
fc' = 210 kg/cm2
fy = 4000 kg/cm2

Longitudinal Reinforcement due to Bending Moment Tie due to Shear

MARK Pu Pu et r Re-bar Min. Shear Actual Shear


Ag Ast Ast.min Asto Design Shear 1/2øVc øVc Vc1 Vc2
Dir ø Agr.0.85fc' ø Agr.0.85fc' h (see table) r Arr. Reinf.spacing Stirrup Reinforcement
( cm2 ) ( cm2 ) ( cm2 ) ( cm2 ) n ( ton ) ( ton ) ( ton ) (ton) (ton) s ( mm ) (mm )

X
C2 900 0.17 0.14 0.016 0.0128 11.5 9.0 11.5 6 - D 16 Vu 2.040 3.414 6.828 6.828 13.176 D 10 @ 130 D 10 @ 125 Not Necessary
Z

NOTE :
d'/h = 0.17
d = 26
r = rb ; b= 0.8 : ø = 0.65
Ast = r Ag Actual Re-bar,
Ast min = 0.01 Ag Asto is Ast or Ast min whichever is larger

i) When Vu < 1/2 øVc , Not Necessary


ii) When øVc > Vu > 1/2 øVc , Min. is Required
iii) When Vu > ø Vc , To be Required
IV) Vs > 2.12√fc'bd Change Size !!!

Compute Shear Reinforcement

Vu < ø Vn = ø (Vc + Vs) ; ø = 0.85

Vc = 0.53 (1 + 0.0071 Pu/Ag) √fc' b d (kg)


whichever is smaller
or Vc = 0.93 √fc' b d √(1 + 0.029 Pu/Ag) (kg)
Vs = (Vu-Vc)/0.85 < 2.12√fc' bd
CONCRETE-COLUMN DESIGN
Material :
fc' = 210 kg/cm2
fy = 4000 kg/cm2

Longitudinal Reinforcement due to Bending Moment Tie due to Shear

MARK Pu Pu et r Re-bar Min. Shear Actual Shear


Ag Ast Ast.min Asto Design Shear 1/2øVc øVc Vc1 Vc2
Dir ø Agr.0.85fc' ø Agr.0.85fc' h (see table) r Arr. Reinf.spacing Stirrup Reinforcement
( cm2 ) ( cm2 ) ( cm2 ) ( cm2 ) n ( ton ) ( ton ) ( ton ) (ton) (ton) s ( mm ) (mm )

X
C3 900 0.27 0.22 0.016 0.0128 11.5 9.0 11.5 6 - D 16 Vu 2.040 3.666 7.332 7.332 10.512 D 10 @ 130 D 10 @ 125 Not Necessary
Z

NOTE :
d'/h = 0.17
d = 26
r = rb ; b= 0.8 :ø= 0.65
Ast = r Ag Actual Re-bar,
Ast min = 0.01 Ag Asto is Ast or Ast min whichever is larger

i) When Vu < 1/2 øVc , Not Necessary


ii) When øVc > Vu > 1/2 øVc , Min. is Required
iii) When Vu > ø Vc , To be Required
IV) Vs > 2.12√fc'bd Change Size !!!

Compute Shear Reinforcement

Vu < ø Vn = ø (Vc + Vs) ; ø = 0.85

Vc = 0.53 (1 + 0.0071 Pu/Ag) √fc' b d (kg)


whichever is smaller
or Vc = 0.93 √fc' b d √(1 + 0.029 Pu/Ag) (kg)

Vs = (Vu-Vc)/0.85 < 2.12√fc' bd

CONCRETE-COLUMN DESIGN
Material :
fc' = 210 kg/cm2
fy = 4000 kg/cm2

Longitudinal Reinforcement due to Bending Moment Tie due to Shear

MARK Pu Pu et r Re-bar Min. Shear Actual Shear


Ag Ast Ast.min Asto Design Shear 1/2øVc øVc Vc1 Vc2
Dir ø Agr.0.85fc' ø Agr.0.85fc' h (see table) r Arr. Reinf.spacing Stirrup Reinforcement
( cm2 ) ( cm2 ) ( cm2 ) ( cm2 ) n ( ton ) ( ton ) ( ton ) (ton) (ton) s ( mm ) (mm )

X
C4 900 0.17 0.14 0.016 0.0128 11.5 9.0 11.5 6 - D 16 Vu 2.040 3.414 6.828 6.828 13.176 D 10 @ 130 D 10 @ 125 Not Necessary
Z

NOTE :
d'/h = 0.17
d = 26
r = rb ; b= 0.8 :ø= 0.65
Ast = r Ag Actual Re-bar,
Ast min = 0.01 Ag Asto is Ast or Ast min whichever is larger

i) When Vu < 1/2 øVc , Not Necessary


ii) When øVc > Vu > 1/2 øVc , Min. is Required
iii) When Vu > ø Vc , To be Required
IV) Vs > 2.12√fc'bd Change Size !!!

Compute Shear Reinforcement

Vu < ø Vn = ø (Vc + Vs) ; ø = 0.85


Vc = 0.53 (1 + 0.0071 Pu/Ag) √fc' b d (kg)
whichever is smaller
or Vc = 0.93 √fc' b d √(1 + 0.029 Pu/Ag) (kg)
Vs = (Vu-Vc)/0.85 < 2.12√fc' bd
CONCRETE-COLUMN DESIGN
Material :
fc' = 210 kg/cm2
fy = 4000 kg/cm2

Longitudinal Reinforcement due to Bending Moment Tie due to Shear

MARK Pu Pu et r Re-bar Min. Shear Actual Shear


Ag Ast Ast.min Asto Design Shear 1/2øVc øVc Vc1 Vc2
Dir ø Agr.0.85fc' ø Agr.0.85fc' h (see table) r Arr. Reinf.spacing Stirrup Reinforcement
( cm2 ) ( cm2 ) ( cm2 ) ( cm2 ) n ( ton ) ( ton ) ( ton ) (ton) (ton) s ( mm ) (mm )

X
C5 3600 0.25 0.14 0.06 0.048 172.8 36.0 172.8 86 - D 16 Vu 2.040 15.575 31.150 31.150 61.522 D 10 @ 280 D 10 @ 125 Not Necessary
Z

NOTE :

d'/h = 0.08
d = 56
r = rb ; b= 0.8 :ø= 0.65
Ast = r Ag Actual Re-bar,
Ast min = 0.01 Ag Asto is Ast or Ast min whichever is larger

i) When Vu < 1/2 øVc , Not Necessary


ii) When øVc > Vu > 1/2 øVc , Min. is Required
iii) When Vu > ø Vc , To be Required
IV) Vs > 2.12√fc'bd Change Size !!!

Compute Shear Reinforcement

Vu < ø Vn = ø (Vc + Vs) ; ø = 0.85

Vc = 0.53 (1 + 0.0071 Pu/Ag) √fc' b d (kg)


whichever is smaller
or Vc = 0.93 √fc' b d √(1 + 0.029 Pu/Ag) (kg)

Vs = (Vu-Vc)/0.85 < 2.12√fc' bd


CONCRETE MEMBER SCHEDULLE
MARKS GB1 GB2 GB3 GB4
DIMENSION 400 x 200 500 x 200 500 x 200 250 x 150
BOTH END MIDDLE BOTH END MIDDLE BOTH END MIDDLE BOTH END MIDDLE

SECTION

TOP BAR 5 D16 2 D16 6 D16 2 D16 5 D20 2 D20 4 D16 2 D16
WEB BAR - - - - - - - -
BOTTOM BAR 3 D16 3 D16 3 D16 5 D16 2 D16 4 D16 2 D16 4 D16
STIRRUP D10 - 150 D10 - 150 D10 - 200 D10 - 200 D10 - 200 D10 - 200 D8 - 100 D8 - 100
CROSS BAR - - - - - - - -
MARKS GB5 B1 B2 B3
DIMENSION 400 x 200 400 x 200 300 x 200 450 x 200
BOTH END MIDDLE BOTH END MIDDLE BOTH END MIDDLE BOTH END MIDDLE

SECTION

TOP BAR 4 D16 2 D16 5 D16 2 D16 6 D16 4 D16 4 D16 4 D16
WEB BAR - - - - - - - -
BOTTOM BAR 2 D16 4 D16 3 D16 3 D16 3 D16 5 D16 2 D16 5 D16
STIRRUP D10 - 150 D10 - 150 D10 - 150 D10 - 175 D10 - 175 D10 - 200 D10 - 175 D10 - 200
CROSS BAR - - - - - - - -
MARKS B4
DIMENSION 300 x 150
BOTH END MIDDLE BOTH END MIDDLE BOTH END MIDDLE BOTH END MIDDLE

SECTION

TOP BAR 3 D16 2 D16 - - - - - -


WEB BAR - - - - - - - -
BOTTOM BAR 2 D16 3 D16 - - - - - -
STIRRUP D8 - 100 D8 - 125 - - - - - -
CROSS BAR - - - - - - - -
C1
300 x 300

8 D16
-
-
D10 - 125
-
Lintel Column
150 x 150

4 D10
-
-
D8 - 125
-
CONCRETE MEMBER SCHEDULLE
MARKS C1 C2 C3
DIMENSION 275 x 275 300 x 300 325 x 325

SECTION

TOP BAR 8 D16 12 D16 12 D16


WEB BAR - - -
BOTTOM BAR - - -
STIRRUP D10 - 150 D10 - 150 D10 - 175
CROSS BAR - - -
MARKS C4 C5 Lintel Column
DIMENSION 400 x 400 300 x 350 130 x 130

SECTION

TOP BAR 12 D16 6 D16 4 D10


WEB BAR - - -
BOTTOM BAR - - -
STIRRUP D10 - 125 D10 - 125 D8 - 125
CROSS BAR - - -